United States v. Continental Casualty Company

346 F. Supp. 1239, 1972 U.S. Dist. LEXIS 12123
CourtDistrict Court, N.D. Illinois
DecidedSeptember 1, 1972
Docket69 C 2534
StatusPublished
Cited by8 cases

This text of 346 F. Supp. 1239 (United States v. Continental Casualty Company) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Continental Casualty Company, 346 F. Supp. 1239, 1972 U.S. Dist. LEXIS 12123 (N.D. Ill. 1972).

Opinion

MEMORANDUM OF DECISION

TONE, District Judge.

This is an action by the United States to enforce a Miller Act performance bond against the defendant surety on a construction contract for modification of a spillway of the Granby Dam in Colorado, upon the default by the contractor and the completion of work by the Government at an excess replacement cost of $76,261.92. The defendant claims in two separate defenses that it is entitled to a set-off of $78,199.10. Of this amount, $71,207.50 was a monthly earned progress payment which the Government paid to the contractor’s assignee several months before the formal default and termination of the contract but only a few days after the Government had notice that the contractor was in financial difficulty; and $6,991.60 was a payment of amounts the Goovernment had retained from prior progress payments which it released on the basis of the contracting officer’s finding that progress in performance was satisfactory. The issue is whether the Government was under a duty to withhold these payments by reason of the notice received from the surety.

Both parties have moved for summary judgment. It does not follow from this alone that the case should be decided by summary judgment (6 Moore’s Federal Practice, ¶ 56.13 (2d ed. 1971), but here it appears to be conceded on both sides that there is no issue as to any material fact, and summary judgment is therefore appropriate. While the facts are undisputed, the inferences and conclusions the court is asked to draw from them are not. A rather full explication of the circumstances is therefore warranted.

The contract was awarded by the Interior Department’s Bureau of Reclamation to Gardner Construction Company on June 16, 1964, all work to be completed by May 20, 1965. The estimated contract price was $464,625, and the defendant surety issued its performance and payment bonds, each for approximately half of the contract price. Shortly thereafter, Gardner assigned all monies due him to a Colorado bank. Work proceeded satisfactorily through the summer and fall of 1964. By the end of November, 80 per cent of the work had been performed to the Government’s satisfaction, on or ahead of schedule.

On November 24, the contractor advised its creditors (but not its surety or the Government) by letter that it was ceasing operations and shutting down all jobs immediately, and requesting their presence at a meeting on December 2 to discuss the company’s problems. The letter suggested that the company would be liquidated. The Granby Dam job in question here was shut down the next day. The Bureau official at the job site was told only that there would be no more work until November 30 or perhaps December 7. On November 30, the same official learned that the contractor was having “a meeting” on December 2, after which more news would be forthcoming.

The circumstances surrounding the shutdown are complicated by three simultaneous events, viz., the arrival of the Thanksgiving Holiday, the onset of increasingly severe winter weather con *1241 ditions at the job site, and the surfacing of Gardner’s financial difficulties. Normal weather conditions at the mountainous site did not permit work beyond mid-November without special “winterizing procedures.” Although there is some evidence that the Government expected some work to continue through the winter, the shutdown in late November was considered by the Bureau’s engineers at the job site to be reasonable and no cause for alarm.

During the next two weeks, from December 2, until December 15- the same period in which the voucher for the November progress payment in question was being processed through the various levels of Government officialdom—both the defendant surety and the various Government officials involved received confusing and contradictory information about the financial condition of the contractor and his ability and intention to complete the job. On December 3, the defendant received a copy of the contractor’s first letter to creditors of November 24 warning of liquidation. On December 4, after an apparently successful meeting of those creditors, the defendant received another communication from the contractor indicating that it was not the contractor’s intention to liquidate, that its jobs were shut down because of weather conditions only, and that it intended to complete all its jobs in the spring.

Similarly, the Government officials involved were hearing discordant themes from and about the contractor. On December 3, the resident engineer at the job site was informed that two material-men had unpaid claims against the contractor. At the same time he discovered that the December 2 meeting had been a meeting of creditors and that the contractor was in financial difficulty and might have to sell some of its equipment. The next day he was told by the contractor’s superintendent that the contractor’s winter plans were indefinite but that it expected to begin work again on the job in April or May of 1965. In the next few days, the job site was prepared for a winter shutdown, but not a permanent cessation of operations. On December 7, the resident engineer received a copy of the contractor’s second communication to its creditors, affirming that it was the intention of the contractor to complete its jobs, and characterizing its difficulties as “a temporary financial bind.”

On December 10, the Bureau’s contracting officer in Denver, the official in charge of the project and the only official with the authority to stop payment on a voucher or to declare a contractor in default, received a letter from the defendant surety enclosing a copy of the contractor’s first letter to creditors (suggesting liquidation) and stating as follows:

“Subsequent to the date of that letter, we have received correspondence from Gardner Construction Company refuting in part and supporting in part their November 24th letter. We are requesting further information from Gardner Construction Company in an effort to resolve the confusion regarding Gardner’s intentions. Any information you may be able to furnish us regarding this matter will be appreciated.
“In the meantime, it is our position that all monies payable under this contract should be devoted first to the performance of the contract and the discharge of obligations incurred therein.
“We therefore request that you make no further payments under this contract without first consulting and conferring with us.” 1

This letter was the first information the contracting officer had that Gardner *1242 was having financial difficulty. The information which the resident engineer at the job site had received had been relayed by him to the Bureau’s Project Office at Loveland, Colorado, which exercised more immediate supervision of the project than the contracting officer. That office had not passed that information on to the contracting officer by December 10. On December 8, the day after the resident engineer had received a copy of Gardner’s second, more optimistic, letter to its creditors, the Project Office concurred in Gardner’s winter shutdown, and engaged in negotiations with Gardner for a revised spring schedule for completion of the work. The Project Office’s report of the shutdown reached the Denver office on December 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
346 F. Supp. 1239, 1972 U.S. Dist. LEXIS 12123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-continental-casualty-company-ilnd-1972.