Jed Spectrum, Inc. v. Stoakes

2025 S.D. 31
South Dakota Supreme Court·Decided July 2, 2025·No. 30420, 30434·Published

Opinion

#30420, #30434-aff in pt & rev in pt-PJD 2025 S.D. 31

IN THE SUPREME COURT

OF THE

STATE OF SOUTH DAKOTA

****

JED SPECTRUM INCORPORATED, a South Dakota corporation, and BIGHORN CONSTRUCTION, LLC, a South Dakota limited liability company, Plaintiffs and Appellants,

v.

KEITH STOAKES, and any person in possession, Defendant and Appellee,

and BANKWEST, INC., Defendant.

****

APPEAL FROM THE CIRCUIT COURT OF THE FOURTH JUDICIAL CIRCUIT MEADE COUNTY, SOUTH DAKOTA

****

THE HONORABLE MICHAEL W. DAY Judge

****

JOEL E. ENGEL III JORDAN J. FEIST of Woods, Fuller, Shultz & Smith, P.C. Sioux Falls, South Dakota Attorneys for plaintiffs and appellants.

JESS M. PEKARSKI PHILIP R. STILES MICHAEL F. STEVE GARRETT J. KEEGAN of Costello, Porter, Hill, Heisterkamp, Bushnell & Carpenter, LLP Rapid City, South Dakota Attorneys for defendant and appellee Keith Stoakes.

****

CONSIDERED ON BRIEFS

MARCH 19, 2024

OPINION FILED 07/02/25

DEVANEY, Justice [¶1.] Bighorn Construction, LLC (Bighorn) and JED Spectrum, Inc. (JED) each filed a mechanic’s lien against property owned by Keith Stoakes and thereafter jointly instituted this action to foreclose on the liens. Stoakes answered, denying the validity of the liens and asserting counterclaims for slander of title against both companies and breach of contract, promissory estoppel, and fraud against JED. After a three-day bench trial, the circuit court issued amended findings of fact and conclusions of law denying JED’s and Bighorn’s claims for lien foreclosure and ruling in favor of Stoakes on his slander of title claims against both companies. The court awarded Stoakes $252,225.27 in damages on his slander of title claims and $33,394.20 in attorney fees. The court denied relief on the parties’ remaining claims. Bighorn and JED appeal, arguing the court erred in ruling in favor of Stoakes on his slander of title claim and in calculating damages. By notice of review, Stoakes challenges the denial of relief on his promissory estoppel claim and associated request for attorney fees. We reverse in part and affirm in part.

Factual and Procedural Background [¶2.] In June 2018, Keith Stoakes and his fiancé Sheri made an offer to Barb Morris to purchase two lots (Lots 12 and 13) in the Mountain Shadows Ranch Estates subdivision in Meade County. At the time they made the offer, they did not know that Jerome (Jerry) and Bonnie Pauling, who owned multiple lots in the subdivision, held a right of first refusal on both lots. Jerry contacted Stoakes to advise him that he had a right of first refusal on both properties, but he expressed a willingness to forego exercising the right so that Stoakes could purchase both lots if

Stoakes would agree to change the property line for Lot 12 to add approximately a half of an acre to the Paulings’ adjacent lot. Stoakes did not agree and instead decided not to purchase Lot 12. The Paulings nevertheless waived their right of first refusal on Lot 13, and Stoakes and Sheri purchased that lot. [¶3.] After the purchase, Jerry befriended Stoakes and Sheri and welcomed them to the community. Jerry also helped them make decisions related to building a home on their property. Jerry has over thirty years of experience in the construction industry and is the sole owner and operator of Bighorn. He is also the sole shareholder of JED, a company he uses to manage his rentals. Stoakes decided, after considering his options, to install a prefabricated home on his property. By this time, he and Sheri had gotten married and divorced, and she deeded her interest in the property to him. [¶4.] Prior to Stoakes obtaining financing, Jerry proposed to him that Bighorn perform the excavation work for the placement of his home. To save Stoakes money, Jerry agreed to allow Stoakes to help with the labor on the project. Stoakes agreed, and Bighorn provided him an estimate indicating that Bighorn could complete the work for approximately $14,800, which included excavation, installing a water line and two septic tanks, gravel and dirt back fill, and trucking. Jerry also proposed that because Lot 13 did not have a water source, Stoakes could enter into an agreement with JED for a shared well system. No agreement was reached regarding the well system at that time. [¶5.] Prior to construction, which did not begin until 2020, Stoakes and Jerry again discussed the topic of Stoakes connecting to JED’s well. Though the

specific terms are disputed, Jerry testified that they discussed a concept whereby all five lots in the subdivision would connect to the well system and each lot owner would pay one-fifth of the cost of the construction of the well. Both Stoakes and Jerry testified that they discussed an arrangement in which Stoakes would pay JED $24,000 (one-fifth of the construction costs) in exchange for Stoakes having a reliable water source and a one-fifth share in the well system. According to Stoakes, Jerry provided him an estimate that was issued by Bighorn. The estimate, dated June 25, 2020, is addressed to JED and contains a detailed list of the cost of materials and labor for a total cost of $23,956.77, representing what Jerry characterized as one-fifth of the homeowner’s water system connection charge. [¶6.] Using this estimate from Bighorn for the excavation and other work on Stoakes’s property, along with the expected $24,000 expense for the shared well, Stoakes secured a construction mortgage in November 2020 from BankWest for $292,968. Pennington Title Company was responsible for issuing payments to contractors for associated construction costs, including site blasting, excavation and dirt work, and installation of a waterline. [¶7.] Construction on the property began in December 2020, and while work was underway by Bighorn, Jerry and Stoakes negotiated terms for a written shared well agreement between JED and Stoakes. Jerry and Stoakes retained separate counsel and exchanged draft agreements, through counsel, that each believed accurately reflected the terms of their oral discussions. In January 2021, Stoakes connected to JED’s well and began drawing water, though no written well agreement had been reached at that time. Stoakes testified that he connected to

the well because of the earlier assurance from Jerry that he would have access to a reliable water source and be a one-fifth owner in the well system. [¶8.] Bighorn finished its work on Stoakes’s property and sent Stoakes an invoice for $42,674. Stoakes claimed that Jerry provided no explanation for the substantial difference between the $14,800 estimate and this later invoice amount. Eventually, Jerry and Stoakes negotiated the total invoice down to $31,728.61, and on June 15, 2021, Bighorn sent Stoakes a new invoice seeking payment for this amount. The invoice described the work performed by Bighorn as: “[i]nstallation of the water line from well house to home”; “[i]nstallation of water line to supply camper pad”; and excavation work, back fill for foundation, footings, walls, and septic tanks. [¶9.] Stoakes submitted Bighorn’s invoice to Pennington Title, and Pennington Title issued Bighorn a check for $31,728.61 on June 29, 2021. The top of the check contained the following statement: “THIS IS A LIEN WAIVER CHECK.” A representative from Pennington Title testified that the company stamps its checks with this statement as a standard practice to indicate that the contractor was “paid for services rendered.” Bonnie, who was the bookkeeper for Bighorn and JED, asked Stoakes to have the check reissued without the lien waiver stamp. Stoakes testified that he did not oppose the request but that the check was not reissued because of the company’s policy to include the lien waiver notation. At trial, a representative from Pennington Title testified that the company would not have reissued a check without the lien waiver because it “goes against policy and procedure.”

Free access — add to your briefcase to read the full text and ask questions with AI

Jed Spectrum, Inc. v. Stoakes, 2025 S.D. 31 (S.D. 2025).

2025 S.D. 31 (Jed Spectrum, Inc. v. Stoakes) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

New York Times Co. v. Sullivan
376 U.S. 254 (Supreme Court, 1964)
Gertz v. Robert Welch, Inc.
418 U.S. 323 (Supreme Court, 1974)
State v. Dreps
1996 SD 142 (South Dakota Supreme Court, 1996)
Gregory's, Inc. v. Haan
1996 SD 35 (South Dakota Supreme Court, 1996)
Kieser v. Southeast Properties
1997 SD 87 (South Dakota Supreme Court, 1997)
Paint Brush Corp. v. Neu
1999 SD 120 (South Dakota Supreme Court, 1999)
Hahne v. Burr
2005 SD 108 (South Dakota Supreme Court, 2005)
In Re the Guardianship of S.M.N.
2010 SD 31 (South Dakota Supreme Court, 2010)
Brown v. Hanson
2011 S.D. 21 (South Dakota Supreme Court, 2011)
Tibke v. McDougall
479 N.W.2d 898 (South Dakota Supreme Court, 1992)
State v. Baysinger
470 N.W.2d 840 (South Dakota Supreme Court, 1991)
Garrett v. BankWest, Inc.
459 N.W.2d 833 (South Dakota Supreme Court, 1990)
Janklow v. Viking Press
459 N.W.2d 415 (South Dakota Supreme Court, 1990)
Interest of I.A.D., L.J.D., and C.M.D.
2023 S.D. 36 (South Dakota Supreme Court, 2023)
Smith Masonry v. Wipi Group, USA, Inc.
2023 S.D. 48 (South Dakota Supreme Court, 2023)