2025 IL App (1st) 241461-U
FOURTH DIVISION Order filed: June 18, 2025
Nos. 1-24-1461, 1-24-2607 (cons.)
NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________
IN THE
APPELLATE COURT OF ILLINOIS
FIRST DISTRICT ______________________________________________________________________________
GW 3800 MILWAUKEE, LLC, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County. ) v. ) No. 22 L 1695 ) BLOOM BOUNCE, LLC, JEREMY BLOOM, and ) SALLY BLOOM, ) Honorable ) Ronald F. Bartkowicz, Defendants-Appellees. ) Judge, presiding.
JUSTICE HOFFMAN delivered the judgment of the court. Presiding Justice Rochford and Justice Ocasio concurred in the judgment.
ORDER
¶1 Held: In an action for breach of contract brought by a landlord following a tenant’s termination of a lease agreement based on a prior alleged breach by the landlord, the circuit court’s order granting summary judgment in favor of the tenant is reversed because there are issues of material fact regarding the tenant’s possible waiver of strict performance and the materiality of the landlord’s alleged breach.
¶2 This consolidated appeal concerns a dispute between GW 3800 Milwaukee, LLC (“GW”),
and Bloom Bounce, LLC (“Bloom Bounce”), along with Bloom Bounce’s member-managers Sally
Bloom and Jeremy Bloom (collectively with Bloom Bounce, “Defendants”), over Bloom Bounce’s Nos. 1-24-1461, 1-24-2607 (cons.)
termination of a lease agreement with GW. GW filed an action against the Defendants, alleging
breach of contract. The Defendants moved for summary judgment, and the circuit court granted
their motion, entering judgment in their favor. We reverse the trial court’s judgment and remand
for further proceedings.
¶3 At the center of this case is a January 29, 2020, lease (“Lease”) between GW and Bloom
Bounce under which Bloom Bounce was to lease commercial real estate (“Premises”) from GW
for 10 years and 2 months for the purpose of operating a “Pump It Up” bounce-house franchise.
Pump It Up utilizes large inflatable structures to provide an indoor play space for children. Sally
and Jeremy signed the Lease as guarantors, personally guaranteeing Bloom Bounce’s payment of
rent and the performance of Bloom Bounce’s obligations under the Lease. Several provisions of
the Lease are at issue in the present appeal, which focuses on whether Bloom Bounce was entitled
to terminate the Lease based on GW’s failure to tender possession of the Premises in a timely
manner and in the condition required by the Lease.
¶4 Article I(b) of the Lease defined the “Possession Date” and set forth additional obligations
and rights surrounding the transfer of possession from GW to Bloom Bounce, including Bloom
Bounce’s right to terminate the Lease if GW failed to deliver possession of Premises in a timely
manner:
“The ‘Possession Date’ is the date [GW] delivers possession of the Premises to [Bloom
Bounce] in the condition required under this Lease (including, without limitation, as set
forth in Section 2.03 below). On the Possession Date, [Bloom Bounce] shall accept
possession of the Premises and execute the form of Tenant Acceptance of Premises as
attached hereto as Exhibit G; provided [Bloom Bounce’s] acceptance of the Premises shall
-2- Nos. 1-24-1461, 1-24-2607 (cons.)
be subject to (a) [GW’s] completion of a ‘punchlist’ of incorrect, incomplete or damaged
items, which punchlist items will be agreed upon by [GW] and [Bloom Bounce] within
thirty (30) days thereafter and [GW] will use its best efforts to correct or repair such
punchlist items within thirty (30) days after such 30-day period, and (b) any latent defects
of which [Bloom Bounce] gives [GW] written notice within one (1) year after the
Possession Date. *** Notwithstanding anything to the contrary in this Lease, if the
Possession Date does not occur on or before September 30, 2020 (the ‘Estimated
Possession Date’), then [Bloom Bounce] may elect to terminate this Lease by delivery of
written notice thereof to [GW] at any time thereafter. In the event of a termination of this
Lease pursuant to the immediately preceding sentence, the parties shall have no further
obligations or liabilities under this Lease (except those which, by the provisions of this
Lease, expressly survive the expiration or termination of the Term of this Lease).”
(Emphasis added.)
¶5 Section 2.03 of the Lease further provided, in relevant part, that “[GW], at [GW’s] sole
cost and expense, shall deliver the Premises to [Bloom Bounce] on the Possession Date in ‘warm
shell condition’ (as defined in Exhibit L), broom clean condition, in compliance with all
Applicable Laws, municipal codes and ordinances, and separately demised from other space in the
building.” “Warm Shell Condition,” in turn, was defined in Exhibit L as: “(i) Demised, with all
utilities and the heating, ventilation and cooling (HVAC) system stubbed to space for Tenant
distribution, drop ceiling, restrooms, plumbing and interior lighting. All site work and storefronts
per [GW’s] plans; and (ii) Installation of a new HVAC unit exclusively serving the Premises.”
¶6 The Lease also provided under section 12.02 that, in relevant part:
-3- Nos. 1-24-1461, 1-24-2607 (cons.)
“The failure of [GW] or [Bloom Bounce] to insist at any time upon the strict performance
of any covenant or agreement of [Bloom Bounce] or [GW] or to exercise any option, right,
power or remedy contained in this Lease shall not be construed as a waiver or a
relinquishment thereof. No provision of this Lease shall be deemed to have been waived
by [GW] or [Bloom Bounce] unless such waiver is in writing, signed by [GW] or [Bloom
Bounce].”
Finally, section 12.04 of the Lease required Bloom Bounce to provide GW with written notice of
any alleged default by GW and to provide GW 30 days to cure such a default.
¶7 The pleadings and summary judgment evidence set forth the following history of relevant
events. On September 22, 2020, the parties executed an amendment to the Lease that extended the
Possession Date to October 1, 2020. On October 2, 2020, after GW failed to deliver possession of
the Premises on October 1, Bloom Bounce exercised its right to terminate the Lease. On November
16, 2020, the parties reinstated the Lease and executed a second amendment that changed the
Possession Date to June 30, 2021.
¶8 At some point in 2020, GW delivered its plans for the Premises to Bloom Bounce. Those
plans did not show any drop ceilings, restrooms, plumbing, or interior lighting to be installed by
GW, and Bloom Bounce did not express any objection to those plans. Bloom Bounce also provided
its own plans to GW, which showed that Bloom Bounce would install the drop ceilings, restrooms,
plumbing, and interior lighting.
¶9 On December 3, 2020, GW told Bloom Bounce by email that the Premises were ready and
provided photographs of the Premises that, according to GW, showed that no drop ceilings,
restrooms, plumbing, or interior lighting had been installed. Sally responded that the Premises
-4- Nos. 1-24-1461, 1-24-2607 (cons.)
looked “great,” but that Bloom Bounce was “waiting to see what happens” with developments in
the ongoing COVID-19 pandemic.
¶ 10 In January 2021, Bloom Bounce accepted keys to the Premises, and on March 10, 2021,
Bloom Bounce notified GW that it intended to begin seeking permits for developing the Premises.
On May 4, 2021, Bloom Bounce’s contractor, CoreBuilt, inspected the Premises to review GW’s
work and confirm the remaining work to be done. Following that inspection, Bloom Bounce did
not raise any objection to the state of the Premises or provide a punch list to GW. In the first week
of August 2021, CoreBuilt began development of the premises, and on August 13, 2021, Bloom
Bounce’s inflatables were delivered to the Premises.
¶ 11 In the second week of September, the parties held a meeting at the Premises, which was
attended by Sally, GW’s manager Mitch Goltz, Bloom Bounce’s real estate broker Paul Bryant,
CoreBuilt’s project manager Eric Okeson, Bloom Bounce’s architect Mark Diganci, and Bloom
Bounce’s general manager Brett Anderson. According to GW, the subject of the meeting was
Bloom Bounce’s concern that Bloom Bounce was over budget, while Bloom Bounce alleges that
the purpose was to discuss the remaining work to be completed by GW. During the meeting, the
parties agreed that GW would provide $90,000 toward certain outstanding work in the form of rent
abatements, and Bloom Bounce would cover the remaining $60,000 that was estimated to be
necessary. Following the conclusion of the meeting, Bloom Bounce agreed to move forward, and
Sally was under the assumption that the parties would continue with their obligations under the
Lease. Over the next two months, CoreBuilt continued to work on preparing the Premises for
Bloom Bounce to begin operations. During that time, the parties also negotiated a third amendment
-5- Nos. 1-24-1461, 1-24-2607 (cons.)
to the Lease, which contained provisions for rent abatements and a modification of the definition
of “warm shell condition,” but the amendment was ultimately never agreed to or executed.
¶ 12 On November 9, 2021, Sally learned that the Premises was not tall enough to accommodate
seven of Bloom Bounce’s ten inflatables. Sally attributed the error to Bloom Bounce’s architect.
Nonetheless, construction at the Premises continued through November 19, 2021.
¶ 13 On December 1, 2021, Sally sent a letter to GW terminating the Lease on the grounds that
GW had not tendered possession of the Premises in warm shell condition by the possession date
specified in the Lease, June 30, 2021. Specifically, Sally noted that the Premises was not in warm
shell condition because GW had not installed a drop ceiling or restrooms. Separately, Sally told
CoreBuilt’s president, James Neavolls, that she was ending the project because the HVAC
ductwork in the Premises was too low to accommodate the Pump It Up inflatables. Sally provided
the same reasoning to Pump It Up when she wrote to the company on January 27, 2022, to
terminate Bloom Bounce’s franchise agreement. In an email, Sally explained to Pump It Up that
the inflatables would not fit under the ductwork and that the only solution was to put the ductwork
on the roof at a cost of $140,000, which Bloom Bounce was unwilling to pay. For those reasons,
she stated, Bloom Bounce terminated the Lease.
¶ 14 On February 18, 2022, GW initiated this action by filing a two-count complaint against the
Defendants, seeking damages from Bloom Bounce for breach of contract and damages from Sally
and Jeremy as guarantors. The Defendants filed a motion to dismiss, which was denied, and then
filed an answer and affirmative defenses.
-6- Nos. 1-24-1461, 1-24-2607 (cons.)
¶ 15 During the course of discovery, the parties took depositions of various people involved in
the case. Relevant to the present appeal, several witnesses provided testimony relating to the
meaning of “warm shell condition,” as that term was used in Exhibit L of the Lease.
¶ 16 GW manager Goltz testified that he had been involved in negotiating and signing hundreds
of commercial leases in his career, including the Lease at issue here. He explained that warm shell
condition “by commercial reasonable expectations is a space that's demised with utilities, with
HVAC stubbed to the space, is separate from any other space in the building, and any sort of
outside site work affiliated with that.” It was Goltz’s belief that HVAC distribution, the drop
ceiling, restrooms, plumbing, and lighting were Bloom Bounce’s responsibility. Goltz further
opined that the definition provided in the Lease was unambiguous and that it was standard
commercial practice for the landlord to stub the utilities to the space and for the tenant to handle
the remaining items, which depend on the tenant’s specific plans for the space. Goltz explained
that the items at issue “require a tremendous amount of communication [between landlord and
tenant], a tremendous amount of coordination and frankly a full set of interior plans to show how
the lighting operates, how the ceiling operates, how the HVAC gets distributed.”
¶ 17 Sally testified that she had no previous experience in commercial real estate development
and had never heard of the term “warm shell condition” before negotiating the terms of the Lease.
Sally stated that she believed that it was GW’s responsibility to install the drop ceiling, bathrooms,
plumbing, and interior lighting because “there's no distribution that can be had with drop ceiling.
You can't distribute restroom. You can't distribute lighting. So I read that as it is plainly written in
plain English to say system stubbed into the space for tenant distribution, comma, drop ceiling,
comma, restroom, comma, plumbing and interior lighting.” Sally acknowledged that Pump It Up
-7- Nos. 1-24-1461, 1-24-2607 (cons.)
had specific interior lighting requirements for its franchises and that Bloom Bounce had never
provided those requirements to GW for GW to install conforming lighting.
¶ 18 CoreBuilt owner Neavolls testified that the definition of “warm shell condition” in the
Lease was “not very clear” and “could be interpreted different ways.” Speaking more generally,
in Neavolls’ experience “warm shell condition” is “usually a landlord deliverable, you know, a
white box, warm shell,” but the meaning of the term is “case dependent” because “everybody has
a different definition of it.”
¶ 19 CoreBuilt project manager Okeson testified that when he first read the Lease at the outset
of the project he believed that it was GW’s responsibility to install the drop ceiling, restrooms,
plumbing, and interior lighting. However, at the time of his deposition, he stated: “As I read it
today, given I have more experience than I did two years ago, I would have asked more questions.
I think it's not clear.” Okeson added, “Today, I would expect basically a landlord's permit drawing
to describe this and the landlord's confirmation. I don't feel that [Exhibit L] accurately describes
landlord work. There's -- this paragraph is very wide for interpretation.”
¶ 20 Real estate broker Bryant agreed that, generally, “warm shell condition with space fully
demised” means that “landlord would be responsible for ensuring that the electricity, the plumbing,
the HVAC were all brought to the space so that the tenant could then do the work on the inside
and then complete what would be the finish construction.” However, Bryant added that “[o]ur
industry is not black and white. There's a lot of terms like this that are a bit gray. So generally --
like I said, you can ask 10 different people and they might give you 10 remotely different answers.”
¶ 21 Real estate broker Westin Kane, who was Bryant’s partner, testified that he had a “strong
understanding” of the term “warm shell condition,” which he understood to mean that HVAC and
-8- Nos. 1-24-1461, 1-24-2607 (cons.)
plumbing would be stubbed to the tenant’s space, and there would be “some form of lighting
already in place.” However, Kane noted that “there’s not one right answer,” and the details are
“usually going to be debated between landlord and tenant.” That includes the installation of
bathrooms, as “some landlords believe that to be including a toilet in the space and some -- and
fixtures. And some would say [plumbing] just needs to be stubbed to the space.”
¶ 22 On February 9, 2024, the Defendants filed a motion for summary judgment as to both
counts of GW’s complaint. The Defendants argued that Bloom Bounce was entitled to terminate
the Lease because GW had not delivered possession of the Premises in a timely manner and in
warm shell condition, as that term was defined in the Lease. Specifically, the Defendants
contended that Exhibit L clearly and unambiguously required GW to install restrooms and interior
lighting by the possession date set forth in Article I(b) of the Lease, which it had not done.
Relatedly, the Defendants argued that, because Bloom Bounce did not breach the Lease, Sally and
Jeremy were not liable as guarantors.
¶ 23 In response, GW argued that both the plain language of the definition of “warm shell
condition” and the term’s trade usage support its position that Bloom Bounce was responsible for
installing drop ceilings, restrooms, plumbing, and interior lighting. GW also raised alternative
arguments that Exhibit L was ambiguous, that Bloom Bounce waived strict compliance with
Article I(b) of the Lease setting the “possession date” by which GW was to tender possession of
the Premises in warm shell condition, that the failure to tender possession in warm shell condition
by the possession date was not a material breach entitling Bloom Bounce to terminate the Lease,
and that issues of material fact regarding Bloom Bounce’s liability preclude summary judgment
on GW’s guaranty claim against Sally and Jeremy.
-9- Nos. 1-24-1461, 1-24-2607 (cons.)
¶ 24 Following a hearing at which the parties presented their arguments, the circuit court entered
an order on June 21, 2024, granting the Defendants’ motion for summary judgment as to both
counts of GW’s complaint. The court specifically found that Exhibit L was unambiguous and
required GW to install the restrooms and interior lighting in the Premises. Because GW failed to
do so by the possession date specified in the Lease, the court explained, Bloom Bounce was entitled
to terminate the agreement. In reaching that conclusion, the court noted that the deposition
testimony of Goltz, Bryant, and Sally did not aid GW’s trade-usage argument, and the court did
not discuss GW’s alternative waiver and material-breach arguments. GW then filed a notice of
appeal.
¶ 25 Shortly after GW initiated its appeal, the Defendants filed a petition for attorneys’ fees and
costs pursuant to the terms of the Lease. GW then filed a motion seeking a finding under Supreme
Court Rule 304(a) (eff. Mar. 8, 2016) and a stay of proceedings on the Defendants’ motion for fees
and costs. The circuit court granted GW’s motion and entered an order on December 19, 2024,
finding that there was no just reason for delaying either enforcement or appeal or both of the court’s
June 21, 2024, order granting summary judgment in favor of the Defendants. GW then filed
another notice of appeal from that order. We have consolidated the two appeals and resolve them
together here.
¶ 26 GW presents what we view as three issues on appeal, as well as one alternative argument.
In its first two issues, GW contends that summary judgment was inappropriate because there are
genuine issues of material fact regarding (1) whether Bloom Bounce waived its right to enforce
strict compliance with Article I(b) and Section 2.03 of the Lease and (2) whether GW’s alleged
failure to strictly comply with those provisions amounted to a material breach justifying Bloom
- 10 - Nos. 1-24-1461, 1-24-2607 (cons.)
Bounce’s termination of the Lease. GW then argues that (3) the plain language of Exhibit L and
its definition of “warm shell condition” required Bloom Bounce, not GW, to install restrooms and
interior lighting. In the alternative, GW asserts that the language of Exhibit L is ambiguous and
presents a genuine issue of material fact regarding its meaning that should have precluded
summary judgment. We agree with GW’s first two contentions regarding waiver and the
materiality of the alleged breach, but we reject its arguments regarding the meaning of Exhibit L.
¶ 27 “Summary judgment is proper where, when viewed in the light most favorable to the
nonmoving party, the pleadings, depositions, admissions, and affidavits on file reveal that there is
no genuine issue as to any material fact and that the moving party is entitled to judgment as a
matter of law.” Hernandez v. Alexian Brothers Health System, 384 Ill. App. 3d 510, 518 (2008).
“In order to survive a motion for summary judgment, the nonmoving party must come forward
with evidentiary material that establishes a genuine issue of [material] fact.” Hotze v. Daleiden,
229 Ill. App. 3d 301, 305 (1992). “The party opposing summary judgment need not prove his case
to defeat the motion, but must present some factual basis that would arguably entitle him to
judgment.” William Blair & Co., LLC v. FI Liquidation Corp., 358 Ill. App. 3d 324, 333 (2005)
(citing Flint v. Court Appointed Special Advocates of Du Page County, Inc., 285 Ill. App. 3d 152,
162 (1996)). “Our review of the trial court's grant of summary judgment is de novo.” Sacramento
Crushing Corp. v. Correct/All Sewer, Inc., 318 Ill. App. 3d 571, 574 (2000).
¶ 28 GW first argues that Bloom Bounce implicitly waived strict compliance with the June 30,
2021, possession date established by the second amended Lease by continuing to work throughout
the summer and fall of 2021 on readying the Premises for the opening of business, by having its
inflatables delivered to the Premises in August 2021, and by agreeing to continue moving forward
- 11 - Nos. 1-24-1461, 1-24-2607 (cons.)
with the Lease after GW offered to provide rent abatements at the September 2021 meeting. GW
also asserts that Bloom Bounce failed to comply with the requirement in Section 12.04 of the Lease
that Bloom Bounce provide GW with written notice of an alleged default and allow GW 30 days
to cure. However, this latter argument was not raised below in GW’s opposition to the Defendants’
motion for summary judgment and, therefore, has been forfeited. See Haudrich v. Howmedica,
Inc., 169 Ill. 2d 525, 536 (1996) (“It is well settled that issues not raised in the trial court are
deemed waived and may not be raised for the first time on appeal.”).
¶ 29 Bloom Bounce argues in response that its words or actions never suggested an intention to
waive its right to terminate the Lease under Article I(b) in the event that GW failed to deliver the
Premises in warm shell condition by the possession date. For support, Bloom Bounce recounts that
its right to do so was preserved in the enacted first and second amendments to the Lease, as well
as the proposed but unsigned third amendment, and it points to Sally’s deposition testimony
recalling that the parties held a meeting in September 2021 to discuss the work the GW still needed
to complete.
¶ 30 We agree with GW that there are genuine issues of material fact regarding waiver and that
summary judgment was, therefore, inappropriate. It is well established that “[w]hether a party's
course of conduct waives strict compliance with a contractual provision and results in forfeiture is
generally a question of fact[,] [and] such a question is unsuitable for disposition by way of
summary judgment.” Giannetti v. Angiuli, 263 Ill. App. 3d 305, 313 (1994) (citing Smith v.
Sturgeon, 35 Ill. App. 3d 750, 751 (1976)); see also Lynch Imports, Ltd. v. Frey, 200 Ill. App. 3d
781, 789 (1990) (“[T]he determination of subjective fact questions, such as waiver and intent,
strains the use of summary judgment. ‘Where the inferences which the parties seek to have drawn
- 12 - Nos. 1-24-1461, 1-24-2607 (cons.)
deal with questions of motive, intent or subjective feelings and reactions, summary judgment is
particularly inappropriate.’ ” (quoting Schuster v. East St. Louis Jockey Club, Inc., 37 Ill. App. 3d
483, 487 (1976))).
¶ 31 It is reasonable to infer from the summary judgment evidence concerning Bloom Bounce’s
actions in this case that Bloom Bounce had waived its right to terminate the Lease based on GW’s
failure to deliver possession of the Premises in warm shell condition by June 30, 2021. First, as a
simple matter, Bloom Bounce did not terminate the Lease immediately after the possession date
passed. That failure to exercise its right to terminate the Lease upon GW’s alleged failure to timely
deliver possession of the Premises in warm shell condition suggests, to some degree, an intention
to forego that right. Second, Bloom Bounce had its contractor continue to work on the Premises
throughout the summer and fall of 2021, further implying that Bloom Bounce did not intend to
enforce strict compliance with GW’s obligation to deliver possession of the Premises in warm
shell condition by June 30, 2021. Third, Bloom Bounce had its inflatables delivered to the Premises
in August 2021, again suggesting that it had declined to require strict compliance with the
provisions of Article I(b) and Section 2.03 of the Lease and intended to continue under the Lease.
Finally, Sally testified in her deposition that, following the meeting between the parties in
September 2021, Bloom Bounce explicitly agreed to move forward, and she was under the
assumption that the parties would continue with their obligations under the Lease.
¶ 32 These facts create a genuine issue of material fact that should have precluded summary
judgment in favor of Bloom Bounce. This conclusion is demonstrated by a case cited by GW,
Kitsos v. Terry's Chrysler-Plymouth, Inc., 70 Ill. App. 3d 728 (1979). In Kitsos, two parties
contracted for the sale of a car dealership. Id. at 729. The deal was to close on August 1, 1976,
- 13 - Nos. 1-24-1461, 1-24-2607 (cons.)
unless modified in writing by the parties. Id. The parties failed to close on August 1 because the
buyer was waiting for approval of its application for a franchise from Chrysler. Id. The parties did
not extend the closing date in writing, but they continued taking actions towards completion of the
contract. Id. On August 13, the seller terminated the contract for the buyer’s failure to close on
August 1. Id. at 729-30. The buyer sued the seller for breach of contract, and the circuit court
granted summary judgment in favor of the seller. Id. at 730. On appeal, this court reversed the
judgment. Id. at 731-32. We first observed that “parties to a contract may waive delays in
performance by conduct which indicates an intention to regard the contract as still in force and
effect, *** even where the contract requires that agreements to extend the date of performance
must be set forth in writing.” (Citations omitted.) Id. at 731. We then held that the parties’ actions
in continuing to move towards completion of the contract after August 1 amounted to a waiver of
the seller’s right to compel strict compliance with the August 1 closing date. Id. at 721-32.
¶ 33 The present case is no different. The possession date passed without GW tendering
possession of the Premises in warm shell condition. Yet, Bloom Bounce did not terminate the
contract in response to that alleged noncompliance, and the parties continued working towards
performance of the contract for several more months. Under these circumstances, we agree with
GW that it can be reasonably inferred that Bloom Bounce waived strict compliance with
Article I(b) and Section 2.03. The fact that the amended versions of the Lease retained Bloom
Bounce’s general right to terminate the Lease in the event of a default by GW does not negate this
conclusion that there are facts supporting GW’s assertion that Bloom Bounce waived the right to
terminate the Lease based on this specific alleged default.
- 14 - Nos. 1-24-1461, 1-24-2607 (cons.)
¶ 34 As an additional consideration within this issue, we note that Bloom Bounce also asserts
that the non-waiver provision of Section 12.02 of the Lease precluded any waiver in the absence
of such a waiver being made in writing. However, Bloom Bounce makes this argument in a
conclusory manner, inserting it as merely a part of one sentence in its conclusion of its analysis of
the waiver issue. It provides no substantive discussion of the applicability of that provision, which
is notable because “the weight of the authority in Illinois holds that Waiver Only in Writing
provisions can be waived by words and deeds of the parties, so long as the waiver is proved by
clear and convincing evidence.” Chicago College of Osteopathic Medicine v. George A. Fuller
Co., 776 F.2d 198, 202 (7th Cir. 1985) (collecting Illinois cases). Such a conclusive and
undeveloped argument, presented without further discussion or citation to authorities, is forfeited.
See Ill. S. Ct. R. 341(h)(7) (eff. Oct. 1, 2020) (requiring an argument “contain the contentions of
the [party] and the reasons therefor, with citation of the authorities and the pages of the record
relied on”); Block 418, LLC v. Uni-Tel Communications Group, Inc., 398 Ill. App. 3d 586, 590
(2010) (holding that an undeveloped two-sentence argument unsupported by relevant authority
was forfeited).
¶ 35 In its second issue, GW asserts that summary judgment was also inappropriate because
there are genuine issues of material fact regarding whether its alleged failure to timely tender
possession of the Premises in warm shell condition was a material breach justifying Bloom
Bounce’s termination of the Lease. Specifically, GW contends that Illinois law does not allow a
party to observe an alleged breach, continue performing under the contract, and then later terminate
the contract based on the prior breach without itself incurring liability. Bloom Bounce responds
- 15 - Nos. 1-24-1461, 1-24-2607 (cons.)
that the terms of the Lease gave it an absolute right to terminate the Lease at any time based on a
breach by GW. We again agree with GW.
¶ 36 “Regardless of the language used by the parties, a breach, to justify a premature
termination or forfeiture of a lease agreement, must have been material or substantial.” Wolfram
Partnership, Ltd. v. LaSalle National Bank, 328 Ill. App. 3d 207, 222-23 (2001) (citing First
National Bank of Evergreen Park v. Chrysler Realty Corp., 168 Ill. App. 3d 784, 793 (1988)). “A
breach is material where the covenant breached is one of such importance that the contract would
not have been entered into without it.” Id. (citing Galesburg Clinic Ass'n v. West, 302 Ill. App. 3d
1016, 1019 (1999), and United States Fidelity & Guaranty Co. v. Old Orchard Plaza Limited
Partnership, 284 Ill. App. 3d 765, 776 (1996)). “Because the determination of whether a breach is
‘material’ depends on the inherent justice of the matter and presents a complicated question of fact
involving consideration of several factors ***, resolution of this issue is generally not appropriate
at the summary judgment stage ***.” (Citations omitted.) Id.
¶ 37 Further, under the “partial breach doctrine,” if a party commits what the injured party
believes is a material breach and the injured party elects to continue performing under the contract,
the injured party remains bound by its obligation to perform and may not later terminate the
contract based on the prior breach without incurring liability itself. PML Development LLC v.
Village of Hawthorn Woods, 2023 IL 128770, ¶¶ 51-52. As our supreme court has explained,
“following a material breach, the injured party reaches a fork in the road: it may either
continue the contract (retain its benefits of the bargain and sue for damages) or repudiate
the agreement (cease performing and sue for damages). See [Restatement (Second) of
Contracts] § 246, cmts. a-c, illus. 1-3; [Emerald Investments Ltd. Partnership v. Allmerica
- 16 - Nos. 1-24-1461, 1-24-2607 (cons.)
Financial Life Insurance & Annuity Co., 516 F.3d 612, 618 (7th Cir. 2008)]. If the party
elects to continue with the contract, it cannot suspend performance later and then claim it
had no duty to perform based on the first material breach. This election converts the
material breach to a ‘partial’ breach. ‘[T]he injured party may sue for any damages caused
by the partial breach, but having elected to keep the contract in force, the injured party
must continue to perform the contract on pain of likewise incurring liability for a breach.’ ”
(Emphasis added, citations omitted.) PML Development, 2023 IL 128770, ¶ 52 (quoting
Dustman v. Advocate Aurora Health, Inc., 2021 IL App (4th) 210157, ¶ 38.
¶ 38 As we recounted in our discussion of the issue of waiver, the summary judgment evidence
demonstrates that, after the June 30, 2021, possession date passed without the transfer of
possession in warm shell condition, Bloom Bounce did not terminate the Lease and instead
continued to perform under the contract for more than four months. Further, Sally explicitly
acknowledged during her deposition that the September 2021 meeting of the parties resulted in an
agreement to continue with their obligations under the Lease. Accordingly, there is a genuine issue
of material fact regarding whether Bloom Bounce’s decision to continue effectively rendered
GW’s alleged breach a partial one and whether Bloom Bounce thereby forfeited its ability to
faultlessly terminate the Lease based on GW’s prior alleged breach. Therefore, summary judgment
in favor of Bloom Bounce was inappropriate on this basis as well.
¶ 39 Finally, we address the definition of “warm shell condition” contained in Exhibit L of the
Lease. Bloom Bounce contends that the provision was unambiguous and obligated GW to install
restrooms and interior lighting. GW primarily argues that Exhibit L left that responsibility to
- 17 - Nos. 1-24-1461, 1-24-2607 (cons.)
Bloom Bounce, and in the alternative it argues that the language used in Exhibit L is ambiguous.
We agree with Bloom Bounce’s view of the issue.
¶ 40 “The primary goal of contract interpretation is to give effect to the intent of the parties.”
Richard W. McCarthy Trust Dated September 2, 2004 v. Illinois Casualty Co., 408 Ill. App. 3d
526, 535 (2011) (citing Virginia Surety Co. v. Northern Insurance Co. of New York, 224 Ill. 2d
550, 556 (2007)). “In determining the intent of the parties, a court must consider the contract
document as a whole and not focus on isolated portions of the document.” Id. (citing Gallagher v.
Lenart, 226 Ill. 2d 208, 233 (2007)). “If the language of a contract is clear and unambiguous, the
intent of the parties must be determined solely from the language of the contract document itself,
which should be given its plain and ordinary meaning, and the contract should be enforced as
written.” Id. (citing Virginia Surety, 224 Ill. 2d at 556, and J.M. Beals Enterprises, Inc. v. Industrial
Hard Chrome, Ltd., 194 Ill. App. 3d 744, 748 (1990)).
¶ 41 “Contract construction and interpretation are generally well suited to disposition by
summary judgment.” William Blair & Co., 358 Ill. App. 3d at 334 (citing Bankier v. First Federal
Savings & Loan Ass'n of Champaign, 225 Ill. App. 3d 864, 869 (1992), and Continental Mobile
Telephone Co. v. Chicago S M S A Ltd. Partnership, 225 Ill. App. 3d 317, 322 (1992)). “When,
however, the language of a contract is ambiguous, its meaning must be ascertained through a
consideration of extrinsic evidence and summary judgment is, therefore, inappropriate.” Id. “A
contract term is ambiguous if it can reasonably be interpreted in more than one way due to the
indefiniteness of the language or due to it having a double or multiple meaning.” Id. (citing Zurich
Midwest, Inc. v. St. Paul Fire & Marine Insurance Co., 159 Ill. App. 3d 961, 963 (1987)). Whether
- 18 - Nos. 1-24-1461, 1-24-2607 (cons.)
a contract is ambiguous is a question of law. Id. (citing Village of Glenview v. Northfield Woods
Water & Utility Co., 216 Ill. App. 3d 40, 48 (1991)).
¶ 42 In relevant part, “Warm Shell Condition” was defined in Exhibit L as: “(i) Demised, with
all utilities and the heating, ventilation and cooling (HVAC) system stubbed to space for Tenant
distribution, drop ceiling, restrooms, plumbing and interior lighting.” The parties each take
conflicting views of the meaning of that language. GW argues that the word “Tenant” modifies all
of the words that follow it, making each subsequent listed item an obligation of Bloom Bounce. In
essence, GW reads the provision as, “Demised, with all utilities and the heating, ventilation and
cooling (HVAC) system stubbed to space for Tenant distribution, [Tenant] drop ceiling, [Tenant]
restrooms, [Tenant] plumbing and [Tenant] interior lighting.” For support, GW cites caselaw
explaining that, “[u]nder generally accepted rules of syntax, an initial modifier will tend to govern
all elements in the series unless it is repeated for each element.” Washington Education Ass'n v.
National Right to Work Legal Defense Foundation, Inc., 187 Fed. Appx. 681, 682 (9th Cir. 2006).
GW further contends that its reading is supported by the deposition testimony of Goltz and Bryant
explaining that in general trade usage the term “warm shell condition” means that the landlord
merely brings the utilities to the space for the tenant to utilize as it desires.
¶ 43 Bloom Bounce, on the other hand, contends that, because Section 2.03 of the Lease states
that the delivery of the Premises in warm shell condition shall be performed by “[GW], at [GW’s]
sole cost and expense,” it was GW’s duty to complete all of the work identified in Exhibit L. Along
those lines, Bloom Bounce also observes that, if it was its responsibility to install the drop ceiling,
bathrooms, plumbing, and interior lighting, then the inclusion of those items within a provision
- 19 - Nos. 1-24-1461, 1-24-2607 (cons.)
outlining GW’s obligations would be superfluous, which we must assume was not the parties’
intention.
¶ 44 We do not view the provision as ambiguous and believe that the only reasonable
interpretation is that GW was responsible for installing restrooms and interior lighting. When
interpreting a contract, we must construe the document as a whole. Richard W. McCarthy Trust,
408 Ill. App. 3d at 535 (citing Gallagher, 226 Ill. 2d 233). Accordingly, the meaning of Exhibit L
must be considered within the context of Section 2.03’s statement that it was GW’s sole obligation
to deliver the Premises in warm shell condition. With that in mind, we cannot agree with GW’s
argument that the listed items were Bloom Bounce’s responsibility. As Bloom Bounce points out,
if that were the case, then there would be no reason to include those items in the definition of warm
shell condition, the accomplishment of which was GW’s sole duty. In other words, there would be
no functional difference if the definition simply stated, “Demised, with all utilities and the heating,
ventilation and cooling (HVAC) stubbed to space for Tenant distribution,” and that result would
run afoul of the principle that “it must be assumed that every provision was intended to serve a
purpose.” Central Illinois Light Co. v. Home Insurance Co., 213 Ill. 2d 141, 153 (2004) (citing
Martindell v. Lake Shore National Bank, 15 Ill. 2d 272, 283 (1958)). Instead, the more logical and
reasonable reading of the definition is that the list set forth the specific items that GW alone was
to install to place the Premises in warm shell condition.
¶ 45 Further, we are not persuaded by GW’s argument that the word “Tenant” was a modifier
that applied to each item in the subsequent list. Rather than being the beginning of a series, the
utilities and HVAC system being stubbed for tenant distribution was itself a single item in a larger
list of items that were to be present in the Premises, a list that began with “Demised, with.” In
- 20 - Nos. 1-24-1461, 1-24-2607 (cons.)
other words, the Premises were to be “Demised, with all utilities and the heating, ventilation and
cooling (HVAC) system stubbed to space for Tenant distribution,” and further “Demised, with ***
drop ceiling, restrooms, plumbing and interior lighting.”
¶ 46 We also do not believe that the testimony of Goltz and Bryant regarding the trade usage of
the term “warm shell condition” should alter our interpretation of Exhibit L. Both testified that
warm shell condition generally only requires the landlord to stub utilities to the space for the tenant
to utilize in the manner it desires. However, Bryant, Neavolls, and Kane each testified that the term
was not used consistently in the industry and that the meaning of the term varied from case to case.
Further, as we have discussed, the plain language of the definition provided by the parties in this
particular case made it GW’s responsibility to install drop ceilings, restrooms, plumbing, and
interior lighting, and trade usage cannot be considered when it contradicts the plain language of
an unambiguous contract. See Illinois Insurance Guaranty Fund v. Nwidor, 2018 IL App (1st)
171378, ¶ 33 (“It is quite established that evidence of custom and usage is only admissible to
explain uncertain or ambiguous terms of a contract. When contract terms are clear, those terms
alone determine the obligations of the parties.”).
¶ 47 To the extent that GW argues that the listed items could not have been its obligation
because Exhibit L did not provide necessary details, such as the specific locations, quality, and
quantities of the listed items, we find it implicit that such details were to be provided to GW by
Bloom Bounce. In the event that Bloom Bounce failed to provide such information, which appears
to have been the case regarding the interior lighting, then GW’s failure to install the item at issue
would have been excused. See Empress Casino Joliet Corp. v. Averus, Inc., 2020 IL App (1st)
192071, ¶ 41 (“A party whose actions preclude performance by the other party may not complain
- 21 - Nos. 1-24-1461, 1-24-2607 (cons.)
of the second party's nonperformance.”); Cenco Inc. v. Seidman & Seidman, 686 F.2d 449, 453
(7th Cir. 1982) (“A breach of contract is excused if the promisee's hindrance or failure to cooperate
prevented the promisor from performing the contract.”).
¶ 48 As a final matter, we note that our conclusion that there are issues of fact precluding
summary judgment on the issue of Bloom Bounce’s liability for breach of contract also
necessitates the reversal of the circuit court’s judgment on GW’s guaranty claim against Sally and
Jeremy, as their liability is directly linked to Bloom Bounce’s.
¶ 49 For the foregoing reasons, we reverse the circuit court’s order granting the Defendants’
motion for summary judgment, and we remand the matter for further proceedings consistent with
this order.
¶ 50 Reversed and remanded.
- 22 -