Milwaukee Area Vocational Technical and Adult Education District v. United States Steel Corporation

847 F.2d 435, 1988 U.S. App. LEXIS 7391, 1988 WL 54310
CourtCourt of Appeals for the Seventh Circuit
DecidedJune 1, 1988
Docket87-1553
StatusPublished
Cited by4 cases

This text of 847 F.2d 435 (Milwaukee Area Vocational Technical and Adult Education District v. United States Steel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Milwaukee Area Vocational Technical and Adult Education District v. United States Steel Corporation, 847 F.2d 435, 1988 U.S. App. LEXIS 7391, 1988 WL 54310 (7th Cir. 1988).

Opinion

MANION, Circuit Judge.

Plaintiff, Milwaukee Area Vocational Technical and Adult Education District (MATC), brought this action against United States Steel Corporation (USS) 1 for the cost of replacement and repair of steel used in the construction of MATC’s campus buildings. USS moved for summary judgment on the ground that MATC’s claim was time-barred. The district court granted the motion and MATC appeals. We affirm.

I.

In the mid-1970’s, MATC commenced extensive construction projects involving the *436 construction of its North Campus Center, its South Campus Center, and an addition to its West Campus Center. The specifications for all three buildings called for the use of “weathering steel” in the construction of the buildings’ roofs and portions of the exterior walls. The specifications for the “weathering steel” were nearly identical for all three buildings. The brand of “weathering steel” actually used in the construction was Cor-Ten steel manufactured by USS. The construction at the North Campus Center and South Campus Center was substantially completed in July, 1976. The construction at the West Campus Center was substantially completed by November, 1977.

In December, 1978, MATC discovered unusual rusting and staining of the Cor-Ten steel at its North Campus Center. Two architects employed by MATC, James Pauers (MATC’s Manager of Construction Services) and Lawrence Earll (a consulting architect) investigated the problem. A memorandum by MATC’s consulting architect dated February 8, 1979, stated that “[investigation has revealed that [Cor-Ten] steel of this g[au]ge can rust thru unless back painted.” The memo concluded:

Review of the shop drawing draws the conclusion that it is a “poor design” of the gutter installation that is contributing to the rusting of the soffit panels. The estimated cost to correct the problems is $60,000.00. This would include the removal of all the gutters; replacing those soffit panels indicating rusting action; caulking at the joining of the soffit panel to the fascia panel; and reinstalling the gutter.

Another document prepared for MATC in February, 1979, stated that the solution to the problem “is to remove all of the drip/gutters; replace defective panels, caulk at the intersection of the soffit and fascia [panels], and reinstall the drip/gutter,” and that “MATC concluded that this was a poorly designed detail.” The memo also noted that the problem with the rusting of the Cor-Ten steel was not observed at the South Campus Center.

The project architects, whom MATC thought shouldered the “probable responsibility” for the problem, conducted their own investigation. In a letter dated July 3, 1979, the project architects noted, among other things, that the Cor-Ten steel needed additional weathering.

Despite having notice of the unusual rusting and staining in December, 1978, MATC waited until March, 1985, to bring this action. MATC’s complaint, naming USS as the sole defendant, alleged that the Cor-Ten supplied by USS was defective, that USS knew or should have known that the Cor-Ten was subject to excessive corrosion and deterioration, that USS negligently failed to disclose that the Cor-Ten was defective, and that the defective Cor-Ten was unreasonably dangerous to MATC’s property, employees, and students. USS moved for summary judgment on the ground that MATC’s action was barred by the six-year limitation period contained in WIS.STAT.ANN. § 893.52 2 (West 1983). The district court granted USS's motion. 3

II.

ANALYSIS

WIS.STAT.ANN. § 893.52 (West 1983) places a six-year limitations period on ac *437 tions “not arising on contract, to recover damages for an injury to real or personal property_” Under § 893.52, the statute of limitations begins to run “after [a] cause of action accrues.” Thus, we must affirm the district court’s grant of summary judgment if the undisputed facts establish that MATC’s action accrued more than six years before it filed its complaint in March, 1985.

In Wisconsin Natural Gas Co. v. Ford, Bacon & Davis Construction Corp., 96 Wis.2d 314, 291 N.W.2d 825 (Wis.1980), the Wisconsin Supreme Court held that under § 893.52 (then codified as WIS.STAT. § 893.19(5)):

[A] cause of action accrues and the statute of limitations ... begins to run when the evidence of injury to property, resulting from the negligent act upon which the action is based, is sufficiently significant to alert the injured party to the possibility of a defect. The injury need not, however, be of such magnitude as to identify the causal factor.

96 Wis.2d at 324, 291 N.W.2d at 830 (emphasis in original) (quoting Tallmadge v. Skyline Construction, Inc., 86 Wis.2d 356, 359, 272 N.W.2d 404, 405 (Wis.Ct.App.1978)). In Wisconsin Natural Gas, the plaintiff had retained the defendant, a pipeline engineering and consulting firm, to design and supervise the installation of a 14-mile natural gas transmission pipeline. The plaintiff sued the defendant after there were a number of “casing shorts” in the pipeline. The defendant argued that the plaintiff’s cause of action was time-barred on the ground that the limitations period began to run as soon as the pipeline suffered its first “casing short.” There was evidence, however, that “casing shorts” are a regular occurrence in a pipeline and often caused by factors other than the improper installation of a pipeline. In view of this evidence, the court held that “the discovery of a single casing short, in a relatively new pipeline, is not ‘sufficiently significant’ to alert the [plaintiff] to the possibility of major defects throughout the entire 14 mile pipeline.” 96 Wis.2d at 325, 291 N.W.2d at 830-31. Instead, the court held that the plaintiff’s cause of action did not accrue “until a number of ‘casing shorts’ rendered the cathodic protection process ineffective and necessitated an extensive excavation and repair program to clear the pipeline of the shorts.” Id.

Relying heavily on Wisconsin Natural Gas, the Wisconsin Supreme Court subsequently adopted the “discovery rule” for purposes of determining the accrual of all tort causes of action. See Hansen v. A.H. Robins, Inc., 113 Wis.2d 550, 560, 335 N.W. 2d 578, 583 (Wis.1983). In Hansen, the plaintiff brought suit against the manufacturer of an intrauterine device alleging that the device caused her to contract pelvic inflammatory disease. Plaintiff filed her suit within three years of the time she had been diagnosed as suffering from pelvic inflammatory disease but more than three years after she first suffered the effects of the disease. Her problem had been previously diagnosed by a doctor as gastroenteritis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
847 F.2d 435, 1988 U.S. App. LEXIS 7391, 1988 WL 54310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/milwaukee-area-vocational-technical-and-adult-education-district-v-united-ca7-1988.