New England Concrete Pipe Corp. v. D/C Systems of New England, Inc.

495 F. Supp. 1334, 1980 U.S. Dist. LEXIS 13131
CourtDistrict Court, D. Massachusetts
DecidedAugust 22, 1980
DocketCiv. A. 75-1327-G
StatusPublished
Cited by3 cases

This text of 495 F. Supp. 1334 (New England Concrete Pipe Corp. v. D/C Systems of New England, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Concrete Pipe Corp. v. D/C Systems of New England, Inc., 495 F. Supp. 1334, 1980 U.S. Dist. LEXIS 13131 (D. Mass. 1980).

Opinion

MEMORANDUM OF DECISION

GARRITY, District Judge.

This case came on for trial on the one count remaining in plaintiff’s twelve count complaint and related crossclaims. Plaintiff, New England Concrete Pipe (New England) was the sub-subcontractor on a private housing project known as Mystic Valley Towers. By this action it seeks to recover $178,994.23 alleged to be owing for materials and labor it supplied to the project.

Plaintiff’s contract was with D/C Systems, Inc., a subcontractor on the project to whom New England was to furnish precast concrete floor members at a price of $1,141,452. D/C Systems in turn had a subcontract with the Dwight Building Company, the general contractor, whose parent corporation is a wholly owned subsidiary of Westinghouse Electric Corporation. Westinghouse played a dual role on the projeetit furnished what was entitled a Bond and Letter of Guarantee purporting to provide security on certain performance and payment obligations of its subsidiary, Dwight, as general contractor; 1 and it had its own sub-subcontract with D/C Systems to install bath and kitchen units. It is the bond and letter of guarantee which lies at the heart of this controversy.

The Owners of the project (also referred to as Sydney and Winn) obtained their financing through the Massachusetts Housing Finance Agency (MHFA). MHFA is a body politic and corporate organized pursuant to the provisions of St.1966, c. 708 as amended. See generally, M.G.L. c. 23A App. Its purpose is to bring together public funds and private enterprise in order to encourage the construction of housing for low and moderate income families. As lender on the Mystic Valley Project, MHFA executed a'loan agreement in 1973 with the Owners, Sydney and Winn, in the principal amount of $13,311,004.

During the course of the construction project, but after plaintiff had delivered the planks to the job site, certain disputes arose concerning the quality of New England’s performance. As a result, sums were charged back on the sub-subcontract and full payment was withheld by D/C Systems *1337 and by Dwight, the general contractor. In August 1974 plaintiff made a demand for payment by letter to Dwight, and thereafter commenced this action. Named as defendants in the original complaint were D/C Systems, Dwight, the Owners (Sydney and Winn), Westinghouse (as guarantor of Dwight’s obligations), and MHPA.

All defendants except D/C Systems moved to dismiss and Judge Skinner of this court heard arguments and received supporting and opposing memoranda. On June 13, 1979, Judge Skinner dismissed all but three counts of the complaint, holding, inter alia, that: (1) the Westinghouse Bond and Letter of Guarantee was not a bond within the meaning of Section 5, St.1971 c. 1030, a provision in the MHFA enabling statute, 2 and that, accordingly, plaintiff had no direct right of action on Westinghouse’s guarantee; (2) plaintiff was not an intended beneficiary of Dwight’s contract with the Owners and could not proceed directly on the contract against Dwight or the Owners; 3 and (3) a cause of action would lie all the same against MHFA on the allegation, implicit in Count X, that MHFA negligently failed to require the Owners to furnish a bond or escrow agreement complying with Section 5, St.1971, c. 1030, which would have secured payment for the labor and materials plaintiff supplied to the project. D/C Systems neither answered nor moved on the pleadings. By the time suit had commenced in 1975 D/C Systems was insolvent and, in light of its default, judgment entered against it on April 1, 1980 for the full amount of plaintiff’s damages, plus interest. 4

Judge Skinner’s ruling left three counts for further proceedings in this session of the court. Two of the counts had only been conditionally sustained by Judge Skinner and we granted summary judgment for the defendants on those counts when plaintiff failed to present evidence of an express independent agreement by the Owners or Dwight to pay for plaintiff’s work. This left only Count X. Plaintiff thus proceeded to trial on the sole issue of whether MHFA had negligently breached a duty owed to plaintiff and other materialmen on the project, to provide a bond or equivalent escrow complying with Section 5.

In February 1980, MHFA answered and cross-claimed against the Owners, Dwight and Westinghouse. The Owners, in turn, cross-claimed against Westinghouse and Dwight. In substance, the cross-claims assert that if MHFA (or the Owners, with respect to their independent cross-claims) is found liable to plaintiffs in the amount of the unpaid labor and materials, then (1) Dwight is liable over to MHFA on its contract with the Owners, of which MHFA is an intended beneficiary; (2) the Owners are liable over to MHFA on the terms of their loan agreement with MHFA which required the Owners to furnish a payment bond; and (3) Westinghouse is liable over to MHFA on the Bond and Letter of Guarantee which was addressed to MHFA and which guaranteed Dwight’s obligations to pay for labor and materials supplied on the project. In this posture the case proceeded to trial.

New England’s Performance on its Sub-subcontract

Preliminary to any question of MHFA’s negligence, plaintiff must show that it fully performed its contract with D/C Systems. The amount plaintiff can claim in damages against MHFA turns on this determination.

New England’s contract with D/C Systems was to furnish and install precast concrete floor planks for a contract price of *1338 $1,141,452. The project specifications required the surface of the planks to be a “standard finish”, acceptable to receive carpet-“small surface holes (less than Vi") caused by air bubbles, minor chips and spalls will be tolerated, but no major or unsightly imperfections, honeycomb, ridges, voids or depressions will be permitted.” The project architect, Alan Haven, determined conformance to specifications. In one instance, New England acknowledged certain imperfections in the finish, and it accepted a backcharge in the amount of $7,293.61. The major dispute, however, involved corrective work in the amount of $48,700.

In October of 1973, Haven, and other field inspectors on the project called to the attention of D/C Systems and Dwight the poor quality of the surface on the floor slabs, most of which had already been delivered to the job site by plaintiff. Dwight was instructed by Haven to correct the deficiencies and, to that end, plaintiff attempted to grind down sample planks to meet specifications. Still not satisfied with plaintiff’s efforts, Haven recommended that $50,000 be withheld on Dwight’s contract until the slabs were made ready to receive carpeting. Ultimately, Dwight had the flooring contractor, Allegheny Flooring, Inc., make the necessary corrections, which involved filling the voids and depressions with a plaster-like substance called levelastic. Dwight paid $48,700 for that work and backcharged D/C Systems in that amount. The backcharge, passed through by D/C Systems to plaintiff, is still disputed by plaintiff who has here included the $48,700 in its claim for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G.M. Builders, Inc. v. Town of Barnstable
469 N.E.2d 1281 (Massachusetts Appeals Court, 1984)
Joseph A. Fortin Construction, Inc. v. Massachusetts Housing Finance Agency
17 Mass. App. Ct. 911 (Massachusetts Appeals Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
495 F. Supp. 1334, 1980 U.S. Dist. LEXIS 13131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-concrete-pipe-corp-v-dc-systems-of-new-england-inc-mad-1980.