Chula Vista, Inc. v. Architectural Design Consultants, Inc.

CourtCourt of Appeals of Wisconsin
DecidedJuly 21, 2022
Docket2021AP000971
StatusUnpublished

This text of Chula Vista, Inc. v. Architectural Design Consultants, Inc. (Chula Vista, Inc. v. Architectural Design Consultants, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chula Vista, Inc. v. Architectural Design Consultants, Inc., (Wis. Ct. App. 2022).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. July 21, 2022 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2021AP971 Cir. Ct. No. 2017CV456

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

CHULA VISTA, INC.,

PLAINTIFF-APPELLANT,

V.

ARCHITECTURAL DESIGN CONSULTANTS, INC.,

DEFENDANT-THIRD-PARTY PLAINTIFF-RESPONDENT.

APPEAL from an order of the circuit court for Sauk County: PATRICIA A. BARRETT, Judge. Affirmed.

Before Blanchard, P.J., Kloppenburg, and Graham, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3). No. 2021AP971

¶1 PER CURIAM. Chula Vista, Inc., appeals the circuit court’s order dismissing its claims against Architectural Design Consultants, Inc., on summary judgment. The issue is whether the circuit court erred by concluding that Chula Vista’s claims are barred by the ten-year statute of repose in WIS. STAT. § 893.89 (2015-16).1 We conclude that the circuit court properly dismissed Chula Vista’s claims based on the statute of repose. Accordingly, we affirm.

¶2 The relevant background facts are straightforward and undisputed. Chula Vista contracted with Architectural Design to design an indoor water park facility. The construction of the facility was completed no later than July 1, 2006. Approximately one year later, Chula Vista discovered that a vapor barrier was missing or had not been properly installed according to Architectural Design’s specifications. Because the construction of the facility was by then complete, it was no longer feasible to install the vapor barrier as specified. Architectural Design worked with Chula Vista’s general contractor to install spray foam insulation instead. The spray foam project was completed by December 4, 2007.

¶3 On October 11, 2017, Chula Vista filed suit against Architectural Design, alleging that Architectural Design breached its duty of care in overseeing the spray foam project. Architectural Design moved for summary judgment, arguing that Chula Vista’s claims were barred by the statute of repose in WIS. STAT. § 893.89. Most pertinent here, the statute provides that “no cause of action may accrue and no action may be commenced … against … any person involved in the

1 All references to the Wisconsin Statutes are to the 2015-16 version unless otherwise noted. In a footnote in its brief, Architectural Design asserts that a newer version of the statute with a seven-year time limit applies retroactively to Chula Vista’s claims. We assume, without deciding, that the 2015-16 version containing the ten-year time limit applies.

2 No. 2021AP971

improvement to real property after the end of the exposure period,” and the “exposure period” is defined as “10 years immediately following the date of substantial completion of the improvement to real property.” Section 893.89(1)- (2).2

¶4 The circuit court concluded that Chula Vista’s suit is barred by the statute of repose because the construction of the water park facility was substantially complete in 2006, more than ten years before Chula Vista filed suit. On this ground, the court granted Architectural Design’s motion for summary judgment and dismissed Chula Vista’s claims. Chula Vista now appeals.

¶5 We review summary judgment de novo, applying the same standards as the circuit court. Schauer v. Baker, 2004 WI App 41, ¶4, 270 Wis. 2d 714, 678 N.W.2d 258. “Summary judgment is appropriate when there is no material factual dispute and the moving party is entitled to judgment as a matter of law.” Id. The interpretation and application of a statute to a given set of facts is likewise a question

2 WISCONSIN STAT. § 893.89(1) and (2) provide in full as follows:

(1) In this section, “exposure period” means the 10 years immediately following the date of substantial completion of the improvement to real property.

(2) Except as provided in sub. (3), no cause of action may accrue and no action may be commenced, including an action for contribution or indemnity, against the owner or occupier of the property or against any person involved in the improvement to real property after the end of the exposure period, to recover damages for any injury to property, for any injury to the person, or for wrongful death, arising out of any deficiency or defect in the design, land surveying, planning, supervision or observation of construction of, the construction of, or the furnishing of materials for, the improvement to real property. This subsection does not affect the rights of any person injured as the result of any defect in any material used in an improvement to real property to commence an action for damages against the manufacturer or producer of the material.

3 No. 2021AP971

of law for our de novo review. Pritchard v. Madison Metro. Sch. Dist., 2001 WI App 62, ¶7, 242 Wis. 2d 301, 625 N.W.2d 613.

¶6 Chula Vista argues that the circuit court erred in its application of the statute of repose. It contends that the ten-year exposure period for its claims ran from completion of the spray foam project in December 2007. According to Chula Vista, that project is a separate project with a separate exposure period for claims arising out of that project. Chula Vista focuses on the statutory language providing that the exposure period commences upon substantial completion of “the improvement to real property,” see WIS. STAT. § 893.89(1), and it argues that the spray foam project was itself an “improvement to real property” as defined in Peter v. Sprinkmann Sons Corp., 2015 WI App 17, 360 Wis. 2d 411, 860 N.W.2d 308. In Peter, we stated that an “improvement to real property” for purposes of the statute means “‘[a] permanent addition to or betterment of real property that enhances its capital value and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.’” Id., ¶22 (quoting Kohn v. Darlington Cmty. Schs., 2005 WI 99, ¶17, 283 Wis. 2d 1, 698 N.W.2d 794). We further stated in Peter that “the initial installation of insulation into a building or house may be considered an improvement to real property.” Id., ¶24.

¶7 Architectural Design counters that the circuit court properly concluded that the exposure period for Chula Vista’s claims commenced upon substantial completion of the water park facility in 2006. It relies on this court’s decision in Holy Family Catholic Congregation v. Stubenrauch Assocs., Inc., 136 Wis. 2d 515, 402 N.W.2d 382 (Ct. App. 1987). Architectural Design argues that under the reasoning in Holy Family, the spray foam project cannot give rise to a new or delayed exposure period because the purpose of the spray foam project was

4 No. 2021AP971

to correct the missing or improperly installed vapor barrier in the underlying building project.

¶8 We agree with Architectural Design. Holy Family involved a newly constructed building with a faulty roof. Id. at 519. We rejected the property owner’s argument that the building was not substantially complete until the roof was repaired. Id. at 525. More importantly for purposes here, we concluded in Holy Family that WIS. STAT. § 893.89 should not be construed to delay the commencement of the exposure period until remedial services are complete. Holy Family, 136 Wis. 2d at 522.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pritchard v. Madison Metropolitan School District
2001 WI App 62 (Court of Appeals of Wisconsin, 2001)
Kohn v. Darlington Community Schools
2005 WI 99 (Wisconsin Supreme Court, 2005)
Holy Family Catholic Congregation v. Stubenrauch Associates, Inc.
402 N.W.2d 382 (Court of Appeals of Wisconsin, 1987)
Schauer v. Baker
2004 WI App 41 (Court of Appeals of Wisconsin, 2004)
Peter v. Sprinkmann Sons Corp.
2015 WI App 17 (Court of Appeals of Wisconsin, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Chula Vista, Inc. v. Architectural Design Consultants, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/chula-vista-inc-v-architectural-design-consultants-inc-wisctapp-2022.