Holy Family Catholic Congregation v. Stubenrauch Associates, Inc.

402 N.W.2d 382, 136 Wis. 2d 515, 1987 Wisc. App. LEXIS 3352
CourtCourt of Appeals of Wisconsin
DecidedJanuary 27, 1987
Docket86-0242
StatusPublished
Cited by18 cases

This text of 402 N.W.2d 382 (Holy Family Catholic Congregation v. Stubenrauch Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Holy Family Catholic Congregation v. Stubenrauch Associates, Inc., 402 N.W.2d 382, 136 Wis. 2d 515, 1987 Wisc. App. LEXIS 3352 (Wis. Ct. App. 1987).

Opinion

CANE, P.J.

Holy Family Catholic Congregation appeals a summary judgment dismissing its complaint against Stubenrauch Associates, Inc., and Hoffman Company, Inc., the architect and general contractor for the congregation’s church building. The circuit court found that sec. 893.89, Stats., barring actions begun more than six years after "substantial completion” of real estate improvements, rendered Holy Family’s suit untimely. 1

*518 Holy Family first contends that the circuit court erred by concluding as a matter of law that the statutory period began to run on the date the congregation held its first service in the new building. Instead, Holy Family submits that "substantial completion of construction” under sec. 893.89 should not occur until "the last of the designers, planners and contractors [have] ceased furnishing their services pursuant to the contract,” providing their performance has met the essential purpose of the contract on that date. Holy Family next asserts that the statute is inapplicable because the building’s leaky roof prevented construction from ever being considered substantially completed. Finally, Holy Family argues that the six-year limitation should begin to run when the defect is discovered, not upon substantial completion of construction.

We conclude that sec. 893.89 governs the facts of this case and that, as a matter of law, substantial completion of construction occurred on the date of the congregation’s first service in the new building. We further conclude as a matter of law that Holy Family discovered the defect more than six years before filing suit. Therefore, we affirm the circuit court’s summary judgment dismissing the action.

The parties agree on the material facts. In June, 1976, Holy Family contracted with Stubenrauch for *519 architectural services for the construction of a new church building. In April, 1977, Holy Family contracted with Hoffman, who agreed to serve as prime contractor for the project. Construction ensued and on March 7, 1978, Stubenrauch issued a certificate of substantial completion. This certificate, issued pursuant to Stubenrauch’s contract with Holy Family, followed Stubenrauch’s February 28 inspection of the church building. It stated that February 28,1978, was the substantial completion date for purposes of lien release and consent of surety to final payment.

Holy Family held its first worship service in the new building on March 28,1978. In the ensuing weeks, members of the congregation noticed that the church’s roof leaked. Holy Family’s brief stated, "[t]he church members agree that the church roof leaked during the spring of 1978, and that officials from Stubenrauch and Hoffman knew of the leaks immediately thereafter.” These complaints were documented in a June 28, 1978, report issued by one of Stubenrauch’s employees.

Various subcontractors made apparently unsuccessful attempts to remedy the roof leaks. Holy Family made its final payments to Stubenrauch and Hoffman on April 17, 1979.

Holy Family filed suit on August 16, 1984. Stu-benrauch and Hoffman subsequently moved for summary judgment, contending that the statute of limitations barred Holy Family’s action. The circuit court granted summary judgment, finding that Holy Family commenced suit more than six years after construction of its church had been substantially completed.

We review the circuit court’s summary judgment construing sec. 893.89. On review of a summary *520 judgment, we apply the same standards as the trial court. Messner v. Briggs & Stratton Corp., 120 Wis. 2d 127, 131, 353 N.W.2d 363, 365 (Ct. App. 1984). Summary judgment is appropriate if the pleadings, depositions, answers to interrogatories and admissions on file, together with any affidavits, show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. Id.; sec. 802.08(2), Stats. Because the parties agree on the material facts, the first summary judgment criterion is met. Construing a statute in relation to a given set of facts is a question of law. Tahtinen v. MSI Insurance Co., 122 Wis. 2d 158, 166, 361 N.W.2d 673, 677 (1985). Thus, we decide the second criterion, whether the statute as applied to the facts entitles Stubenrauch and Hoffman to summary judgment as a matter of law, without special deference to the circuit court’s decision. See id.

We first conclude that the circuit court correctly applied sec. 893.89 as the limitation on this action. Section 893.89, commonly referred to as a "builder’s statute,” governs "actionfs] to recover damages for any injury to property, ... arising out of the defective and unsafe condition of an improvement to real property_” The statute plainly includes an action to recover damages for a leaky roof on a newly constructed church. Having made this preliminary determination, we move on to issues raised by the parties.

Holy Family first contends that the phrase, "substantial completion of construction,” describing the event that triggers sec. 893.89’s six-year limitation period, is ambiguous. Assuming ambiguity, Holy Family asserts that substantial completion of construction *521 should be defined as the date the last of the designers, planners, and contractors cease furnishing their services pursuant to the contract, providing their performance meets the essential purpose of the contract on that day. We agree that the statutory language is ambiguous, but we reject Holy Family’s proposed definition of substantial completion of construction.

A statute is ambiguous if it is capable of being construed in two different ways by reasonably well-informed persons. Kollasch v. Adamany, 104 Wis. 2d 552, 561, 313 N.W.2d 47, 51-52 (1981). However, ambiguity does not arise merely because adverse parties disagree on a statute’s meaning. See Aero Auto Parts, Inc. v. Department of Transportation, 78 Wis. 2d 235, 238-39, 253 N.W.2d 896, 897 (1977). We must examine the statute’s language to determine if the parties are justified in their disparate views. Id.

Here, the statute offers no definition for "substantial completion of construction.” The word "substantial,” commonly defined as being "largely but not wholly that which is specified,” 2 suggests that the period begins to run some time before final completion. Precisely when substantial completion occurs, however, cannot be discerned from the face of the statute. The vagueness of the word "substantial,” without further definition, justifiably invites the parties to disagree as to the time the church was largely, but not wholly, completed. We thus conclude that the statute is ambiguous. Accordingly, we must look beyond its words to determine its meaning.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Wascher v. Carved Stone Creations
Court of Appeals of Wisconsin, 2022
Hensel Phelps Construction Co. v. Super. Ct.
California Court of Appeal, 2020
Flaminio v. Mclain
E.D. Wisconsin, 2019
Caldwell v. JH FINDORFF & SON, INC.
698 N.W.2d 132 (Court of Appeals of Wisconsin, 2005)
ARBOR VITAE-WOODRUFF JOINT SCH. DIST. v. Gulf Ins. Co.
2002 WI App 24 (Court of Appeals of Wisconsin, 2001)
Arbor Vitae-Woodruff Joint School District No.1 v. Gulf Insurance Co.
2002 WI App 24 (Court of Appeals of Wisconsin, 2001)
LAKEVIEW v. Apartment Sales Corp.
6 P.3d 74 (Court of Appeals of Washington, 2000)
1519-1525 Lakeview Boulevard Condominium Ass'n v. Apartment Sales Corp.
101 Wash. App. 923 (Court of Appeals of Washington, 2000)
State v. Richard Knutson, Inc.
537 N.W.2d 420 (Court of Appeals of Wisconsin, 1995)
Currier v. Holden
862 P.2d 1357 (Court of Appeals of Utah, 1993)
Young Radiator Co. v. Celotex Corp.
881 F.2d 1408 (Seventh Circuit, 1989)
Hartland-Richmond Town Insurance v. Wudtke
429 N.W.2d 496 (Court of Appeals of Wisconsin, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
402 N.W.2d 382, 136 Wis. 2d 515, 1987 Wisc. App. LEXIS 3352, Counsel Stack Legal Research, https://law.counselstack.com/opinion/holy-family-catholic-congregation-v-stubenrauch-associates-inc-wisctapp-1987.