Safeco Insurance Co. of America v. Honeywell, Inc.

639 P.2d 996, 1981 Alas. LEXIS 618
CourtAlaska Supreme Court
DecidedDecember 12, 1981
Docket5112, 5127
StatusPublished
Cited by31 cases

This text of 639 P.2d 996 (Safeco Insurance Co. of America v. Honeywell, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safeco Insurance Co. of America v. Honeywell, Inc., 639 P.2d 996, 1981 Alas. LEXIS 618 (Ala. 1981).

Opinion

OPINION

CONNOR, Justice.

This is an action by a subcontractor against a surety’s payment bond. Interstate Company, Inc. (Interstate) was the prime contractor for the construction of the Mulcahy Park Sports Arena under Contract No. C-7425, awarded by the predecessor of the Municipality of Anchorage on July 11, 1974. Safeco Insurance Company of America (Safeco) executed a payment bond under AS 36.25.010(aX2) with Interstate as principal. Interstate awarded the mechanical subcontract to General Mechanical of Alaska (GMA). Interstate required GMA to post a performance and payment bond; GMA’s bond was provided by Summit Insurance Company of New York. GMA awarded two subcontracts to Honeywell, Inc. Later, on December 12, 1975, Honeywell served notice of a claim on Interstate for $24,011 for services rendered. Honeywell served another claim for $5,569 on Interstate on February 4, 1976. Honeywell then sued Safeco, as the bonding company, and Interstate for $30,204 on March 18, 1977.

Honeywell moved for summary judgment on May 29, 1979. The superior court considered part of Honeywell’s motion and granted it as to the timeliness of the suit. The issue of proper notice to Interstate on all claims was left for trial.

Before the trial, the parties, without their attorneys, agreed to settle the case on August 31,1979, as to the $5,569 claim. When Interstate presented the settlement check to Honeywell’s attorney, the attorney denied that Honeywell’s Anchorage representative had the authority to settle.

On September 12, 1979, there was a trial on the remaining issues. Judgment was entered on September 20th in favor of Honeywell. Following a hearing on November 1, the judgment was revised, in response to a motion under Alaska Rule of Civil Procedure 60(b), to reflect the parties’ signed settlement of September 28th, which was negotiated on August 31st. The judgment was again revised on December 5, 1979, on the superior court’s own motion, to modify the findings of fact and conclusions of law. Interstate and Safeco appeal from the judgment in favor of Honeywell; Honeywell cross-appeals from the same judgment.

I

Honeywell claims that the appeal should not be considered because it is untimely. Former Appellate Rule 7(a)(1) 1 required that the appellant file a notice of appeal within 30 days from the entry of judgment. In this case, there are three dates of entry on the judgment from which the appeal and cross-appeal are taken. The first judgment was entered on September 20, 1979. The second judgment, based on the November 1st hearing, was entered on November 16th and reduced Honeywell’s recovery. The third judgment was entered on December 5th and reflected modified findings of fact and conclusions of law to establish consistency between the court’s reasoning and the damage award.

If Interstate had appealed from the September 20th judgment, both the judgment amount and the findings of fact and conclusions of law would have been inaccurate. An appeal from the November 16th judg *999 ment would have contained the proper award, but inconsistent reasoning. The superior court, aware of the confusion in the case, modified its reasoning and reaffirmed the award in the December 5th judgment.

Former Appellate Rule 46 provides that the requirements of the appellate rules may be relaxed where a strict adherence to them will work injustice. See McCarrey v. Commissioner of Natural Resources, 526 P.2d 1353, 1355 (Alaska 1974). This case is an appropriate one in which to relax the provisions of former Appellate Rule 7(a)(1). We note that had the parties appealed from either the September or November judgments, the resolution of the appeal would have been more difficult than necessary. Further, we do not wish to discourage trial courts from revising their judgments and clarifying the record. As a practical consideration, the judgment, on its face, has three dates of entry. That in itself is highly confusing and suggests that it is appropriate to relax the rules. Thus, we find that the appeal is timely.

II

On December 19,1979, the superior court ordered Interstate to post a $40,000 bond to stay judgment. Interstate filed a motion to invest the cash deposit in a money market fund with the income to be paid to Interstate. Honeywell agreed with the investment, provided that it would receive one-half of the income in addition to the judgment award if Honeywell prevailed in the appeal. The trial court permitted the investment and granted Honeywell’s condition.

The decision of whether to impose the condition requested by Honeywell is within the trial court’s discretion. We will interfere with a discretionary determination of the trial court only if it is arbitrary, capricious or manifestly unreasonable. See Tobeluk v. Lind, 589 P.2d 873, 878 (Alaska 1979).

Interstate submitted the prospectus for the money market fund in which it planned to invest the $40,000. The prospectus reflects a net asset gain for the years ending August 31, 1978, and August 31, 1979. Honeywell argued that there was a risk of loss of the $40,000 if the amount were placed in the money market fund and thus Honeywell should receive one-half of the income as compensation for the risk. The risk alleged by Honeywell is not supported by the record. There are no accompanying documents with Honeywell’s motion supporting its concern that the investment may decrease in value. It was arbitrary and capricious for the trial court to agree to Honeywell’s condition, which in effect increased Honeywell’s award, based on a claimed risk that has no support in the record. The order granting one-half of the income to Honeywell is reversed.

Ill

On March 18,1977, Honeywell sued Safe-co and Interstate for breach of contract. Interstate moved for summary judgment on the ground that Honeywell’s complaint was untimely. The superior court denied Interstate’s motion, but granted Honeywell’s concurrent motion, and held that the complaint was timely. 2

*1000 The applicable statute of limitations is AS 36.25.020(c): “No suit may be started after the expiration of one year after the date of final settlement of the contract.” The contract between the Municipality and Interstate did not define final settlement. As the contract was completed and payments were made, agents of the Municipality made no specific determination of the date of final settlement. The issue is: Under the circumstances surrounding this contract, when did final settlement occur?

The term “final settlement,” in referring to government contracts, appeared in 1905 in the Heard Act (Ch. 778, 33 Stat. 811):

“Provided, That where suit is instituted by any of such creditors on the bond of the contractor it shall not be commenced until after the complete performance of said contract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract ... . ”

The Miller Act (Ch. 642, § 2,49 Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Christianson v. Conrad-Houston Insurance
318 P.3d 390 (Alaska Supreme Court, 2014)
American Marine Corporation v. Sholin
295 P.3d 924 (Alaska Supreme Court, 2013)
Jarvill v. Porky's Equipment, Inc.
189 P.3d 335 (Alaska Supreme Court, 2008)
In Re Estate of Blodgett
147 P.3d 702 (Alaska Supreme Court, 2006)
Lively v. Flexible Packaging Ass'n
830 A.2d 874 (District of Columbia Court of Appeals, 2003)
Cencomp, Inc. v. Webcon, Inc.
579 S.E.2d 482 (Court of Appeals of North Carolina, 2003)
Fernandes v. Portwine
56 P.3d 1 (Alaska Supreme Court, 2002)
Goodman v. Fairbanks North Star Borough School District
39 P.3d 1118 (Alaska Supreme Court, 2001)
Egemo v. Egemo Construction Co.
998 P.2d 434 (Alaska Supreme Court, 2000)
Toney v. City of Anchorage Police Department
950 P.2d 123 (Alaska Supreme Court, 1997)
Beesley v. Van Doren
873 P.2d 1280 (Alaska Supreme Court, 1994)
Gustafson v. Bridger Coal Co.
834 F. Supp. 352 (D. Wyoming, 1993)
Simpson v. District of Columbia Office of Human Rights
597 A.2d 392 (District of Columbia Court of Appeals, 1991)
Latham v. Haney Seed Co.
807 P.2d 645 (Idaho Court of Appeals, 1990)
A.H. v. State
779 P.2d 1229 (Alaska Supreme Court, 1989)
Bibo v. Jeffrey's Restaurant
770 P.2d 290 (Alaska Supreme Court, 1989)
Jenkins v. Daniels
751 P.2d 19 (Alaska Supreme Court, 1988)
Carman v. Prudential Insurance Co. of America
748 P.2d 743 (Alaska Supreme Court, 1988)
James v. Buck
727 P.2d 1136 (Idaho Supreme Court, 1986)
Metzger v. Kalke
709 P.2d 414 (Wyoming Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
639 P.2d 996, 1981 Alas. LEXIS 618, Counsel Stack Legal Research, https://law.counselstack.com/opinion/safeco-insurance-co-of-america-v-honeywell-inc-alaska-1981.