Central National Insurance Co. of Omaha v. Tri-County State Bank

823 F. Supp. 652, 1993 U.S. Dist. LEXIS 7505, 1993 WL 188445
CourtDistrict Court, D. Minnesota
DecidedJune 4, 1993
DocketCiv. 4-91-244
StatusPublished

This text of 823 F. Supp. 652 (Central National Insurance Co. of Omaha v. Tri-County State Bank) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central National Insurance Co. of Omaha v. Tri-County State Bank, 823 F. Supp. 652, 1993 U.S. Dist. LEXIS 7505, 1993 WL 188445 (mnd 1993).

Opinion

MEMORANDUM AND ORDER

MacLAUGHLIN, District Judge.

This matter is before the Court on cross-motions for summary judgment. Plaintiffs motion for summary judgment will be granted and defendant’s motion for summary judgment will be denied.

*654 FACTS

The facts in this case are no longer in dispute. 1 On May 3, 1985, the United States awarded a channel clearing and improvement project near Watson, Minnesota (Watson project) to Walter Ervin d/b/a Minnesota Drillers (Ervin). On August 16, 1985, the United States and Ervin entered into a contract for the Watson project in the amount of $439,851.00. On August 20, 1985, plaintiff Central National Insurance Company of Omaha (CNIC) issued performance and payment bonds for the project pursuant to the Miller Act, 40 U.S.C. §§ 270a et seq. The face amount of the performance bond was $439,851.00; the face amount of the payment bond was $219,925.50.

Defendant Tri-County State Bank (TriCounty) provided Ervin with financing for the Watson project. Because of this financing, on August 27, 1985, Ervin assigned his rights to progress payments due from the United States to Tri-County. On September 4, 1985, a representative of the United States acknowledged the assignment by letter receipt. However, Tri-County did not provide CNIC with notice of the assignment.

Following the assignment, the United States mailed each of the progress payments to Tri-County, in the form of checks payable to Tri-County alone. Tri-County credited the progress payments to Ervin’s account at Tri-County. Tri-County then deducted funds from Ervin’s account to reduce Ervin’s indebtedness to Tri-County.

CNIC first learned of the assignment to Tri-County on October 20, 1986, through a letter sent by an agent of the United States to an attorney for CNIC. At about the same time several of Ervin’s subcontractors and suppliers on the project filed actions against CNIC’s payment bond in the United States District Court for the District of Minnesota. Effective October 22, 1986, Ervin entered into an agreement with CNIC under which Ervin assigned to CNIC all moneys due from the United States in connection with the project toward satisfaction of the bond claims. However, it was not until December 15, 1986, that Tri-County executed a release of its assignment.

On January 12,1987, CNIC commenced an interpleader action in the District of Minnesota. CNIC deposited the full amount of the payment bond ($219,925.50) into the court. The individual bond claim actions and the interpleader action were consolidated into one lawsuit, and on January 26, 1988, the court entered an order for judgment under which the $219,925.50 bond amount was divided among the various bond claimants in proportion to the amounts of their respective claims.

On October 18, 1988, the United States made a final payment to Tri-County in the amount of $13,618.33. However, that payment was erroneously made because TriCounty had released its assignment on December 15, 1986. The United States discovered the mistake and on July 27, 1989, made a written request to Tri-County for the return of the $13,618.33. Tri-County did not comply with that request. In the meantime, on April 22, 1988, pursuant to the agreement under which Ervin assigned his claims against the United States to CNIC, CNIC commenced an action against the United States in the United States Court of Claims to recover for work Ervin performed on the project for which payment had not been made. In October 1990, the Claims Court entered a stipulated judgment in accord with which the United States paid CNIC $85,-000.00, and assigned to CNIC any claim that the United States had to recover the final payment of $13,618.33 mistakenly paid to Tri-County.

On April 1, 1991, CNIC commenced the instant action against Tri-County, seeking (1) recovery of the $13,618.33 final payment pursuant to the assignment of that claim by the United States, and (2) recovery of various other progress payments on equitable grounds. CNIC concedes that the majority of the assigned progress payments made to Tri-County were applied to repay loans which financed the Watson project. There *655 was a dispute, however, over $95,554.31 which CNIC claimed was used by Tri-County to repay loans which were unrelated to the Watson project. The parties agreed to hold a trial on this issue before the United States Magistrate Judge. The Magistrate Judge found that $95,554.31 was used by Tri-County to repay loans unrelated to the Watson project. That amount includes the $13,-618.33 mistakenly paid to Tri-County after it had released its assignment.

The parties have now filed cross-motions for summary judgment. CNIC seeks an entry of judgment in the amount of $95,554.31 on the basis of the Magistrate Judge’s finding that $95,554.31 was applied to loans unrelated to the Watson project and thus increased CNIC’s exposure on the payment bond. Tri-County requests an order stating that it is not liable to CNIC for any amount.

DISCUSSION

A movant is not entitled to summary judgment unless the movant can show that no genuine issue exists as to any material fact. Fed.R.Civ.P. 56(c). In considering a summary judgment motion, a court must determine whether “there are any genuine factual issues that properly can be resolved only by a finder of fact because they may reasonably be resolved in favor of either party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 250, 106 S.Ct. 2505, 2511, 91 L.Ed.2d 202 (1986). The role of a court is not to weigh the evidence but instead to determine whether, as a matter of law, a genuine factual conflict exists. AgriStor Leasing v. Farrow, 826 F.2d 732, 734 (8th Cir.1987). “In making this determination, the court is required to view the evidence in the light most favorable to the nonmoving party and to give that party the benefit of all reasonable inferences to be drawn from the facts.” AgriStor Leasing, 826 F.2d at 734. When a motion for summary judgment is properly made and supported with affidavits or other evidence as provided in Fed.R.Civ.P. 56(c), then the nonmoving party may not merely rest upon the allegations or denials of the party’s pleading, but must set forth specific facts, by affidavits or otherwise, showing that there is a genuine issue for trial. Lomar Wholesale Grocery, Inc. v. Dieter’s Gourmet Foods, Inc., 824 F.2d 582, 585 (8th Cir.1987), cert. denied, 484 U.S. 1010, 108 S.Ct. 707, 98 L.Ed.2d 658 (1988). Moreover, summary judgment must be entered against a party who fails to make a showing sufficient to establish the existence of an element essential to that party’s case, and on which that party will bear the burden of proof at trial. Celotex Corp. v. Catrett,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Wurts
303 U.S. 414 (Supreme Court, 1938)
Gardner v. Panama Railroad
342 U.S. 29 (Supreme Court, 1951)
Costello v. United States
365 U.S. 265 (Supreme Court, 1961)
Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Great American Insurance v. United States
492 F.2d 821 (Court of Claims, 1974)
First National City Bank v. United States
548 F.2d 928 (Court of Claims, 1977)
AgriStor Leasing v. Farrow
826 F.2d 732 (Eighth Circuit, 1987)
Lindsay v. City of San Antonio
484 U.S. 1010 (Supreme Court, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
823 F. Supp. 652, 1993 U.S. Dist. LEXIS 7505, 1993 WL 188445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-national-insurance-co-of-omaha-v-tri-county-state-bank-mnd-1993.