E. I. Du Pont De Nemours & Co. v. City of Glenwood Springs

19 F.2d 225, 1927 U.S. App. LEXIS 2219
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 18, 1927
DocketNo. 7512
StatusPublished
Cited by6 cases

This text of 19 F.2d 225 (E. I. Du Pont De Nemours & Co. v. City of Glenwood Springs) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. I. Du Pont De Nemours & Co. v. City of Glenwood Springs, 19 F.2d 225, 1927 U.S. App. LEXIS 2219 (8th Cir. 1927).

Opinion

JOHN B. SANBORN, District Judge.

This is a suit brought by the-'plaintiff in error to recover $6,589.23 and interest from the defendant in error. The parties will be given in this opinion the designations which they had in the court below, namely, plaintiff and defendant. The complaint was demurred to, and the demurrer sustained. An amended complaint was filed, to which a demurrer was filed and sustained. The plaintiff elected to stand upon its amended complaint, and thereupon judgment of dismissal was entered as to the defendant.

The only question involved is whether the amended complaint stated a cause of action. Por the purpose of this opinion, it is not necessary to set forth in detail all of the allegations, which are voluminous. In a general way, the facts shown by the complaint are these:

In the month of September, 1922, the city advertised for bids for the construction of a tunnel for improving its waterworks. In October, 1922, R. A. White and K. V. Johnson filed their bid, in accordance with instructions and forms given them by the city, and offered, as a surety upon their bond, the Southern Surety Company. The ■bid was made for and accepted as the bid of the White & Johnson Construction Company, “either then or thereafter organized by the same parties who made and were parties to and interested in said bid, and all with the full knowledge and consent of the city.” The contract and bond were executed by the White & Johnson Construction Company on or about October 11, 1922; but the city did not accept the Southern Surety Company as surety, but took K. V: Johnson, R. A. White, and A. L. Johnson as sureties, who were interested in the construction company, and who subsequently turned out to be worthless. None of these men could qualify under the law as sureties on sueh a bond. Between November 18, 1922, and November 30, 1923, the plaintiff sold to the White & Johnson Construction Company explosives of the value of $9,790.-31, to be used and which were used* in the construction of the tunnel. There remains unpaid of this amount $5,790.31, with interest at 6 per cent, to July 1, 1925, making a total indebtedness on that date of $6,589.-23.

On the 7th of September, 1923, the city entered into a supplemental agreement with the construction company with reference to the construction of the tunnel, in which the city agreed that the total cost of all the work and materials should be $102,000 instead of the amount fixed by the contract, of which $62,230.27 had been paid, leaving a balance of $39,769.73, which the city agreed to pay in monthly estimates, and required the construction company to give a chattel mortgage on all its tools, machinery, and material on the ground to secure the city against loss, demands, liens, claims, and failure to .perform its agreement. ‘The city reserved the right to require additional sureties on the bond of the construction company, but did not do so. The plaintiff, in making the sale of material to the construction company and in extending credit to it, examined the requirements, instructions, specifications, contract, and bond, and found them to be in the form required by law, and duly executed and approved by the proper city officials, and relied upon compliance by the city with all statutory requirements, and particularly with the requirement that the city would demand a good and sufficient bond of the contractor, either with a surety company or with individual persons owning real estate in Colorado, in double the amount of their individual liability, and assumed that the city had required sueh a bond and had complied with the statutes. The plaintiff also relied upon the city’s requiring from the contractor sworn statements of all amounts owing for labor and material, as required by the contract; but the city failed to withhold amounts due materialmen, and permitted its engineer to give estimates, and appropriated money to pay and paid the same, without requiring a statement of any kind from the construction company as to obligations due for material, and particularly the obligation due the plaintiff. It neglected and .refused to pay the plaintiff any part of its debt due from the contractor for materials furnished and used by it.

In November, 1923, the city took over the work, but permitted the construction company to remain in charge and control of the construction of the tunnel, and continued to make payments without affidavits or. statements from the construction company as to the amount of unpaid'labor or material, after it had been notified by the plaintiff of its unpaid account for explosives and demand for payment. The city paid, after sueh notice and demand, some $40,000 to the construction company, and retained no portion of any estimates for labor or material or otherwise, and took .over a large amount of the explosives and materials furnished by the plaintiff to the contractor, of the value of at least $2,000, and used the same in and about the comple[227]*227tion of the water works tunnel. The contract has been fully performed, the improvements accepted, and the city is enjoying the benefits. The form of the bid of White & Johnson is set out in the amended complaint, and also the contract between the city and the construction company, as1 well as the bond given by the company to the city.

In sustaining the demurrer to the complaint, the court below seems to have relied very largely upon the fact that there was no bid made by the construction company, as required by the laws of Colorado, and that therefore the contract was absolutely void, and no recovery could be had under it — citing Town of Durango v. Pennington, 8 Colo. 257, 7 P. 14; Colorado Springs v. Coray, 25 Colo. App. 460, 139 P. 1031; Sullivan v. Leadville, 11 Colo. 483, 18 P. 736; Denver v. Hindry, 40 Colo. 42, 90 P. 1028, 11 L. R. A. (N. S.) 1028.

The plaintiff attempted in its pleading to avoid this difficulty by alleging that White & Johnson made the bid for the corporation, which was then or thereafter organized, and that that was understood by the city. We think it is unnecessary to-pass upon the question as to whether the White & Johnson Construction Company had a valid contract with the city or not. There is no claim that the plaintiff ever sold the city anything, or that the plaintiff had any express agreement with the city to pay for the explosives furnished the construction company. The theory of the plaintiff seems to be, either that the contract with the construction company obligated the city to pay materialmen for material furnished to the White & Johnson Construction Company, or that it was in some way a trustee for the plaintiff and other materialmen.

There is no dispute as to the faet that the city had authority to enter into such a contract as is referred to in the amended complaint, and there is no question but that it failed to require the bond provided for by statute. We know of no authority for the proposition that, because the officers of a city, in letting a contract, fail to require the proper statutory bond, that makes the city liable to all persons furnishing labor or material to the person to whom the contract was let. The plaintiff, however, says that the city, in the contract with the construction company, either agreed that it would pay for labor or material furnished to the contractor, or that it constituted itself a trustee for laborers and materialmen.

Section 5406, Revised Statutes of Colorado 1908, required municipal corporations contracting for the construction of public works to withhold payment of moneys due contractors to satisfy the claims of material-men and others.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
19 F.2d 225, 1927 U.S. App. LEXIS 2219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-i-du-pont-de-nemours-co-v-city-of-glenwood-springs-ca8-1927.