Fireman's Fund Insurance Company v. The United States

421 F.2d 706, 190 Ct. Cl. 804, 1970 U.S. Ct. Cl. LEXIS 115
CourtUnited States Court of Claims
DecidedFebruary 20, 1970
Docket377-66
StatusPublished
Cited by18 cases

This text of 421 F.2d 706 (Fireman's Fund Insurance Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fireman's Fund Insurance Company v. The United States, 421 F.2d 706, 190 Ct. Cl. 804, 1970 U.S. Ct. Cl. LEXIS 115 (cc 1970).

Opinion

ON DEFENDANT’S AND PLAINTIFF’S MOTIONS FOR SUMMARY JUDGMENT

COWEN, Chief Judge.

In August of 1958, Construction Management Corporation contracted with the United States through the Corps of Engineers for the modification of an existing power plant at Kindley Air Force Base in Bermuda at an adjusted contract price of $759,179.56. Plaintiff, a surety company, issued payment and performance bonds for the contract, pursuant to the Miller Act, 49 Stat. 793 (1935), as amended, 40 U.S.C. § 270a et seq. (1964). Plaintiff now seeks to recover from the Government a contract payment alleged to have been made improperly to Construction Management Corporation.

In connection with performance, the prime contractor entered into an agreement with English Electric Export and Trading Company, Ltd., for the supply of an engine and parts for a generator to be installed in the power plant at a total price of approximately $170,000. On January 26, 1960, English Electric notified plaintiff of Construction Management Corporation’s refusal to pay invoices totaling $168,345. A copy of this letter was sent to the Corps of Engineers in Jacksonville, Florida. On October 10, 1961, English Electric instituted an action in the United States District Court for the Southern District of New York, under the Miller Act, against the prime contractor and plaintiff surety for nonpayment.

The contractor satisfactorily completed the contract on November 4, 1960, at which time there were seven appeals by the contractor pending from decisions concerning disputes arising out of the contract. On April 16, 1962, the Corps of Engineers Board of Contract Appeals issued its decision on the contractor’s main appeal, involving a considerably larger amount than the total of the other six appeals. On the basis of the formula for settlement set forth in the Board’s decision, the contracting officer and the contractor negotiated a settlement of the disputes covered by the seven appeals. It was agreed that the contractor would-be paid a total of $78,100, subject to the qualifications (1) that the contracting officer’s agreement was subject to his obtaining the necessary funds to make the final payment, and (2) that the contractor’s agreement was subject to its receiving payment as soon as possible.

Since the applicable Armed Services Procurement Regulation contemplated that consent of the surety should be obtained to increase the penal amount of the payment bond protection when the contract price was increased by as much as $50,000, representatives of the contractor were requested to obtain such consent of the surety. Instead of requesting the surety to increase the amount of the payment bond protection, the contractor asked the surety to consent to the final payment under the contract to the contractor. The request was made on December 14, 1962. It was a condition of the payment bond that the contractor would pay promptly all bills incurred in connection with the performance of contract work, and suit had already been instituted against plaintiff and the contractor by English Electric for nonpayment. Consequently, plaintiff refused to consent to a direct payment to contractor of any further money due or to become due under the contract.

*708 Instead, plaintiff immediately wired the contracting officer on December 14, 1962, demanding that the final payment not be paid to the contractor but to plaintiff in order that the claim of English Electric could be satisfied, and the suit which it had filed under the terms of the bond could be settled. Nevertheless, the contracting officer, noting that the supplier’s claim represented an un-liquidated liability, issued Contract Modification No. 17 on December 21, 1962, in the amount of $78,100. The modification was accepted, the final payment of $78,100 was made to the contractor on the same day, and the contract was administratively closed.

The Miller Act suit by English Electric was settled by the payment of $182,250 by Fireman’s Fund Insurance Company, without contribution or reimbursement from Construction Management Corporation, on January 20, 1969. The contractor not only appeared in the suit to contest the right of English Electric to recover but filed a counterclaim against it. The litigation was protracted and was not concluded until settlement was reached in December 1968.

Plaintiff surety now seeks to recover the $78,100 which defendant paid to the contractor over the objection of plaintiff and after notice of the pending suit against plaintiff on the payment bond. Relying on this court’s decisions in Newark Ins. Co. v. United States, 169 F.Supp. 955, 144 Ct.Cl. 655 (1959), and Home Indem. Co. v. United States, 376 F.2d 890, 180 Ct.Cl. 173 (1967), among others, plaintiff maintains that, in light of the facts recited above, the Government became liable to it by making the final payment to the contractor. We agree.

We find no controlling distinctions between the facts in this case and those upon which our decision in Home Indem. Co. v. United States, supra, was based. The fact that the $78,100 was paid to the contractor as the result of a settlement, negotiated by adopting a formula set forth in the decision of the Corps of Engineers Board of Contract Appeals, does not alter the fact that it was a final payment under the contract. The payment was effected by a change order, which added that amount to the total estimated consideration of the contract in accordance with a practice frequently followed after a decision by a board of contract appeals. More than two years before the payment was made, the contracting officer had written notice that the contractor had failed to pay English Electric for material supplied as a part of the basic contract. By a telegram of December 14, 1962, and by letter of December 18, 1962, both of which were received by the contracting officer before the final payment to the contractor was made, the surety asserted its equitable rights to the fund, gave notice that English Electric had instituted suit against the contractor, and demanded that the contract balance be paid to the surety.

The failure of the contractor to pay for the material obtained from English Electric was a breach of the contract with the Government, because “the terms of the [payment] bond are read into the contract, and there is default under the contract where there is default under the bond.” Martin v. National Sur. Co., 300 U.S. 588, 598, 57 S.Ct. 531, 81 L.Ed. 822 (1937). As for the surety, it is clear that its rights of subrogation and property interest in the final contract payment exist when the surety is called upon to pay a material-man to the same extent as when it is required to complete the contract. Pearlman v. Reliance Ins. Co., 371 U.S. 132, 83 S.Ct. 232, 9 L.Ed.2d 190 (1962). As we noted in Home Indem. Co., 376 F.2d at 893, 180 Ct.Cl. at p. 177:

The defendant contends quite correctly that the surety’s right is only a potential one which does not become an actuality until the surety satisfies a debt of its principal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Travelers Indemnity Co. v. United States
72 Fed. Cl. 56 (Federal Claims, 2006)
Dunn & Black, P.S. v. United States
366 F. Supp. 2d 1008 (E.D. Washington, 2005)
Insurance Co. of the West v. United States
55 Fed. Cl. 529 (Federal Claims, 2003)
Fireman's Fund Insurance Company v. The United States
909 F.2d 495 (Federal Circuit, 1990)
District of Columbia v. Aetna Insurance
31 Cont. Cas. Fed. 71,231 (District of Columbia Court of Appeals, 1983)
Lambert v. Maryland Cas. Co.
403 So. 2d 739 (Louisiana Court of Appeal, 1981)
American Fidelity Fire Insurance v. United States
513 F.2d 1375 (Court of Claims, 1975)
Clincher v. United States
499 F.2d 1250 (Court of Claims, 1974)
Great American Insurance v. United States
492 F.2d 821 (Court of Claims, 1974)
Fireman's Fund Insurance Company v. United States
362 F. Supp. 842 (D. Kansas, 1973)
United States Fidelity & Guaranty Co. v. United States
475 F.2d 1377 (Court of Claims, 1973)
Argonaut Insurance Company v. United States
434 F.2d 1362 (Third Circuit, 1970)
Argonaut Insurance v. United States
434 F.2d 1362 (Court of Claims, 1970)
National Surety Corporation v. United States
319 F. Supp. 45 (N.D. Alabama, 1970)
Fireman's Fund Insurance v. United States
192 Ct. Cl. 951 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
421 F.2d 706, 190 Ct. Cl. 804, 1970 U.S. Ct. Cl. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/firemans-fund-insurance-company-v-the-united-states-cc-1970.