ARBOR VITAE-WOODRUFF JOINT SCH. DIST. v. Gulf Ins. Co.
This text of 2002 WI App 24 (ARBOR VITAE-WOODRUFF JOINT SCH. DIST. v. Gulf Ins. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
ARBOR VITAE-WOODRUFF JOINT SCHOOL DISTRICT NO. 1, Plaintiff-Respondent,
v.
GULF INSURANCE COMPANY, a foreign corporation, Defendant-Appellant,
TEMPERATURE CONTROL CORPORATION, a Wisconsin corporation, Defendant.
Court of Appeals of Wisconsin.
*640 On behalf of the defendant-appellant, the cause was submitted on the briefs of Bruce Gillman and Boardman, Suhr, Curry & Field LLP of Madison.
On behalf of the plaintiff-respondent, the cause was submitted on the brief of Mary Sue Anderson and Ruder, Ware & Michler, a Limited Liability S.C. of Wausau.
Before Cane, C.J., Hoover, P.J., and Peterson, J.
¶ 1. HOOVER, P.J.
Gulf Insurance Company appeals a judgment declaring timely the action brought against it by Arbor Vitae-Woodruff Joint School District No. 1 and allowing it to proceed. WISCONSIN STAT. § 779.14(2)[1] allows an injured party to directly sue the surety on a public works bond within a year of the "completion of work under the contract." Gulf contends that § 779.14(2), a statute of limitations, precludes the claim because it was not brought within one year of the completion of work. At issue is when work was completed under the contract. We conclude that the statute of limitations began to run on the date Temperature Control Corporation (TCC), the contractor for which Gulf is a surety, completed its work. The parties stipulated that TCC did no work on the project after December *641 16, 1998. Therefore, the district's February 7, 2000, suit was filed more than a year after TCC completed its work under the contract. We reverse the judgment and remand for the entry of judgment in favor of Gulf.
BACKGROUND
¶ 2. In 1997, the school district began construction on a new elementary school. The district entered into a written contract with TCC on June 20, 1997. TCC agreed to install the heating, venting and air-conditioning system in the new elementary school, and Gulf issued a surety bond for TCC.
¶ 3. TCC performed the work on the elementary school. It submitted its final application for payment on December 22, 1998. TCC did no work at the school after it submitted the application. On February 8, 1999, the district's architect certified that TCC completed its work and approved TCC's final payment request.
¶ 4. The district discovered problems with the heating, venting and air-conditioning system in June 1999. Gulf communicated with the district and requested documents to ascertain whether it was liable under TCC's performance bond. Gulf advised that its attorney would contact the district after it reviewed the documents, but, "In the meantime, the School District should feel free to do whatever is necessary to mitigate its damages in this matter."
¶ 5. On January 3, 2000, Gulfs attorney sent a letter to the district denying liability under the surety bond, claiming that the one-year statute of limitations under WIS. STAT. § 779.14(2) had expired. The district filed an action requesting declaratory relief on February 7, 2000. It asked the trial court to declare that the statute of limitations for claims under the surety bond *642 began to run on February 8, 1999, the date the district's architect accepted the work under the contract as complete and certified final payment to TCC.
¶ 6. The trial court granted declaratory judgment in the district's favor. It found ambiguous the phrase, "completion of work under the contract," in WIS. STAT. § 779.14(2). It then (1) looked to legislative history and (2) interpreted the contract between the parties. The court concluded that the statute of limitations began to run on February 8, 1999, when the district's architect accepted TCC's work as complete and authorized final payment. Gulf now appeals.
STANDARD OF REVIEW
[1-4]
¶ 7. The interpretation of a statute and its application to a set of facts are questions of law we review de novo. Reyes v. Greatway Ins. Co., 227 Wis. 2d 357, 364-65, 597 N.W.2d 687 (1999). "The purpose of statutory interpretation is to discern the intent of the legislature." Id. at 365. To determine intent, we look to the plain language of the statute. Id. A "statute is ambiguous if it is capable of being understood by a reasonably well-informed person in either of two senses." Id. If the language of the statute renders legislative intent ambiguous, we resort to judicial construction. Id.
DISCUSSION
[5]
¶ 8. As indicated, WIS. STAT. § 779.14(2) allows an injured party to directly sue the surety on a public works bond within a year of the "completion of work *643 under the contract." Gulf contends that § 779.14(2) is ambiguous and that legislative intent proves that "completion of work under the contract" occurs when a contractor has completed the work described in the contract. The district argues that the words, "under the contract," refer the parties to their contract to determine when the work was completed. The district argues that the work was complete under the contract when its architect accepted the work and approves final payment to TCC. We conclude that the statute is ambiguous.
¶ 9. WISCONSIN STAT. § 779.14(2) provides no definition for its operative phrase, "completion of work under the contract." Precisely when work is completed under the contract cannot be discerned from the face of the statute. This phrase may be interpreted as the time when the contractor finishes the work it agreed to do in the contract. Or it may be interpreted as the time when the contractor's work has been accepted by the district's architect. A reasonably well-informed person could understand the statute in either sense. Thus, we deem the statute ambiguous and look beyond its words to determine its meaning.[2]
[6, 7]
¶ 10. We examine the "scope, history, context, subject matter, and object" of ambiguous statutory language to discern the legislature's intent. Reyes, 227 Wis. 2d at 366-67. Because the legislature's intent *644 cannot be discerned from the statute itself, we turn to the legislative history of WIS. STAT. § 779.14(2) to see if it clarifies the meaning of the statute. See Milwaukee Cty. v. LIRC, 113 Wis. 2d 199, 204, 335 N.W.2d 412 (Ct. App. 1983).
[8]
¶ 11. Prior to 1935, an action on a public works bond had to be commenced "within one year after the completion and acceptance of said contract." WIS. STAT. § 289.16(2) (1925) (emphasis added). In Pittman v. Lieffring, 59 Wis. 2d 52, 64, 207 N.W.2d 610 (1973), our supreme court stated, "Generally, the studied omission of a word or words in the re-enactment or revision of a statute indicates an intent to alter its meaning." In 1935, LAWS OF 1935 ch. 483, the legislature deleted the words, "and acceptance," and signaled its intent to change the statute of limitations trigger from acceptance and payment, which can arbitrarily be delayed by one party, to completion of work.[3]
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2002 WI App 24, 639 N.W.2d 788, 250 Wis. 2d 637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arbor-vitae-woodruff-joint-sch-dist-v-gulf-ins-co-wisctapp-2001.