Kuhlman, Inc. v. G. Heileman Brew. Co., Inc.

266 N.W.2d 382, 83 Wis. 2d 749, 1978 Wisc. LEXIS 1020
CourtWisconsin Supreme Court
DecidedJune 6, 1978
Docket75-770
StatusPublished
Cited by39 cases

This text of 266 N.W.2d 382 (Kuhlman, Inc. v. G. Heileman Brew. Co., Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kuhlman, Inc. v. G. Heileman Brew. Co., Inc., 266 N.W.2d 382, 83 Wis. 2d 749, 1978 Wisc. LEXIS 1020 (Wis. 1978).

Opinion

ABRAHAMSON, J.

This action was instituted by Kuhlman, Inc. (Kuhlman), a corporation engaged in the manufacture, installation, and servicing of industrial refrigeration equipment, to recover from the G. Heile-man Brewing Company, Inc. (Heileman) a $6,850.00 unpaid balance on four construction contracts. The parties stipulated that Heileman owed $6,850.00 to Kuhlman on the contracts, subject to Heileman’s counterclaims for damages caused by alleged breach of the contracts by Kuhlman.

Three issues were pursued at trial: (1) whether Kuhl-man breached two of the contracts by defectively installing equipment at Heileman’s Sheboygan plant; (2) if Kuhlman breached the contracts what sum of money would compensate Heileman for the reasonable cost of repairing the defective installations; and (3) what amount listed as “state taxes” in bid tenders submitted by Kuhlman and incorporated by reference into two of the contracts included Wisconsin sales taxes for which Heileman was entitled to reimbursement.

The jury determined that Kuhlman breached the contracts by performing work in a faulty manner, and it *752 awarded Heileman $114.00 as the reasonable cost of correcting the defects. The jury further determined that no amount of the state taxes set forth in the bid tenders constituted sales taxes. Judgment was entered on the verdict, and Heileman appealed. We reverse and remand the cause for a new trial on the issue of damages at the Sheboygan plant as a result of Kuhlman’s breach of contract.

I.

By its counterclaim, Heileman sought damages for Kuhlman’s breach of contract. The measure of the damages sought was the cost incurred by Heileman in repairing Kuhlman’s defective installations. Stevens Construction Corp. v. Carolina, Corp., 63 Wis.2d 342, 360, 217 N.W.2d 291 (1974). Heileman challenges on appeal the trial court’s instructions with regard to Heileman’s duty to mitigate these repair costs.

An injured party has a duty to mitigate damages, that is, to use reasonable means under the circumstances to avoid or minimize the damages. An injured party cannot recover any item of damage which could have been avoided. The burden of proof is on the delinquent party to show that the injured party could have mitigated its damages. If the effort, risk, sacrifice or expense which the injured person must incur to avoid or minimize the loss or injury is such that a reasonable person under the circumstances might decline to incur it, the injured party’s failure to act will not bar recovery of full damages. Byrnes v. Metz, 53 Wis.2d 627, 631, 632, 193 N.W.2d 675 (1972); O’Brien v. Isaacs, 17 Wis.2d 261, 266, 116 N.W.2d 246 (1962); Monroe County Finance Co. v. Thomas, 243 Wis. 568, 571, 11 N.W.2d 190 (1943); 11 Williston on Contracts, sec. 1354 (Jaeger 3d ed. 1968); McCormick, Law of Damages, sec. 33 et seq. (1935).

*753 Whether Heileman exercised reasonable care to mitigate or lessen its costs of repair centers around Heile-man’s use of its own employees and third-party contractors to make the repairs rather than requesting Kuhlman to make repairs.

There was conflicting testimony as to whether Heile-man advised Kuhlman of the defective installations or requested Kuhlman to make repairs. Ronald Kuhlman, Kuhlman’s vice-president, testified that had Kuhlman been given the opportunity to make repairs, Heileman would not have been charged for any repairs made necessary by Kuhlman’s defective materials or workmanship. Kuhlman would have borne the cost of such repairs, stated the vice-president, because of Kuhlman’s warranty of “parts, labor or material supplied.” The warranty in the contract provided that:

“We [Kuhlman] will guarantee the Work of the Contract against, and agree to make good, any and all faulty materials and/or workmanship for a minimum period of one year from the date of acceptance by the Engineer.”

The contract does not state that Kuhlman will “make good” its warranty by correcting defects. The contract is silent as to whether Heileman was obligated to resort to Kuhlman’s services before undertaking other measures to repair defects covered by the warranty. 1 Neither party asked the trial court to interpret the contract to *754 require Heileman to ask that Kuhlman make the repairs before Kuhlman incurred liability. Whether Heile-man had to notify Kuhlman of alleged defe'cts and afford Kuhlman the first opportunity to correct the defects was viewed by the parties and the trial court as. an aspect of Kuhlman’s affirmative defense that Heileman failed to mitigate damages.

In its instructions to the jury, the trial court characterized as follows Heileman’s duty to mitigate its repair costs:

“. . . You are further instructed it was the duty of Heileman’s to exercise ordinary care to mitigate or lessen its damages. By ordinary care, as that term is here used, is meant that care usually exercised by a person of ordinary intelligence and prudence, under the same or similar circumstances. Heileman’s is entitled to avoid loss, to avoid undue risks and to safeguard its product. \_Heileman\ must ask Kuhlman, Inc. to comply with its warranty unless you are satisfied Kuhlman, Inc., ignored requests of Heileman and that it would be useless to call on them.
“In fixing damages you will keep in mind this duty of Heileman’s to exercise ordinary care to mitigate its damages; and, if you find they did not do so, you should not include in your answer to this question any amount which could have been avoided by the exercise of such care.” [Emphasis added]

Heileman claims that the trial court erred in instructing the jury that “[Heileman] must ask Kuhlman . . . to comply with its warranty unless . . . Kuhlman . . . ignored requests of Heileman and ... it would be useless to call on them.” [Emphasis added.] The jury should have been instructed, argues Heileman, that Heile-man’s affording (or failure to afford) Kuhlman an opportunity to correct the defects was one of the factors to be considered in determining whether Heileman exercised ordinary care in seeking to mitigate its damages. The instruction given, asserts Heileman, erroneously placed *755 upon the injured party, as a matter of law, the duty to ask the breaching party to make repairs. Thus, instead of allowing the jury to determine the reasonable conduct of the injured party under the circumstances, the trial court, in effect, instructed the jury that the only reasonable course of conduct was to seek out Kuhlman to make repairs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WILKERSON v. 3M COMPANY
N.D. Florida, 2022
Daniel S. Krueger v. Paul C. Hsu
Court of Appeals of Wisconsin, 2021
The Bank of New York Mellon v. Elizabeth M. Brozek
Court of Appeals of Wisconsin, 2020
Kostal v. Life Insurance Co. of North America
834 F. Supp. 2d 882 (E.D. Wisconsin, 2011)
S.C. Johnson & Son, Inc. v. Morris
2010 WI App 6 (Court of Appeals of Wisconsin, 2009)
Stewart Title Guaranty Co. v. Residential Title Services, Inc.
607 F. Supp. 2d 959 (E.D. Wisconsin, 2009)
Peterson v. Cornerstone Property Development, LLC
2006 WI App 132 (Court of Appeals of Wisconsin, 2006)
Mayberry v. Volkswagen of America, Inc.
2005 WI 13 (Wisconsin Supreme Court, 2005)
Kramer v. Board of Education of the School District of the Menomonie Area
2001 WI App 244 (Court of Appeals of Wisconsin, 2001)
Kramer v. BD. OF EDUC. OF MENOMONIE AREA
2001 WI App 244 (Court of Appeals of Wisconsin, 2001)
Langreck v. Wisconsin Lawyers Mutual Insurance
594 N.W.2d 818 (Court of Appeals of Wisconsin, 1999)
Frieburg Farm Equipment, Inc. v. Van Dale, Inc.
978 F.3d 395 (Seventh Circuit, 1992)
Kolpin v. Pioneer Power & Light Co.
469 N.W.2d 595 (Wisconsin Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
266 N.W.2d 382, 83 Wis. 2d 749, 1978 Wisc. LEXIS 1020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kuhlman-inc-v-g-heileman-brew-co-inc-wis-1978.