Sacramento Crushing Corp. v. Correct/All Sewer, Inc.

CourtAppellate Court of Illinois
DecidedDecember 29, 2000
Docket1-99-0882, 1-00-2313 cons. Rel
StatusPublished

This text of Sacramento Crushing Corp. v. Correct/All Sewer, Inc. (Sacramento Crushing Corp. v. Correct/All Sewer, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sacramento Crushing Corp. v. Correct/All Sewer, Inc., (Ill. Ct. App. 2000).

Opinion

No. 1-99-0882 First Division

      1-00-2313        December 29, 2000

SACRAMENTO CRUSHING CORPORATION, ) Appeal from the

Plaintiff, ) Circuit Court of

) Cook County.

v. )

)

CORRECT/ALL SEWER, INC.; E.A. COX )

COMPANY; THE CITY OF CHICAGO, ) 96 CH 198, 96 CH 12924,

DEPARTMENT OF TRANSPORTATION, and ) 96 CH 14213, 96 CH 2255,

FIDELITY AND DEPOSIT COMPANY OF ) 96 CH 2441, 96 CH 3547,

MARYLAND, Defendants ) 96 CH 3549, 96 CH 3560,

) 97 CH 12500

(Correct/All Sewer, Inc., Cross-Plaintiff and )

Counterdefendant, Appellant, )

) The Honorable

E.A. Cox Company, Cross-Defendant and ) Cyril Watson,

Counterplaintiff, Appellee.) ) Judge Presiding.

JUSTICE COHEN delivered the opinion of the court:

Defendant-Appellee E.A. Cox Company (Cox) served as general contractor on a road construction project (the project) for the City of Chicago Department of Transportation (the City).  Defendant-appellant Correct/All Sewer, Inc. (Correct/All) was Cox's sewer subcontractor for the project.  Defendant Fidelity and Deposit Company of Maryland (Fidelity) provided Cox's surety bond.  Nine subcontractors and/or material suppliers filed complaints against Cox and Correct/All for mechanics' liens against public funds pursuant to section 23 of the Mechanics Lien Act (770 ILCS 60/23 (West 1998)) and for bond claims against Fidelity and Cox pursuant to section 1 if the Public Construction Bond Act (30 ILCS 550/1 (West 1998)).  The trial court consolidated all nine cases into Sacramento Crushing Corporation v. Correct/All Sewer, Inc., 96 CH 198.  Once consolidated, no order of severance was ever entered with respect to any of these cases.

Correct/All cross-claimed against Cox and Fidelity, asserting mechanic's lien and bond claims.  Cox moved to reduce the amount of Correct/All's lien, seeking a summary determination under section 2-1005(d) of the Code of Civil Procedure (735 ILCS 5/2-1005(d) (West 1998)) that Correct/All was not entitled to a separate pay item of $170,025.75 for "spoil removal" (waste hauling).  In an order dated December 3, 1997 (the summary determination order), the trial court granted Cox summary determination as to the spoil removal issue.  Correct/All's motion for reconsideration of the summary determination order was denied. Cox and Fidelity then moved for summary judgment under Section 2-1005(b) of the Code of Civil Procedure, requesting a ruling that Correct/All was owed nothing further on the project.  On September 3, 1998, the trial court granted their motion (the first summary judgment order), finding that Correct/All was owed nothing further on the road construction project and ruling that Correct/All had no valid mechanic's lien or bond claims.  On January 28, 1999, the trial court entered a Rule 304(a) (134 Ill. 2d R. 304(a)) finding with respect to the first summary judgment order.  Correct/All filed its timely notice of appeal on March 2, 1999.

Cox counterclaimed against Correct/All to recover certain "backcharges" ( i.e. , money that Cox had spent on Correct/All's behalf).  Cox moved for summary judgment against Correct/All on the issue of backcharges.  On May 2, 2000, the trial court granted Cox's motion, entering judgment in favor of Cox in the amount of $312,346.02 plus costs (the second summary judgment order).  The court also entered a Rule 304(a) finding with respect to this order.  Correct/All's motion to reconsider was denied.  The same day, the trial court entered an order dismissing with prejudice all claims and causes of action filed in the nine consolidated cases that had not been disposed of by prior order.  Correc/All's motion to reconsider the second summary judgment order was denied.  Correct/All filed its second timely notice of appeal on July 13, 2000.

Correct/All's first appeal, case no. 1-99-0882, is from the trial court's summary determination order and the first summary judgment order.  Correct/All's second appeal, case no. 1-00-2313, is from the second summary judgment order and the denial of its motion to reconsider.  Cox has moved on appeal for sanctions against Correct/All and its counsel, Mr. Lamont Cranston Strong (Strong).  Cox has also moved for the reconsideration of our previous order consolidating this case with Correct/All's second appeal.  Cox's motions are taken with the case.  We affirm the judgment of the trial court, deny Cox's motion for reconsideration and grant Cox's motion for sanctions.

I. Summary Determination, Summary Judgment and the Motion to Reconsider

We note as a preliminary matter that there is currently an order of this court on file, dated October 3, 2000, consolidating this case (Correct/All's appeal under Rule 304(a) from the trial court's entry of summary determination and summary judgment in favor of Cox and against Correct/All on Correct/All's amended cross-claim) with case no. 1-00-2313 (Correct/All's appeal from the trial court's entry of summary judgment in favor of Cox and against Correct/All on Cox's counterclaim for backcharges and from the denial of Correct/All's motion to reconsider) .  Cox has moved for reconsideration of the order granting consolidation.  Case no. 1-99-0882 has already been fully briefed, and the issues in the two appeals are nearly identical.  No briefs have yet been filed in case no. 1-00-2313; however, we require no briefs from the parties to guide our decision.    As we will further discuss, the record on appeal in the second case, standing alone, affords us a sufficient basis to rule on Correct/All's second appeal.  Cox's motion for reconsideration is denied.

Although the trial court entered no Rule 304(a) finding with respect to the summary determination order of December 3, 1997, that order was a step in the procedural progression leading to the summary judgment order of September 3, 1998.  Therefore, Correct/All's notice of appeal was sufficient to grant this court jurisdiction over the summary determination order.  155 Ill. 2d R. 304(a); Ruane v. Amore , 287 Ill. App. 3d 465, 470 (1997).   

Our review of the trial court's grant of summary judgment is de novo .   Natale v. Gottlieb Memorial Hospital., 314 Ill. App. 3d 885, 888 (2000).  Summary judgment is properly granted "where the pleadings, affidavits, depositions, admissions, and exhibits on file, when viewed in the light most favorable to the nonmovant, reveal that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law."   Natale , 314 Ill. App. 3d at 888.  In its first appeal, Correct/All argues that the trial court’s summary determination order reducing its claimed lien violated both an unspecified section of the Chicago Municipal Code and the separation of powers doctrine.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCullough v. Gallaher & Speck
627 N.E.2d 202 (Appellate Court of Illinois, 1993)
Joel R. by Salazar v. Board of Educ. of Mannheim Sch. Dist.
686 N.E.2d 650 (Appellate Court of Illinois, 1997)
47th & State Currency Exchange, Inc. v. B. Coleman Corp.
371 N.E.2d 294 (Appellate Court of Illinois, 1977)
Malanowski v. Jabamoni
688 N.E.2d 732 (Appellate Court of Illinois, 1997)
In Re Marriage of Palacios
656 N.E.2d 107 (Appellate Court of Illinois, 1995)
Soderlund Bros., Inc. v. Carrier Corp.
663 N.E.2d 1 (Appellate Court of Illinois, 1995)
In Re Marriage of Lewis
572 N.E.2d 1246 (Appellate Court of Illinois, 1991)
Korogluyan v. Chicago Title and Trust Co.
572 N.E.2d 1154 (Appellate Court of Illinois, 1991)
Kennedy v. Miller
555 N.E.2d 105 (Appellate Court of Illinois, 1990)
Fitzpatrick v. Human Rights Commission
642 N.E.2d 486 (Appellate Court of Illinois, 1994)
Natale v. Gottlieb Memorial Hospital
733 N.E.2d 380 (Appellate Court of Illinois, 2000)
People Ex Rel. Brzica v. Village of Lake Barrington
644 N.E.2d 66 (Appellate Court of Illinois, 1994)
Ruane v. Amore
677 N.E.2d 1369 (Appellate Court of Illinois, 1997)
Lewanski v. Lewanski
375 N.E.2d 961 (Appellate Court of Illinois, 1978)
Werckenthein v. Bucher Petrochemical Co.
618 N.E.2d 902 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Sacramento Crushing Corp. v. Correct/All Sewer, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/sacramento-crushing-corp-v-correctall-sewer-inc-illappct-2000.