Emulsicoat, Inc. v. City of Hoopeston

425 N.E.2d 1349, 99 Ill. App. 3d 835, 55 Ill. Dec. 176, 1981 Ill. App. LEXIS 3230
CourtAppellate Court of Illinois
DecidedSeptember 3, 1981
Docket16962
StatusPublished
Cited by19 cases

This text of 425 N.E.2d 1349 (Emulsicoat, Inc. v. City of Hoopeston) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Emulsicoat, Inc. v. City of Hoopeston, 425 N.E.2d 1349, 99 Ill. App. 3d 835, 55 Ill. Dec. 176, 1981 Ill. App. LEXIS 3230 (Ill. Ct. App. 1981).

Opinion

Mr. JUSTICE WEBBER

delivered the opinion of the court:

This appeal presents questions of statutory construction relating to portions of “An Act in relation to bonds of contractors entering into contracts for public construction” (Ill. Rev. Stat. 1979, ch. 29, pars. 15, 16) (Bond Act), and to portions of the Local Governmental and Governmental Employees Tort Immunity Act (Ill. Rev. Stat. 1979, ch. 85, pars. 1 — 101 et seq.) (Immunity Act).

Defendants City of Hoopeston and Village of Rossville entered into contracts for public improvements with Tom’s Equipment Company. Plaintiff was a subcontractor pf Tom’s Equipment and furnished materials for the jobs. It was alleged that defendant Kenneth Collins was comptroller of the City of Hoopeston and had general control over all municipal officers. A similar allegation concerning defendant Joyce Redden was that she was the village clerk of Rossville and had general control over the other municipal officers.

Further allegations in plaintiff’s complaint were that Tom’s Equipment had failed to pay plaintiff for the materials furnished by it, even though that claim had been reduced to judgment in another proceeding; that the defendants had failed, or neglected, to obtain the contractor’s bond required by section 1 of the Bond Act (Ill. Rev. Stat. 1979, ch. 29, par. 15); that plaintiff had served proper notice as required by section 2 of the Bond Act (Ill. Rev. Stat. 1979, ch. 29, par. 16) but that all funds had been paid out prior to that time; and that plaintiff had been damaged to the extent of its unpaid claim.

It can thus be seen that plaintiff’s complaint sounds in ordinary negligence, and so far as we can determine, presents a question of first impression under the Bond Act.

The circuit court of Vermilion County, after briefing and argument by the parties, entered separate orders of dismissal as to all defendants. The court indicated that it was basing its order on the wording of the Bond Act itself and the analogy found in Gunther v. O’Brien Brothers Construction Co. (1938), 369 Ill. 362, 16 N.E.2d 890.

We affirm.

Since the bases of our decision depend on different statutes and different theories, we will discuss the claim versus the municipalities and the claim versus their respective officers separately; first, as to the municipalities. Section 1 of the Bond Act provides:

“All officials, boards, commissions or agents of this State, or of any political subdivision thereof in making contracts for public work of any kind to be performed for the State, or a political subdivision thereof shall require every contractor for such work to furnish, supply and deliver a bond to the State, or to the political subdivision thereof entering into such contract, as the case may be, with good and sufficient sureties. The amount of such bond shall be fixed by such officials, boards, commissions, commissioners or agents, and such bond, among other conditions, shall be conditioned for the completion of the contract, for the payment of material used in such work and for all labor performed in such work, whether by subcontractor or otherwise.” Ill. Rev. Stat. 1979, ch. 29, par. 15.

Section 2 of the Bond Act provides:

“Every person furnishing material or performing labor, either as an individual or as a sub-contractor for any contractor, with the State, or a political subdivision thereof where bond shall be executed as provided in this Act, shall have the right to sue on such bond in the name of the State, or the political subdivision thereof entering into such contract, as the case may be, for his use and benefit, and in such suit the plaintiff shall file a copy of such bond, certified by the party or parties in whose charge such bond shall be, which copy shall, unless execution thereof be denied under oath, be prima facie evidence of the execution and delivery of the original; provided, however, that this Act shall not be taken to in any way make the State, or the political subdivision thereof entering into such contract, as the case may be, liable to such sub-contractor, materialman or laborer to any greater extent than it was liable under the law as it stood before the adoption of this Act.” Ill. Rev. Stat. 1979, ch. 29, par. 16.

The critical language is the proviso in section 2: “* * ” provided, however, that this Act shall not be taken to in any way make the State, or the political subdivision thereof entering into such contract, as the case may be, liable to such subcontractor, materialman or laborer to any greater extent than it was liable under the law as it stood before the adoption of this Act.” The Act was adopted in 1931.

Plaintiff places a narrow construction on the proviso, arguing that it relates only to the language immediately preceding it, which deals with the right of the contractor to bring a suit in the name of the municipality, that it limits recovery to the extent of the bond and thus becomes operative only when there is a bond. Therefore, he deduces, there is no limit on liability when there is no bond. We cannot agree.

If the municipality did obtain a bond, there could be no liability on it for failure to do so, and section 1 of the Act requires a sufficient bond for completion of the work. It therefore follows that the proviso must be to limit whatever liability might arise from failure to require the bond. The proviso states that the “* * ° Act shall not be taken to in any way make * * * the political subdivision * * * liable ” ” ” to any greater extent * 9 9’ (Emphasis added.) By its own terms it is not limited to the presence of a bond.

In our judgment, the proviso represents a very cautious approach by the legislature to the question of tort immunity of municipalities. This had existed from the time of Town of Waltham v. Kemper (1870), 55 Ill. 346, some 60 years before the passage of the Bond Act, and continued until Molitor v. Kaneland Community Unit District No. 302 (1959), 18 Ill. 2d 11, 163 N.E.2d 89, almost 30 years after the Bond Act was passed. It seems clear to us that by adding a new remedy for unpaid contractors the legislature was taking meticulous care to see that the traditional immunity was not infringed in 1931, or thereafter.

Plaintiff further argues that Molitor abrogated municipal immunity and that various sections of the Immunity Act must be considered. Again, we disagree, and insofar as the municipalities are concerned, we find the Immunity Act irrelevant.

The Immunity Act is a general statute dealing with many general potential liabilities; the Bond Act is a specific statute dealing with a specific liability. It is a cardinal rule of statutory construction that a specific statute will control over a general one. (2A Sutherland, Statutory Construction §§51.01, 51.05 (3d ed. 1973).) The Immunity Act was passed in 1965, and although a variety of other statutes were repealed by it (Ill. Rev. Stat. 1967, ch. 83, par. 10 — 101), the Bond Act was left untouched.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Imperial Manufacturing Ice Cold Coolers, Inc. v. Shannon
101 P.3d 627 (Alaska Supreme Court, 2004)
Carter v. Du Page County Sheriff
Appellate Court of Illinois, 1999
Bradshaw v. City of Metropolis
688 N.E.2d 332 (Appellate Court of Illinois, 1998)
Tosado v. Miller
293 Ill. App. 3d 544 (Appellate Court of Illinois, 1997)
Cleaver v. Marrese
625 N.E.2d 1129 (Appellate Court of Illinois, 1993)
Glenn v. City of Chicago
628 N.E.2d 844 (Appellate Court of Illinois, 1993)
Hernon v. E.W. Corrigan Construction Co.
149 Ill. 2d 190 (Illinois Supreme Court, 1992)
Hernon v. EW Corrigan Const. Co.
595 N.E.2d 561 (Illinois Supreme Court, 1992)
BYRBE v. City of Chicago
576 N.E.2d 19 (Appellate Court of Illinois, 1991)
Flowers v. City of Harvey
739 F. Supp. 1148 (N.D. Illinois, 1990)
People v. Sass
494 N.E.2d 745 (Appellate Court of Illinois, 1986)
Homes v. State
37 Ill. Ct. Cl. 190 (Court of Claims of Illinois, 1984)
Marley v. Palmyra Bor.
473 A.2d 554 (New Jersey Superior Court App Division, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
425 N.E.2d 1349, 99 Ill. App. 3d 835, 55 Ill. Dec. 176, 1981 Ill. App. LEXIS 3230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/emulsicoat-inc-v-city-of-hoopeston-illappct-1981.