BX Chicago, LLC v. Galaxy Environmental, Inc.

2015 IL App (1st) 133624
CourtAppellate Court of Illinois
DecidedJuly 28, 2015
Docket1-13-3624
StatusUnpublished
Cited by1 cases

This text of 2015 IL App (1st) 133624 (BX Chicago, LLC v. Galaxy Environmental, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BX Chicago, LLC v. Galaxy Environmental, Inc., 2015 IL App (1st) 133624 (Ill. Ct. App. 2015).

Opinion

2015 IL App (1st) 133624 FIRST DIVISION JULY 27, 2015

No. 1-13-3624

GX CHICAGO, LLC, an Illinois Limited Liability Company, ) Appeal from the and LEDCOR CONSTRUCTION, INC., a Washington ) Circuit Court of Corporation, ) Cook County. ) Plaintiffs and Counterdefendants-Appellees, ) ) v. ) ) GALAXY ENVIRONMENTAL, INC., SHERWIN-WILLIAMS ) COMPANY, an Ohio Corporation, JESUS PEOPLE, U.S.A. ) FULL GOSPEL MINISTRIES d/b/a Lakefront Supply, ) No. 12 CH 00739 an Illinois Corporation, UNKNOWN OWNERS, NON-RECORD ) CLAIMANTS, and THE CITY OF CHICAGO, a Municipal ) Corporation, ) ) Defendants and Counterdefendants ) ) (Creative Vistas, Inc., Decmen Construction Inc., Greenwerks ) Recycling, Inc., Highlander Builders, Inc. and Householder ) Honorable Accounting Services, Inc., each an Illinois Corporation, ) Lewis M. Nixon, Defendants and Counterplaintiffs-Appellants). ) Judge Presiding.

JUSTICE CUNNINGHAM delivered the judgment of the court, with opinion. Justices Connors and Harris concurred in the judgment and opinion.

OPINION

¶1 This dispute concerns mechanics liens arising from a construction project to develop

certain real property owned by plaintiff-appellee GX Chicago, LLC (the owner).

¶2 BACKGROUND

¶3 On or about September 2, 2010, the owner contracted with plaintiff-appellee Ledcor

Construction Inc. (Ledcor) to serve as the general contractor for the project. Ledcor contracted

with various subcontractors for the project. One such subcontractor was Galaxy Environmental, 1-13-3624

Inc. (Galaxy), who entered into a contract with Ledcor in March 2011 to perform masonry work

on the project. Galaxy, in turn, entered into subcontracts with various other parties to provide

materials and labor on the project. Those subcontractors included the five defendants-appellants

herein: Creative Vistas, Inc.; Decmen Construction, Inc.; Greenwerks Recycling, Inc.;

Highlander Builders, Inc.; and Householder Accounting Services, Inc. (together, the Galaxy

subcontractors).

¶4 Through a series of "change order" requests submitted from Galaxy to Ledcor, the

amount of the Ledcor-Galaxy contract was steadily increased from an original amount of

$199,500 to an adjusted contract price of $518,185.75. Over the course of its work, Galaxy

submitted periodic applications for payment to Ledcor between April and June 2011. Galaxy’s

last application for payment, dated June 30, 2011, claimed a "current payment due" to Galaxy of

$117,201.06. That submission by Galaxy did not inform Ledcor that there were any outstanding

amounts owed to the Galaxy subcontractors.

¶5 On July 15, 2011, Ledcor made a corresponding payment to Galaxy in the amount of

$117,201.06. Sometime after that July 2011 payment, the owner and Ledcor became aware that

certain of Galaxy's subcontractors had not received payment from Galaxy for the work they

performed on the construction project. After that time, Ledcor made no further disbursements to

Galaxy.

¶6 In October and November 2011, the Galaxy subcontractors served the owner and Ledcor

with various notices of mechanics liens, for claims totaling $267,989.98. The amounts claimed

by the Galaxy subcontractors far exceeded the amount that Ledcor believed was remaining to be

paid on its contract with Galaxy; specifically, Ledcor asserted that only $126,178.30 remained to

be paid out of the total Ledcor-Galaxy contract amount of $518,185.75. Ledcor took the position

2 1-13-3624

that it could not be liable to Galaxy's subcontractors for any amount exceeding that $126,178.30

sum.

¶7 In December 2011, counsel for Ledcor advised Galaxy and the Galaxy subcontractors of

"Ledcor's position that neither Ledcor nor owner owe more than $126,178.37 to Galaxy and its

second tier subcontractors." Ledcor indicated that it was prepared to pay out that amount, but

that if agreement could not be reached, Ledcor would seek relief from the circuit court for "a

determination and ruling that neither Ledcor nor owner owe Galaxy or its [subcontractors] an

amount greater than $126,178.37." Shortly thereafter, Galaxy responded that an agreement

could not be reached with the Galaxy subcontractors.

¶8 Accordingly, on January 9, 2012, the owner and Ledcor filed a complaint pursuant to

section 30 of the Mechanics Lien Act (the Act), which states: "If there are several liens *** upon

the same premises, and the owner or any person having such a lien shall fear that there is not a

sufficient amount coming to the contractor to pay all such liens" the owner may file a complaint

for the court to determine "the amount due from the owner to the contractor, and the amount due

to each of the persons having liens." 770 ILCS 60/30 (West 2012).

¶9 The owner and Ledcor's section 30 complaint pleaded that the Galaxy subcontractors had

claims totaling $267,989.98, but that "there remains to be paid out to Galaxy under its contract

with Ledcor, *** the sum of $126,178.19." The section 30 complaint sought an accounting to

determine: the amount due to Galaxy under the Ledcor-Galaxy contract; the amounts due to

Galaxy's subcontractors; and "the amount due from the [owner] to [Ledcor] under their contract

with respect to the amounts due and payable to Galaxy and its sub-subcontractors."

¶ 10 On July 2, 2012, the Galaxy subcontractors filed their answer and three affirmative

defenses to the owner and Ledcor's complaint. In the first affirmative defense, they asserted that

3 1-13-3624

full payment for their work was past due under the Contractor Prompt Payment Act. See 815

ILCS 603/1 et seq. (West 2012). Second, the Galaxy subcontractors asserted an "unclean hands"

defense, claiming that certain change orders relied upon by Ledcor and Galaxy to support their

position that only $126,178.19 remained due on the Ledcor-Galaxy contract were fraudulently

created "ex post facto" "months after the original change orders were generated [and the] work

was completed." The Galaxy subcontractors stated that through such change orders Ledcor had

misrepresented that the Ledcor/Galaxy contract totaled $518,185.75 and that there was only

$126,178.19 remaining due on the contract. The Galaxy subcontractors asserted that the actual

value of the Ledcor/Galaxy contract was higher, "about $610,553.75," and that the unpaid

balance was actually $218,546.19. Thus, the Galaxy subcontractors alleged that Ledcor and

Galaxy worked together to mislead the Galaxy subcontractors "into believing the Galaxy/Ledcor

Contract, as amended, was smaller in scope and dollar amount, with about $92,368.00 less due

and payable available" to the Galaxy subcontractors. As a third affirmative defense, the Galaxy

subcontractors claimed that after they notified the owner of their mechanics liens, pursuant to the

Act the owner was required to withhold sufficient funds from Ledcor to pay their claims. The

Galaxy subcontractors thus argued that their claims "should be paid from the funds [the owner]

withheld in accord with the Act, or if it failed to do so, directly by [the owner]."

¶ 11 Also on July 2, 2012, the Galaxy subcontractors filed a counterclaim against the owner,

Ledcor, and Galaxy. The first eight counts of the counterclaim sought foreclosure of the Galaxy

subcontractors' mechanics liens. Counts 9 through 16 of the counterclaim asserted breach of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GX Chicago, LLC v. Galaxy Environmental, Inc.
2015 IL App (1st) 133624 (Appellate Court of Illinois, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
2015 IL App (1st) 133624, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bx-chicago-llc-v-galaxy-environmental-inc-illappct-2015.