Employers Insurance of Wausau v. Town of Northbourough

11 Mass. L. Rptr. 280
CourtMassachusetts Superior Court
DecidedJanuary 14, 2000
DocketNo. 991308
StatusPublished

This text of 11 Mass. L. Rptr. 280 (Employers Insurance of Wausau v. Town of Northbourough) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Employers Insurance of Wausau v. Town of Northbourough, 11 Mass. L. Rptr. 280 (Mass. Ct. App. 2000).

Opinion

Gershengorn, J.

This is an action in which the plaintiff, Employers Insurance of Wausau, a Mutual Company (“Wausau”), surety to a contract between the defendant, Town of Northborough (“the Town”) and another, claims entitlement to funds allegedly owed by the defendant under the contract. Among the other allegations in the complaint, the plaintiff alleges that the doctrine of equitable subrogation entitles the plaintiff, as surety, to priority reimbursement for amounts it has paid out, in preference to any rights the Town may have in the funds. With respect to this claim, the plaintiff has filed a motion for summary judgment on the issue of liability, pursuant to Mass.R.Civ.R 56(c). For the reasons stated below, the motion of the plaintiff is DENIED.

FACTS1

In early November 1997, the Town and The February Corporation, d/b/a Charlesgate Construction Company (“Charlesgate"), entered into a contract (“the contract”) for renovation of the Zeh Elementary School in Northborough, Massachusetts. The Town appropriated funds for the contract. Pursuant to statute, the Town required that Charlesgate obtain and deliver to the Town two separate bonds, a performance bond and [281]*281a payment bond, to guarantee completion of the contract and payment of labor and materialmen. Wausau issued the two required bonds, and the bonds were delivered to the Town by Charlesgate. Construction followed from November 7, 1997, until mid-October, 1998, when Charlesgate left the job, and the Town occupied the school building.

On August 26, 1998, Charlesgate submitted a tenth Application for Payment to the Town, totalling $294,488.21.2 procedure was the same procedure Charlesgate had followed in the submission of its previous nine applications for payment. The Town’s architect reviewed the requisition and put it aside. The Town has occupied and been working on the Zeh school since October 1998.

On September 15, 1998, the Town determined that Charlesgate was in default in its performance of the contract. Nevertheless, the Town chose not to make a claim under the performance bond issued by Wausau. From September 10, 1998, through October 14, 1998, several subcontractors filed direct claims against the Town pursuant to G.L.c. 30, §39F, alleging that Charlesgate failed to pay them. The Town has not paid any of the subcontractors. Subcontractors and material suppliers have, in turn, made claim against the payment bond provided by Wausau. As of April 16, 1999, Wausau had paid $848,147.19 to subcontractors and suppliers under the payment bond.

On September 24, 1998, Charlesgate assigned to Wausau all of its rights to any contract balances due to be paid by the Town. Upon learning that the Town was waiving its right to have Wausau complete the project under the performance bond, but was looking to Wausau to perform under the payment bond, Wau-sau demanded payment by the Town of any remaining contract balances. The Town refused to pay.

The difference between the original contract amount and the amount paid to Charlesgate is approximately $640,000.3 The Town claims that it is entitled to use this money to pay for the completion of the contract, plus any damages caused by Charlesgate’s breach of the contract.4 Wausau claims that its performance under the payment bond and the doctrine of equitable subrogation entitle it to preferential payment from this money before the Town deducts any amounts.

DISCUSSION

Summary judgment may be appropriate where, as here, all material facts are undisputed. Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). The parties do not dispute that if Charlesgate had completed the project per the terms of the contract, the Town would be obligated to pay the money to Charlesgate. It also appears undisputed that if Wau-sau had been required to complete the project under the performance bond, then the doctrine of equitable subrogation would entitle it to the funds. See generally Prairie State Bank v. United States, 164 U.S. 227 (1896). Finally, the parties agree that had Charlesgate completed the project and Wausau performed under the payment bond, then Wausau would be subrogated to Charlesgate’s position and would therefore be entitled to the money. See generally Henningsen v. United States Fid. & Guar. Co., 208 U.S. 404 (1908). The uniqueness of the situation here lies in the fact that Charlesgate did not complete the project per the terms of the contract. Wausau performed under the payment contract, but Wausau was not called upon to perform under the performance bond. No case, apparently, has touched upon such a situation.

If Wausau were not implicated by performance under one of the bonds, then the Town would be entitled to deduct its damages from the amounts otherwise payable to Charlesgate under the contract. United States v. Munsa Trust Co., 332 U.S. 234, 239 (1947); Superior Glass Co., Inc. v. First Bristol Co. Nat. Bk., 380 Mass. 829, 833 (1980). Wausau contends that because it had to perform under the payment bond, the doctrine of equitable subrogation entitles it to the funds held by the Town in preference to the Town’s deduction of damages. This argument falls.

“Subrogation is an old term, rooted in equity, and semantically stemming from words meaning ‘ask under.’ ’’ National Shawmut Bk. of Boston v. New Amsterdam Gas Co., 411 F. 2d 843, 844 (1 st Cir. 1969) (applying Massachusetts law). The equitable principle is that when, pursuant to an obligation, one fulfills the duties of another, he is entitled to “step in the shoes” of and assert the rights of that other against third persons. Id. Thus, a surety who pays the debt of another is entitled to all the rights of the person he paid to enforce his right to be reimbursed by a third party. Pearlman v. Reliance Ins. Co., 371 U.S. 132, 137 (1962). It has been held that when a surety “pays all the bills of the job to date and completes the job, it stands in the shoes of the contractor insofar as there are receivables due it; in the shoes of laborers and materialmen who have been paid by the surety — who may have had liens; and, not least, in the shoes of the government, for whom the job was completed.”5 Wausau relies on this principle, together with the rule that the doctrine of equitable subrogation applies whether the surety performs under either the payment bond or the performance bond, to argue that it, as surety, succeeds to a preferential interest in the funds.6 The flaw in this argument is exposed by an examination of the right, or rights, that the contractor, laborers and materialmen, and government have in a case such as this.

It is clear that when a surety pays under either a payment or a performance bond, the surety becomes subrogated to the rights of the contractor. Where the contractor has not completed performance under the contract, however, the contractor does not, by statute, have the right to be paid out of funds needed to pay for completion of the contract. G.L.c. 30, §39K. To the [282]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
11 Mass. L. Rptr. 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/employers-insurance-of-wausau-v-town-of-northbourough-masssuperct-2000.