State Ex Rel. Palmer Supply Co. v. Walsh & Co.

575 P.2d 1213
CourtAlaska Supreme Court
DecidedMarch 16, 1978
Docket2816
StatusPublished
Cited by9 cases

This text of 575 P.2d 1213 (State Ex Rel. Palmer Supply Co. v. Walsh & Co.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
State Ex Rel. Palmer Supply Co. v. Walsh & Co., 575 P.2d 1213 (Ala. 1978).

Opinion

OPINION

Before BOOCHEVER, C. J., and RABI-NOWITZ, CONNOR, and BURKE, JJ. DIMOND, J. Pro Tem.

*1216 CONNOR, Justice.

This appeal arises from a claim filed pursuant to Alaska’s “Little Miller Act.” 1 See AS 36.25.010 et seq.

On August 14, 1970, Walsh & Company, Inc. (Walsh), contracted with the State of Alaska, Department of Public Works, to construct the Bethel Regional High School. General Insurance Company of America was the surety on this contract. Walsh entered into a subcontract with Hohn Corporation (Hohn) to perform a portion of the state job. Palmer Supply Corporation (Palmer) supplied materials to Hohn which were used in the Bethel project. Hohn was not bonded and at the time of the judgment below was operating under Chapter XI of the Bankruptcy Act.

Alleging that it had not been paid for a substantial portion of the materials it had furnished to Hohn for the Bethel job, Palmer brought suit pursuant to AS 36.25.020 on the payment bond furnished to Walsh by General Insurance Company. Walsh im-pleaded Hohn and defended on the ground that Palmer had been paid by a check in the amount of $54,002.12, drawn by Hohn on July 19, 1971, from funds received from Walsh, for the supplies which Palmer had furnished.

After a non-jury trial, the court entered judgment against Palmer ruling that Palmer was not entitled to any payment on its claim. Hohn then filed a motion for attorney’s fees which were awarded in the amount of $8,000.00. This appeal follows.

The parties do not agree on the statement of issues. We believe they can fairly be stated as follows:

1. Whether the court erred in finding that Palmer knew that Walsh was the source of the $54,002.12 payment;
2. Whether the court erred in finding that the purported Hohn-Palmer agreement did not permit the application of the $54,002.12 to Hohn’s oldest outstanding accounts;
3. Whether Hohn was bound by principles of ratification, waiver or estoppel to Palmer’s application of the funds to Hohn’s other accounts;
4. Whether the court erred in concluding that Palmer was not entitled to any lien at all against Walsh;
5. Whether the court erred in ruling that Hohn was the prevailing party and, therefore, entitled to attorney’s fees;
6. Whether the court erred in failing to grant Palmer’s motion for a new trial.

The following is a discussion of the basic facts.

In 1969, Hohn owed Palmer approximately $480,000.00 for material it had purchased and used in various building projects. Many of Hohn’s accounts had been out *1217 standing for more than 90 days. This situation concerned Palmer, which could only obtain financing for receivables less than 60 days old. Top executives from both companies met on several occasions in 1969 to discuss how Hohn could reduce its outstanding balance. An understanding was reached that Hohn would make several large payments to Palmer. The details of this understanding or agreement were in dispute at the trial. According to Palmer, the companies agreed that funds would be applied only to the oldest accounts unless the amount received was less than $1,000 or a joint check was issued. Hohn denied that there was any such agreement and maintained there was nothing more than a general understanding that payments would be applied to the oldest accounts first.

On July 19,1971, Hohn issued check number 363 for $54,002.12 to Palmer. At that time, Walsh was concerned that its suppliers were not being paid and instructed Hohn to make sure that the $54,002.12 check was applied specifically to pay for materials used on the Bethel job. Accordingly, the skirt of Hohn’s check for $54,-002.12 carried the following notation:

“Pay on Account
Bethel High School Project 21011-01 $54,002.12.”

Palmer disregarded the notation, applying most of the funds to Hohn’s other accounts and only $6,574.17 to bills arising out of the Bethel project. Palmer contended that the notation on Hohn’s check was meaningless, and that in light of Palmer’s agreement with Hohn, it should have applied the check only to Hohn’s oldest accounts. Hohn contended that the notation was an explicit instruction to Palmer to apply the funds to the Bethel account and that Palmer ignored these instructions. 2 Hohn also introduced evidence to show that despite the purported agreement, in five of seven cases in which checks were issued with similar notations, Palmer did in fact apply the funds according to the notations. 3

I

Appellant claims that the trial court erred in not finding that the Palmer-Hohn agreement permitted Palmer’s application of the $54,002.12 payment to Hohn’s other accounts. Palmer argues that the purported agreement stripped Hohn of the right to direct to which accounts payments were to be applied and that, even if Palmer had known Walsh to be the source of the funds, this knowledge did not create a duty to apply the payment for the benefit of the source.

The trial court found that Palmer and Hohn had had an agreement under which Palmer could apply payments in an attempt to prevent Hohn’s accounts from becoming more than 90 days old. Palmer does not quarrel with the trial court’s characterization of the terms of the agreement, but disagrees with the trial court’s conclusion of law that the agreement was not controlling under the facts of this case.

Palmer relies primarily upon Ott v. Bray, 114 Fla. 547, 154 So. 209 (1934), in support of its position that although Hohn may have originally had the right to designate the account to which payment should be applied, that right was relinquished by virtue of the Hohn-Palmer agreement. Ott concerned an agreement between a mortgagor and a mortgagee to extend a mortgage. As additional collateral for the mortgage extension, a judgment was assigned to the mortgagee. Any sums collected from that judgment were to be applied to reduce the *1218 mortgage, but the mortgagee failed to do so. The court held that the usual rule that a contract fixing the mode of application controls funds received did not apply because the pledge of the judgment was not such a contract. Id., 154 So. at 210.

To the extent that Ott may stand for the general rule that a contract fixing the mode of application of funds governs, it does not control here. The case at bar arises in connection with a “Little Miller Act” claim and is, therefore, governed by special principles.

AS 36.25.010, et seq., is modeled after the federal Miller Act. Like its federal counterpart, Alaska’s statute is designed “to protect persons who furnish labor or material for a state public works project from the risks of nonpayment.” State v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BP Pipelines (Alaska) Inc. v. State, Department of Revenue
327 P.3d 185 (Alaska Supreme Court, 2014)
Sagers v. Sackinger
318 P.3d 860 (Alaska Supreme Court, 2014)
Imperial Manufacturing Ice Cold Coolers, Inc. v. Shannon
101 P.3d 627 (Alaska Supreme Court, 2004)
Newmont Alaska Ltd. v. McDowell
22 P.3d 881 (Alaska Supreme Court, 2001)
Fairbanks North Star Borough v. Lakeview Enterprises, Inc.
897 P.2d 47 (Alaska Supreme Court, 1995)
Safeco Insurance Co. of America v. Honeywell, Inc.
639 P.2d 996 (Alaska Supreme Court, 1981)
Moses v. McGarvey
614 P.2d 1363 (Alaska Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
575 P.2d 1213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/state-ex-rel-palmer-supply-co-v-walsh-co-alaska-1978.