Fowler & Hammer, Inc. v. Relyant Global, LLC

CourtDistrict Court, W.D. Wisconsin
DecidedJune 16, 2022
Docket3:22-cv-00089
StatusUnknown

This text of Fowler & Hammer, Inc. v. Relyant Global, LLC (Fowler & Hammer, Inc. v. Relyant Global, LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fowler & Hammer, Inc. v. Relyant Global, LLC, (W.D. Wis. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

FOWLER & HAMMER, INC., Plaintiff, OPINION AND ORDER v. 22-cv-89-slc RELYANT GLOBAL, LLC, Defendant. _____________________________________________________________________________________ In this removal action, plaintiff Fowler & Hammer, Inc. (F&H) alleges that defendant Relyant Global, LLC breached the parties’ subcontract related to the construction of a shipping and receiving building at Fort McCoy, Wisconsin. Citing mandatory dispute resolution provisions in the subcontract, Relyant has moved to dismiss this action under Fed. R. Civ. P. 12(b)(6) for F&H’s failure to follow the dispute resolution procedures set forth in the subcontract. Dkt. 17. In the alternative, Relyant asks the court to stay this action and compel F&H to arbitrate pursuant to the Federal Arbitration Act (FAA), 9 U.S.C. § 1, and the parties’ agreement. For the reasons below, I am denying Relyant’s motion to dismiss and denying without prejudice Relyant’s alternative motion to stay this case and compel arbitration. Although Relyant has shown that the parties had a written arbitration agreement that applies to the instant dispute, this court does not have the authority to compel arbitration in the forum selected by the parties (Tennessee). If Relyant wishes to pursue arbitration, it may file a motion to dismiss for improper venue under Fed. R. Civ. P. 12(b)(3) or bring an action under Section 4 of the FAA in a district court in Tennessee, which would have the authority to compel arbitration of F&H’s claims. In deciding a motion to dismiss, the court accepts all well-pled factual allegations in the complaint as true, Adams v. City of Indianapolis, 742 F.3d 720, 728 (7th Cir. 2014), and views them in the light most favorable to the non-movant, Santiago v. Walls, 599 F.3d 749, 756 (7th Cir. 2010). F&H alleges the following facts in its amended complaint (dkt. 11):

ALLEGED FACTS

Plaintiff F&H is a Wisconsin Corporation with its principal place of business in La Crosse, Wisconsin. Defendant Relyant is a Tennessee limited liability company with its principal place of business in Maryville, Tennessee.1 On May 10, 2019, the parties entered into a subcontract agreement under which Relyant hired F&H to design and build a shipping and receiving building at Fort McCoy, Wisconsin for the contract price of $952,730.00, which was subsequently increased to $2,060,681.33 by change orders and other agreements between the parties. The subcontract contains a section entitled “Choice of Law and Disputes,” which provides

in relevant part: The Parties acknowledge that there are a number of informal dispute resolution procedures (such as arbitration, mediation, and informal conferences) which will be used in an effort to resolve any controversy, dispute or claim arising out of this Agreement, or the alleged breach thereof. The Parties agree that the aforementioned procedures will be utilized prior to proceeding in a judicial forum. Should any such controversy, dispute or claim arise, the Parties shall first attempt to resolve it following the steps outlined below. Conference: The Parties shall schedule a conference with the Parties’ representatives who executed this agreement, or any other representatives the Parties’ designate in their stead. This conference shall take place within 14 days from the time a substantiated claim has been submitted. The conference shall take 1 Relyant states in its notice of removal that there is a diversity of citizenship between the parties because F&H is a citizen of Wisconsin and all of Relyant’s members are citizens of Tennessee. 2 place either in person or telephonically to discuss and determine if a resolution can be reached. Executive Discussions: If the first step is unsuccessful and a resolution has not been reached within 10 days of the conference, the Parties shall move to the next step and hold executive discussions. A conference shall be scheduled within fourteen (14) days of the executive discussion request either in person or telephonically with senior executives from each company to discuss and determine if a resolution can be reached. Mediation: If the claim is not resolved via the executive conference within 10 days, the claim then moves to non-binding mediation. The mediation will be conducted by a mutually agreeable impartial mediator and will be governed by and conducted pursuant to the procedures established by the mediator. . . . Dependent on the mediator’s schedule, the mediation will commence within thirty (30) days of the submission of the claim to mediation. Arbitration: If the claim is not resolved within 10 days of mediation, the claim will then move to arbitration. The decision of the arbitrator(s) shall be final and binding on both Prime Contractor and Subcontractor. For all Claims to Prime Contractor initiated by Subcontractor, Subcontractor must submit its demand for arbitration no later than twelve (12) months after the mediation unless such deadline extension is otherwise agreed to in writing by the Parties. Each of the steps set forth above is a condition precedent to taking the next step (i.e., a party may not proceed to executive discussion until the step one conference has been completed, may not proceed to mediation until executive discussion has been completed.) Dkt. 11-1 at 7-8. The subcontract also contains a waiver provision that provides that “[n]o asserted waiver of any right or benefit by Relyant shall be valid unless such waiver is in writing, signed by Relyant, supported by consideration and specifies the extent and nature of the rights or benefits being waived.” Id. at 9. 3 F&H alleges that Relyant failed to pay the full contract price for F&H’s services and owes F&H $249,116.48. The parties participated in the first two steps of the dispute resolution process. However, Relyant failed to respond to F&H’s May 25, 2021 demand to schedule mediation. On October 5, 2021, F&H’s attorney sent another written demand to schedule

mediation, stating that if “Relyant continues to refuse mediation, we will consider the choice of forum and dispute resolution provisions of the subcontract to be null and void and proceed accordingly.” Dkt. 11-2. Relyant did not respond to the second demand. After waiting nearly four months for a response, F&H considered the ADR process waived and filed suit in Monroe County Circuit Court on January 28, 2022. Relyant removed the case to this court on February 18, 2022.

OPINION

A motion to dismiss under Fed. R. Civ. P. 12(b)(6) tests the complaint’s legal sufficiency. A complaint survives a motion to dismiss if it “contain[s] sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct

alleged.’” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Santiago v. Walls
599 F.3d 749 (Seventh Circuit, 2010)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Faulkenberg v. CB Tax Franchise Systems, LP
637 F.3d 801 (Seventh Circuit, 2011)
Wisconsin Electric Power Co. v. Union Pacific Railroad
557 F.3d 504 (Seventh Circuit, 2009)
Haber v. Biomet, Inc.
578 F.3d 553 (Seventh Circuit, 2009)
Thompson v. Village of Hales Corners
340 N.W.2d 704 (Wisconsin Supreme Court, 1983)
Hanz Trucking, Inc. v. Harris Brothers Co.
138 N.W.2d 238 (Wisconsin Supreme Court, 1965)
Bank of Sun Prairie v. Opstein
273 N.W.2d 279 (Wisconsin Supreme Court, 1979)
Kendale L. Adams v. City of Indianapolis
742 F.3d 720 (Seventh Circuit, 2014)
Zurich American Insurance v. Watts Industries, Inc.
466 F.3d 577 (Seventh Circuit, 2006)
Cowie v. Strohmeyer
136 N.W. 956 (Wisconsin Supreme Court, 1912)
Somers v. Germania National Bank of Milwaukee
138 N.W. 713 (Wisconsin Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
Fowler & Hammer, Inc. v. Relyant Global, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fowler-hammer-inc-v-relyant-global-llc-wiwd-2022.