PML Development LLC v. Village of Hawthorn Woods

2025 IL App (2d) 240191-U
CourtAppellate Court of Illinois
DecidedMarch 26, 2025
Docket2-24-0191
StatusUnpublished

This text of 2025 IL App (2d) 240191-U (PML Development LLC v. Village of Hawthorn Woods) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PML Development LLC v. Village of Hawthorn Woods, 2025 IL App (2d) 240191-U (Ill. Ct. App. 2025).

Opinion

2025 IL App (2d) 240191-U No. 2-24-0191 Order filed March 26, 2025

NOTICE: This order was filed under Supreme Court Rule 23(b) and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT ______________________________________________________________________________

PML DEVELOPMENT LLC, ) Appeal from the Circuit Court ) of Lake County. Plaintiff and Counterdefendant- ) Appellee and Cross-Appellant, ) ) v. ) No. 15-CH-848 ) VILLAGE OF HAWTHORN WOODS, ) ) Honorable Defendant and Counterplaintiff- ) Luis A. Berrones, Appellant and Cross-Appellee. ) Judge, Presiding. ______________________________________________________________________________

JUSTICE SCHOSTOK delivered the judgment of the court. Justices Hutchinson and Jorgensen concurred in the judgment.

ORDER

¶1 Held: (1) Plaintiff’s damages were not barred under the new business rule; (2) in its calculation of damages, the trial court only erred in its calculation of plaintiff’s lost revenue; (3) the trial court properly declined to award monetary damages to defendant where defendant never sought monetary damages in its pleadings; (4) postjudgment interest accrued from the date of the trial court’s judgment on remand; (5) the trial court did not err in finding that plaintiff was the prevailing party, but it erred in not awarding attorney fees for the entirety of the litigation; (6) award of costs under the parties’ contract was limited to court costs.

¶2 This breach of contract case stems from a 2012 development agreement (Agreement)

between plaintiff and counterdefendant PML Development LLC (PML) and defendant and

counterplaintiff Village of Hawthorn Woods (Village). Following a bench trial, the trial court

found in favor of PML and awarded it monetary damages and attorney fees. On appeal, we 2025 IL App (2d) 240191-U

reversed because we determined that neither party was entitled to damages since both materially

breached the Agreement. PML Development LLC v. Village of Hawthorn Woods, 2022 IL App

(2d) 200779, ¶ 61 (PML I). Our supreme court agreed that both parties materially breached the

Agreement but held that each party was entitled to seek damages under the “partial-breach

doctrine.” PML Development LLC v. Village of Hawthorn Woods, 2023 IL 128770, ¶ 66 (PML

II). The supreme court therefore remanded to the trial court to determine each party’s damages

and hold a further evidentiary hearing, if necessary. Id. ¶ 69. On remand, the trial court declined

to hold an evidentiary hearing and awarded both parties damages, though not all the damages each

sought. The Village appealed and PML cross-appealed. We affirm in part and reverse in part.

¶3 I. BACKGROUND

¶4 A more thorough version of the facts may be found in our previous opinion and our

supreme court’s opinion. See PML II, 2023 IL 128770; PML I, 2022 IL App (2d) 200779. We

recite only those facts necessary to resolving the parties’ appeals.

¶5 In summer 2012, Dan Powell, a business owner who did fill and grading projects, became

interested in purchasing a 62-acre property (Property) in the Village. The Property was across the

street from a different property that Powell owned through his company DA Development, which

is co-owned by Mitch Maneval. Powell did his due diligence and had the property inspected by a

wetland specialist, surveyors, and a civil engineering firm. The engineering firm, Pearson Brown

& Associates, prepared a full set of grading plans. Powell submitted those grading plans to the

Village before purchasing the Property, and the Village’s chief administration officer, Donna

Lobaito, told him the plans “looked good.” On September 7, 2012, Powell purchased the Property

through his new company, PML. “PML” stands for Powell, Meneval, Lenzini, the co-owners

when it was formed in 2012 (Rob Lenzini later left the company).

-2- 2025 IL App (2d) 240191-U

¶6 On October 11, 2012, PML entered into the Agreement with the Village. The Agreement

allowed PML to use the Property as a fill site and grade it for the Village’s later use. The

Agreement required PML to transfer the Property to the Village “free and clear” by December 31,

2015. The Agreement required PML to protect existing trees, maintain surrounding roadways,

comply with “all environmental measures,” obtain and comply with necessary permits, allow the

Village to inspect the Property at PML’s expense, and rebuild Kruger Road—the road on which

the Property is located—at the conclusion of the project. PML was also required to execute a draw

down agreement and fund a draw down account to pay for various costs related to the Property

that were incurred by the Village.

¶7 In February 2013, the Village allowed PML to begin work on the Property. However, the

Village’s engineers had concerns because the Village lacked plans for how to use the Property.

The Village therefore limited the area on which PML could work. This caused several problems

for PML, including poor site conditions and long lines of trucks on Kruger Road waiting to enter

the Property. Over the course of the next two years, the Village continued to limit PML’s use of

the property through permitting and stop-work orders while it continued to develop a plan for its

use of the Property.

¶8 In May 2015, PML filed a complaint against the Village alleging that the Village interfered

with PML’s work on the property and caused it to incur additional costs. PML sought to enforce

the provision of the Agreement that allowed it to bring 1.2 million cubic yards of fill onto the

Property. It also sought a declaration that the Village was required by the Agreement to give it a

two-year work permit. PML sought monetary damages, an injunction barring the Village from

interfering with its work, and a declaration that PML was no longer required to convey the Property

-3- 2025 IL App (2d) 240191-U

to the Village. PML additionally sought mandamus relief to compel the Village to rescind all stop-

work orders and issue a two-year permit.

¶9 In July 2015, the Village filed a counterclaim alleging that PML breached the Agreement

by failing to repair Kruger Road, failing to pay taxes on the Property, and failing to fund the draw

down account. The Village sought monetary damages for the failure to repair Krueger Road and

the failure to fund the draw down account, while it sought specific performance for conveyance of

the Property from PML.

¶ 10 Before trial, the trial court granted PML’s mandamus petition and ordered the Village to

issue a work permit through December 2016. It later ordered the permit extended through

December 2018. The trial court also granted the Village partial summary judgment on its claim

that PML failed to convey the Property, but it did not grant any relief. The trial court expressed

concern that PML did not have the funds to pay off the taxes on the Property.

¶ 11 The trial court conducted a bench trial over ten days between June 2019 and January 2020.

Two experts from Gleeds, USA, Will Burton and Charl Neser, testified for PML regarding its

damages. They testified that to calculate PML’s damages, Gleeds looked at Powell’s 2012

estimated budget for PML’s work on the Property and determined its reasonability based on similar

projects in the area, Powell’s prior projects, and PML’s “competitors.” After finding the estimate

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doornbos Heating & Air Conditioning, Inc. v. Schlenker
932 N.E.2d 1073 (Appellate Court of Illinois, 2010)
Valley Forge Insurance v. Swiderski Electronics, Inc.
860 N.E.2d 307 (Illinois Supreme Court, 2006)
Galowich v. Beech Aircraft Corp.
441 N.E.2d 318 (Illinois Supreme Court, 1982)
Phelps v. O'MALLEY
543 N.E.2d 311 (Appellate Court of Illinois, 1989)
Kramer v. Mount Carmel Shelter Care Facility, Inc.
750 N.E.2d 757 (Appellate Court of Illinois, 2001)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
Rosenbaum v. Rosenbaum
418 N.E.2d 939 (Appellate Court of Illinois, 1981)
Vicencio v. Lincoln-Way Builders, Inc.
789 N.E.2d 290 (Illinois Supreme Court, 2003)
Lee v. Chicago Transit Authority
605 N.E.2d 493 (Illinois Supreme Court, 1992)
People v. Crawford Distributing Co.
397 N.E.2d 1362 (Illinois Supreme Court, 1979)
Newton v. Aitken
633 N.E.2d 213 (Appellate Court of Illinois, 1994)
People v. Anderson
944 N.E.2d 359 (Appellate Court of Illinois, 2011)
Brown and Kerr, Inc. v. American Stores Properties, Inc.
715 N.E.2d 804 (Appellate Court of Illinois, 1999)
Staes and Scallan, P.C. v. Orlich
2012 IL App (1st) 112974 (Appellate Court of Illinois, 2012)
Oak Forest Properties, LLC v. RER Financial, Inc.
2018 IL App (1st) 161704 (Appellate Court of Illinois, 2019)
PML Development LLC v. Village of Hawthorn Woods
2022 IL App (2d) 200779 (Appellate Court of Illinois, 2022)
Ivey v. Transunion Rental Screening Solutions Inc.
2022 IL 127903 (Illinois Supreme Court, 2022)
Village of Kirkland v. Kirkland Properties Holdings Co., LLC I
2023 IL 128612 (Illinois Supreme Court, 2023)
PML Development LLC v. Village of Hawthorn Woods
2023 IL 128770 (Illinois Supreme Court, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2025 IL App (2d) 240191-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pml-development-llc-v-village-of-hawthorn-woods-illappct-2025.