Imperial Manufacturing Ice Cold Coolers, Inc. v. Shannon
Opinion
OPINION
I. INTRODUCTION
A subcontractor asks this court to hold that the Little Miller Act provides it with a private right of action through which it can sue a school district for failing to ensure that the bonding requirements of the act were met. Because we can find no indication that the legislature intended to impose such liability on public entities, we affirm the superior court's decision.
II. FACTS AND PROCEEDINGS
The Lower Kuskokwim School District contracted with Clifton Shannon, d/b/a Arctic Construction Enterprises, to deliver, assemble, and install two two-bedroom panel houses in Tooksook Bay and Kwillingok. The contract acknowledged that Shannon had provided no bonding under the Little Miller Act, AS 36.25.010.1 Shannon purchased the house packages from Imperial Manufacturing Iee Cold Coolers, Inc., and Imperial delivered them to the villages. Shannon did not pay Imperial.
Imperial sued, among others, the school district on the theory that the school district had failed to require that Shannon obtain a payment bond and thereby had breached duties owed to Imperial. On cross-motions for summary judgment, the superior court granted the school district's motion and ruled that AS 36.25.010 does not provide a private cause of action against a political subdivision. As this is the ruling that is challenged on appeal, we assume for present purposes that AS 36.25.010 applied to the contract.2 A Civil Rule 54(b) partial final judgment was entered from which Imperial appeals.
III. DISCUSSION
Alaska Statute 36.25.010 requires contractors who are awarded public construction contracts to furnish payment bonds for the protection of those who supply labor and materials. The remedy of a supplier who is not paid is set forth in AS 36.25.020. Under this section the supplier may sue on the bond in the name of the political subdivision for [629] the use of the claimant.3 Alaska Statute 36.05.085(2), a section of the Little Davis Bacon Act concerning wages and hours of labor on public construction projects, provides that political subdivisions shall verify that the bonding requirements of AS 836.25 have been met.4
Imperial argues on appeal that AS 36.25.010 should be construed to provide an implied private right of action in favor of an unpaid supplier against a political subdivision that fails to require a contractor to purchase a payment bond. It also contends that the duty expressed in AS 36.05.0385 to verify whether bonding requirements have been met should be enforceable by a civil claim brought by a party in its position. The school district argues that no right of action against a political subdivision by entities with which it has no contractual relationship is expressed either in the Little Miller Act or in AS 86.05.0385, and that none is implied.
Subcontractors and suppliers cannot lien public projects.5 They thus would be dependent on the financial solvency of prime contractors and might be reluctant to supply labor or material to public projects were there not an alternative remedy. The Little Miller Act was designed to address these problems.
The purpose of the statute is:
to protect persons who furnish labor or material for a state public works project from the risks of nonpayment. In exchange for providing such protection the state is assured that material and labor will be readily furnished for its projects. Persons who furnish labor and material for the state's projects do so in reliance on the existence of a valid payment bond.Footnotes
101 P.3d 627 (Imperial Manufacturing Ice Cold Coolers, Inc. v. Shannon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Ask about Imperial Manufacturing Ice Cold Coolers, Inc. v. Shannon — and the 3 cases citing it.
Two-minute setup · Revoke anytime