American Casualty Co. v. Board of Education of Independent School District, No. 2

228 F. Supp. 843, 1964 U.S. Dist. LEXIS 8023
CourtDistrict Court, W.D. Oklahoma
DecidedMarch 23, 1964
Docket9639
StatusPublished
Cited by5 cases

This text of 228 F. Supp. 843 (American Casualty Co. v. Board of Education of Independent School District, No. 2) is published on Counsel Stack Legal Research, covering District Court, W.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Casualty Co. v. Board of Education of Independent School District, No. 2, 228 F. Supp. 843, 1964 U.S. Dist. LEXIS 8023 (W.D. Okla. 1964).

Opinion

*845 DAUGHERTY, District Judge.

This is a dispute between the American Casualty Company, who as plaintiff sues the defendants, Board of Education of Independent School District, No. 2, Cleveland County, Moore, Oklahoma, and the individual members of said Board, Noftsger-Lawrenee and Associates, a co-partnership, and the W. R. Lowe Building Company, a corporation, and W. R. Lowe and Kenneth Lowe, Individually.

In view of the positions occupied by the parties in this controversy the plaintiff will hereinafter be called the Surety, the defendant, Board of Education the Owner, the defendant architect partnership the Architect and the defendant Construction Company and the individual members thereof the Contractor.

On June 28, 1960, the Owner entered into an owner-architect agreement with the Architect. On February 6, 1961, the Owner entered into a construction contract with the Contractor. Both contracts pertained to the construction of a cafeteria and classroom addition to the existing high school building in Moore, Oklahoma. The construction contract was in the amount of $289,939.00. The architect contract called for a fee of $17,364.-34.

The Contractor furnished a separate performance bond, payment bond and maintenance bond in connection with the said construction project, each separate bond having the plaintiff as surety thereon. These three separate bonds were furnished at approximately the time the said construction contract was entered into.

The owner-architect agreement provided in part that:

“The Architect’s services shall consist of the necessary conferences, the preparation of preliminary studies, working drawings, specifications and detail drawings, and the supervision of the work by visiting the site from time to time during the progress of construction to be assured that the work is being carried out by the Contractor in strict compliance with plans and specifications, but the Architect does not guarantee performance by the Contractor.”

The construction contract provided in part that:

“Within the first ten (10) days of each calendar month, the Owner shall make partial payments to the Contractor for work performed during the preceding calendar month on estimate certified by the Architect and the Owner. Ten per cent (10%) of each such approved estimate shall be retained by the Owner until final completion and acceptance of all work covered by contract. Upon completion of all work, and compliance with the contract, the Owner’s Architect shall issue a Certificate of Completion, based on final measurements of all work completed, and the Owner shall, within a reasonable time, pay to the Contractor the balance due under the terms and conditions of the Contract.”

The owner-architect agreement did not provide that the Architect would approve or certify monthly estimates of the Contractor and upon completion issue a Certificate of Completion, but in fact such responsibility was undertaken and accomplished by the Architect as clearly shown by certain exhibits put in evidence. Monthly estimates were so certified beginning in March, 1961. They continued, and on December 8, 1961, the Architect made an inspection and prepared a so-called “Punch List” which set out 15 minor items yet to be done or corrected. A final inspection was made on or about December 14, 1961, and under date of December 15, 1961, the Architect reported in writing that the building was complete according to plans and specifications and recommended that it be accepted with some 24 minor listed exceptions. At this time the final estimate was certified and approved by the Architect with $500.00 withheld from the construction funds for these 24 incomplete items. Under date of December 28, 1961, the Architect in *846 a letter to the Contractor reported that another inspection had been made and 14 of the said 24 minor listed incomplete items were stated not yet to have been corrected.

In late December, 1961, (apparently on Friday before Christmas), the Contractor notified the Surety for the first time that it could not pay its bills on the job. The Surety thereafter in due course (and of course, after the retainage fund was released), paid approximately $58,291.53 to satisfy unpaid labor and material bills of its principal, the Contractor, relating to the project.

All of the incomplete items were eventually corrected or supplied and were effected by the Contractor except that apparently the Surety in paying the bills did guarantee and pay for a set of blackout drapes (on the 24 item list) costing $120.00 which were not installed until April, 1962. The said $500.00 fund withheld as above stated is still available to cover this item of completion expense.

No one requested the performance bond Surety to complete or perform the contract under the performance bond and it does not appear that it did. It appears from the evidence that the construction work was fully performed by the Contractor with the possible exception of the black-out drapes as above outlined. In fact, it appears that such work was substantially completed by the Contractor much earlier than the December activities above related for on or about September 1, 1961, the classrooms were occupied and used by the Owner and on or about November 1, 1961, the cafeteria was occupied by the Owner and meals were being served in the same by November 10, 1961.

Through September, 1961, estimates had been approved by the Architect totaling $281,149.10, of which $253,034.19 had been paid to the Contractor, and $28,114.-91 had been retained by the Owner under the 10% retainage right in the construction contract. On October 20, 1961, when the work was substantially completed, the Contractor applied for 75% of the retainage held by the Owner and the Architect approved for payment the sum of $20,000.00 on this request. The final estimate (less the said $500.00) was approved for payment by the Architect on December 14,1961, in the amount of $15,-207.81, and paid by the Owner on December 15, 1961. The total construction cost finalized out at $288,742.00.

It does not appear from the evidence that the Owner or Architect had any knowledge of the bad financial condition of the contractor or its non-payment of bills on the project, until late in December, 1961, and after all construction funds had been released save the said $500.00, nor apparently did the Surety have any such knowledge until then except on November 13, 1961, the Surety did learn that a sub-contractor had failed to pay a bill, and on December 13,1961, the Surety received a complaint from a Lumber Company that the Contractor owed it a bill which was past due and unpaid.

The plaintiff Surety contends herein that because the owner released the 10% retainage before all the work had been completed it impaired the Surety’s rights of subrogation and exoneration and is liable to the plaintiff for the amount of said retainage and that the Architect in issuing a final certificate of completion and approving release of the retainage to the Contractor before all of the work had been completed, likewise impaired the Surety’s rights of subrogation and exoneration, and is also liable to plaintiff for the amount of retainage. It is claimed by the Surety that such retainage amounted to $25,207.81.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
228 F. Supp. 843, 1964 U.S. Dist. LEXIS 8023, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-casualty-co-v-board-of-education-of-independent-school-district-okwd-1964.