G.M. Builders, Inc. v. Town of Barnstable

469 N.E.2d 1281, 18 Mass. App. Ct. 664, 1984 Mass. App. LEXIS 1717
CourtMassachusetts Appeals Court
DecidedOctober 22, 1984
StatusPublished

This text of 469 N.E.2d 1281 (G.M. Builders, Inc. v. Town of Barnstable) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G.M. Builders, Inc. v. Town of Barnstable, 469 N.E.2d 1281, 18 Mass. App. Ct. 664, 1984 Mass. App. LEXIS 1717 (Mass. Ct. App. 1984).

Opinion

Greaney, C.J.

This is an action by G.M. Builders, Inc. (G.M.), against the town of Barnstable (town) seeking $75,000 in damages for the town’s alleged failure to acquire a bond under G. L. c. 149, § 29, as amended through St. 1978, c. 155, § 1, in connection with certain construction work at the Hyannis airport. G.M. claims that it was entitled to protection by such a bond. The action was heard by a Superior Court judge sitting without a jury. The judge entered a memorandum of decision which contained findings of fact and rulings of law. Pursuant to the memorandum, a final judgment entered in the town’s favor. G.M. has appealed.

The judge’s findings of fact are fully supported by the evidence, see New England Canteen Serv., Inc. v. Ashley, 372 [665]*665Mass. 671, 674 (1977), and may be summarized as follows. On October 17,1978, the town, through its airport commission, was informed that a corporation known as LaCipollina at the Airport, Inc. (LaCipollina), intended to assume management of the restaurant at the airport and that, in connection with the takeover, LaCipollina planned renovations of the restaurant premises and nearby areas. LaCipollina’s architect prepared plans for the renovations, which were submitted for approval to the commission. In November, 1978, representatives of LaCipollina attended a meeting of the commission at which the plans and their cost were discussed. The commission approved the intended renovations as well as “the concept of [a] proposed lease” between the town and LaCipollina. On November 27, 1978, the commission sent a “letter of intent” to LaCipollina which outlined the provisions of the proposed lease and included details for payment of the rent. The letter required that “[e]vidence of bonding, disclaimers and hold harmless documents must be presented to the [c]ommission prior to the start of actual construction.”

In meetings in December, 1978, and January, 1979, the commission again discussed the proposed lease with LaCipol-lina’s representatives. These discussions included provisions for reimbursement of LaCipollina for the cost of its renovations. On February 8, 1979, the town through the commission, as lessor, and LaCipollina, as lessee, executed a lease for an initial term of ten years with an option to extend for an additional ten years. Among other provisions, the lease required LaCipollina to pay a fixed annual base rent to the town, together with a percentage of its gross receipts from the operation of the restaurant and cocktail lounge. Article Thirty of the lease recognized that LaCipollina contemplated making renovations to the building containing the demised premises, including additions which would expand the lobby and other nonrestaurant areas and improve the restaurant’s premises and facilities. LaCipollina was given the right to recapture during the initial term of the lease, primarily by way of deductions from percentage rent, the entire cost of each such type of construction, according to specified detailed formulae. The [666]*666only reference to a bond appeared in Article Twenty-One of the lease.1 At the conclusion of the lease were appended various papers collectively referred to as “contract documents”.2

During the same period that LaCipollina was negotiating the terms of the lease with the commission, it was also negotiating with G.M. for the project’s construction. On February 13, 1979, LaCipollina accepted a final proposal from G.M. setting atotal construction price of $265,000 forG.M.’s work. G.M.’s proposal stated that its “figure also includes a performance and payment bond as requested”.3 G.M. was aware of the provisions of the lease and also knew that there had been no public bidding for the job.

G.M. commenced its work under the contract with LaCipol-lina without determining that a bond had been provided for its protection. G.M. made no inquiry to ascertain whether LaCipollina had provided the bond specified in Article Twenty-One of the lease, see note 1, supra. G.M. also failed to consult an attorney to advise it concerning bonds or security. On March 1, 1979, it sent an invoice to LaCipollina “for work completed to date.” Item no. 1 on that invoice requested payment of the premium fee for a bond procured by G.M. pursuant to its agreement with LaCipollina.4

[667]*667LaCipollina encountered financial difficulties, eventually defaulted, and was adjudicated a bankrupt. Before that juncture, however, G.M. and LaCipollina, on May 22, 1979, entered into an additional agreement by which G.M. agreed to accept payment of the sums then owed it by LaCipollina over a three-year period, in equal monthly payments, on a direct reduction basis, and LaCipollina agreed to execute a promissory note therefor with interest. In this agreement, signed for G.M. by its president and treasurer, it was acknowledged that “G.M. has acted as general contractor with respect to [the project] on behalf of [LaJCipollina” (emphasis supplied).

The judge noted that G.M. sought recovery on a theory that the town had violated a duty, imposed on it by the lease and the contract documents, to obtain a bond under G. L. c. 149, § 29, to pay G.M. for its work under the construction agreement. The judge viewed the case as requiring a “close analysis of the relationship of the various parties,” concluding, on the facts found, that “when it came to the work to be done on the [bjuilding, the [ojwner for purposes of the general contract was LaCipollina and not the [t]own,” and that G.M. was LaCipollina’s “general contractor.” On the facts found, the judge ruled that the town had not made any contract which would oblige it to obtain a bond under G. L. c. 149, § 29, and that G.M. had no rights under the bond which LaCipollina had agreed to furnish the town in accordance with Article Twenty-One of the lease.

The first paragraph of G. L. c. 149, § 29, provides, in relevant part, that “[o]fficers or agents contracting in behalf of any . . . town ... for the construction, reconstruction, alteration, remodeling, repair or demolition of public buildings . . . when the amount of the contract ... is more than two thousand dollars, shall obtain security by bond in an amount not less than one half of the total contract price, for payment by the contractor and subcontractor for labor performed or fur[668]*668nished and materials used.” The statute “afford[s] security to subcontractors and materialmen in public works because they do not have the benefit of a mechanic’s or materialman’s lien, as would be the case in private construction work.” Floors, Inc. v. B.G. Danis, Inc., 7 Mass. App. Ct. 356, 358 (1979), S.C., 380 Mass. 91 (1981). See American Air Filter Co. v. Innamorati Bros., 358 Mass. 146, 150 (1970); Peters v. Hartford Acc. & Indem. Co., 377 Mass. 863, 865, 866 (1979). As such, the statute does not afford protection to general contractors who deal directly with public officials. See Friedman v. County of Hampden, 204 Mass. 494 (1910); Duteau v. Salvucci, 330 Mass. 531, 535 (1953). Nor, quite obviously, does the statute cover general contractors who deal with private entities.

There is no dispute that the restaurant and adjacent areas at the airport are portions of public buildings owned by the town or that the project involved “reconstruction” or “remodeling” of such buildings. G.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AMERICAN AIR FILTER CO. INC. v. Innamorati Bros. Inc.
260 N.E.2d 718 (Massachusetts Supreme Judicial Court, 1970)
Duteau v. Salvucci
115 N.E.2d 726 (Massachusetts Supreme Judicial Court, 1953)
New England Canteen Service, Inc. v. Ashley
363 N.E.2d 526 (Massachusetts Supreme Judicial Court, 1977)
Peters v. Hartford Accident & Indemnity Co.
389 N.E.2d 63 (Massachusetts Supreme Judicial Court, 1979)
Floors, Inc. v. B. G. Danis of New England, Inc.
401 N.E.2d 839 (Massachusetts Supreme Judicial Court, 1980)
Floors, Inc. v. B. G. Danis of New England, Inc.
387 N.E.2d 1166 (Massachusetts Appeals Court, 1979)
Friedman v. County of Hampden
90 N.E. 851 (Massachusetts Supreme Judicial Court, 1910)
John D. Ahern Co. v. Trustees of Boston University
421 N.E.2d 477 (Massachusetts Appeals Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
469 N.E.2d 1281, 18 Mass. App. Ct. 664, 1984 Mass. App. LEXIS 1717, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gm-builders-inc-v-town-of-barnstable-massappct-1984.