W. S. Dickey Clay Mfg. Co. v. Ferguson Investment Co.

1963 OK 298, 388 P.2d 300, 1963 Okla. LEXIS 561
CourtSupreme Court of Oklahoma
DecidedDecember 31, 1963
Docket40272
StatusPublished
Cited by33 cases

This text of 1963 OK 298 (W. S. Dickey Clay Mfg. Co. v. Ferguson Investment Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. S. Dickey Clay Mfg. Co. v. Ferguson Investment Co., 1963 OK 298, 388 P.2d 300, 1963 Okla. LEXIS 561 (Okla. 1963).

Opinion

WILLIAMS, Justice.

The principal question to be determined in this appeal is whether or not a condition in the bond of a developer of a sub-division, required by the city planning commission, to pay for materials and labor furnished, and which condition was not specifically provided for either in the statute or in the ordinance authorizing such commission to accept such bond, is enforceable in suit brought by a lien claimant.

Plaintiff in error, hereinafter called plaintiff, initiated the action from which this appeal arises against defendants in error, Ferguson Investment Company, Inc., and M. S. Ferguson, hereinafter called Ferguson, and American-First Title & Trust Company, a corporation, hereinafter called American First, to recover the balance owing it for materials furnished to Concho Construction Co., hereinafter called Concho.

In plaintiff’s amended petition, in pertinent part, it is alleged that on or about February 22, 1961, Ferguson undertook to subdivide and plat a tract of land in Oklahoma City and as a part thereof, to construct and install certain improvements and utilities; that in connection with such subdivision Ferguson as principal and American-First as surety executed a subdivision bond pursuant to the provisions of 11 O.S.1951 § 1425, Section 13.1.07 of the Revised Ordinances of the City of Oklahoma City, 1960, and paragraph VII of the duly adopted and published rules and regulations of the Oklahoma City Planning Commission; that such bond was conditioned that Ferguson would, within two years, install and complete all improvements and utilities in such subdivision and pay all bills for contractors, sub-contractors, and labor and materials incurred in completion thereof; that Con-cho entered into a contract with Ferguson to construct and install certain utilities; that plaintiff sold and delivered to Concho certain materials used in the construction thereof; that $1,658.86 of the cost of such materials remained due to plaintiff and unpaid by Concho.

The trial court sustained the general demurrer of Ferguson and American-First to plaintiff’s amended petition and dismissed the action.

For reversal plaintiff advances three propositions. The first is: “A general demurrer lies only when the entire petition taken as a whole fails to state a cause of action.”

Plaintiff contends that it alleged “three separate and distinct governmental requirements pursuant to which the bond was executed” ; that Ferguson and American-First in their brief in the trial court “having specifically limited their objection to only one, [the statute] admit the other two” (the ordinance and the rules and regulations of the planning commission) ; and that a “petition showing plaintiff is entitled to any *302 relief is good as against a general demurrer and the demurrer should he overruled.”

The statute, 11 O.S.1951 § 1425 in pertinent part, provides:

“Before exercising the powers referred to in Section 13, the planning commission shall adopt regulations governing the subdivision of land within its jurisdiction. Such regulations may provide for the proper arrangement of streets in relation to other existing or planned streets and to the master plan, for adequate and convenient open spaces for traffic, utilities, * * *
« ⅜ ⅜ * The regulations or practice of the commission may provide for a tentative approval of the plat previous to such installation; but any such tentative approval shall be revocable for failure to comply with commitments on which such tentative approval was based, and shall not be entered on the plat. In lieu of the completion of such improvements and utilities prior to the filial approval of the plat, the commission may accept an adequate bond satisfactory to the commission, with surety, to secure to the municipality the actual construction and installation of such improvements or utilities at a time and according to specifications fixed by or in accordance with the regulations of the commission. * * * ”

The ordinance, section 13.1.07 of the revised ordinances of the City of Oklahoma City, 1960, in pertinent part, provides:

“ * * * In lieu of the completion of such improvements and utilities prior to the final approval of the plat, the Commission may accept an adequate bond satisfactory to the Commission, with surety, to secure to the City of Oklahoma City, the actual construction and installation of such improvements or utilities at a time and according to specifications fixed by or in accordance with the regulations of the Commission.”

Paragraph VII of the rules and regulations of the Oklahoma City planning commission, in pertinent part, provides:

“When the plat is in final record form ready for the approval of the Commission, the request for approval will be accompanied by the following:
⅜ ⅜ * ⅜ ⅜⅞ >¡c
“d. A good and sufficient, surety bond in the amount of 100% of the total cost of the improvements in accordance with the estimates required by Section c above, guaranteeing that the addition will be developed in accordance with current subdivision regulations of the Planning Commission of the City of Oklahoma City, and that paving, sanitary sewers, storm sewers, and other provisions for handling surface water will be constructed in accordance with the plans and specifications, approved by the City Engineer, and water mains will be constructed in accordance with the plans and specifications approved by the City Water Superintendent, of the City of Oklahoma City, and that the developer will guarantee the payment of all materials and labor entering into the construction of said improvements.” (Emphasis supplied.)

In its reply brief plaintiff states: “It is not disputed that the bond in question is a statutory bond and we agree with defendants that the general rules in respect to construction of statutory bonds as set forth on pages 6 and 7 of defendants’ brief are recognized as the generally accepted and established rules pertaining to the construction and enforcement of statutory bonds.”

The language of the ordinance and the statute is identical except that in the former the words “City of Oklahoma City” are substituted for the word “municipality”.

Therefore, contrary to argument of the plaintiff of which note was made hereinabove, if the condition of the bond in question inserted pursuant to the above-emphasized portion 'of rule Vlld is not authorized by the language of the statute, *303 it is likewise not authorized by that of the ordinance. The city planning commission has only such power and authority as are delegated to it by the statute and the ordinance. In 42 Am.Jur., Public Administrative Law, § 99, p. 428, is the following:

“Administrative rules and regulations, to be valid, must be within the authority conferred upon the administrative agency. * * * The statute which is being administered may not be altered or added to by the exercise of a power to make regulations thereunder. A rule which is broader than the statute empowering the making of rules cannot be sustained. Administrative authorities must strictly adhere to the standards, policies, and limitations provided in the statutes vesting power in them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IN THE MATTER OF THE GUARDIANSHIP OF WOOD
2019 OK CIV APP 53 (Court of Civil Appeals of Oklahoma, 2018)
Ply v. National Union Fire Insurance Co.
2003 OK 97 (Supreme Court of Oklahoma, 2003)
Opinion No. (2002)
Oklahoma Attorney General Reports, 2002
Opinion No. (2001)
Oklahoma Attorney General Reports, 2001
Opinion No. (1999)
Oklahoma Attorney General Reports, 1999
Opinion No. (1997)
Oklahoma Attorney General Reports, 1997
Opinion No. (1995)
Oklahoma Attorney General Reports, 1995
Southwestern Bell Telephone Co. v. Parker Pest Control, Inc.
737 P.2d 1186 (Supreme Court of Oklahoma, 1987)
Opinion No. (1985)
Oklahoma Attorney General Reports, 1985
Hewson Construction, Inc. v. Reintree Corp.
685 P.2d 1062 (Washington Supreme Court, 1984)
Sooner Oil & Gas Corp. v. State
1981 OK 118 (Supreme Court of Oklahoma, 1981)
Opinion No. 80-169 (1980) Ag
Oklahoma Attorney General Reports, 1980
Opinion No.
Oklahoma Attorney General Reports, 1980
Riffe Petroleum Co. v. Great Nat. Corp., Inc.
1980 OK 112 (Supreme Court of Oklahoma, 1980)
Opinion No. 80-164 (1980) Ag
Oklahoma Attorney General Reports, 1980
Opinion No. 80-032 (1980) Ag
Oklahoma Attorney General Reports, 1980
Opinion No. (1979)
Oklahoma Attorney General Reports, 1979
Opinion No. 79-112 (1979) Ag
Oklahoma Attorney General Reports, 1979

Cite This Page — Counsel Stack

Bluebook (online)
1963 OK 298, 388 P.2d 300, 1963 Okla. LEXIS 561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-s-dickey-clay-mfg-co-v-ferguson-investment-co-okla-1963.