Yellow Pine Lumber Co. v. Insurance Co. of North America

687 F. Supp. 545, 1988 U.S. Dist. LEXIS 6595, 1988 WL 64904
CourtDistrict Court, W.D. Oklahoma
DecidedMay 5, 1988
DocketNo. CIV-87-681-T
StatusPublished

This text of 687 F. Supp. 545 (Yellow Pine Lumber Co. v. Insurance Co. of North America) is published on Counsel Stack Legal Research, covering District Court, W.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yellow Pine Lumber Co. v. Insurance Co. of North America, 687 F. Supp. 545, 1988 U.S. Dist. LEXIS 6595, 1988 WL 64904 (W.D. Okla. 1988).

Opinion

ORDER

RALPH G. THOMPSON, Chief Judge.

This matter is before the Court for consideration of the Motion for Summary Judgment filed by the defendant Insurance Company of North America (“INA”) and the Motion for Partial Summary Judgment filed by the plaintiff, Yellow Pine Lumber Co., Inc. The parties have responded to each other’s motions, and the issues raised are ready for determination.

This case arises out of the City of Edmond’s awarding of a contract for the construction of the Arcadia Lake Ground Storage Reservoirs to Preload Technologies, Inc. (“Preload”). As a condition to the award of this contract, Preload procured a payment bond as required by Okla.Stat. tit. 61, § 1. This bond, denominated Statutory Bond No. K02298508, was issued by the defendant INA.

After being awarded the contract, Pre-load ordered lumber for the Arcadia Lake project from the defendant A & W Lumber Company (“A & W”). In turn, A & W ordered some of this lumber from the plaintiff, Yellow Pine.

Yellow Pine filed this action to recover some $21,312.36 from A & W for the lumber and other materials that it furnished for use in the Arcadia Lake project. Yellow Pine alleges that the defendant INA is also liable for this sum under the terms of the Statutory Payment Bond procured by the contractor, Preload.

INA now moves for summary judgment on the grounds that Yellow Pine’s claim is not within the coverage of the subject bond. In response, Yellow Pine has moved for partial summary judgment, arguing that its claim is covered by the bond and that, because there is no genuine issue of material fact as to A & W’s liability on three of the four invoices referred to in the [546]*546Complaint, summary adjudication is warranted.1

Both motions are based upon Okla.Stat. tit. 61, §§ 1 and 2, which set forth the required terms of bonds covering public works projects and the procedures to be followed in filing actions on such bonds.

Okla.Stat. tit. 61, § 1 provides (in part): The bond or irrevocable letter of credit shall insure the proper and prompt completion of the work in accordance with the contract and shall insure that the contractor shall pay all indebtedness incurred by said contractor, his subcontractors, and all materialmen for such labor, material, and repair of and parts for equipment as are used and consumed in the performance of said contract. Okla.Stat. tit. 61, § 2 provides (in part): Any person to whom there is due any sum for labor, material or repair to machinery or equipment, furnished as stated in the preceding section, his heirs or assigns, may bring an action on said bond for the recovery of said indebtedness, provided that no action shall be brought on said bond after one (1) year from the day on which the last of the labor was performed or material or parts furnished for which such claim is made. Provided, however, that any person having direct contractual relationship with a subcontractor performing work on said contract, but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond only upon giving written notice to said contractor and surety on said payment bond within ninety (90) days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material or parts for which such claim is made....

INA contends that the “proviso” of section 2, which requires persons who have a direct contractual relationship with a subcontractor but not with the contractor to notify the contractor before bringing suit, precludes persons not having a direct contractual relationship with the contractor or a subcontractor from recovering on bonds for public works projects. According to INA, since Yellow Pine had a direct contractual relationship only with A & W Lumber, and since A & W Lumber was a supplier and not a subcontractor, Yellow Pine is not entitled to bring the instant action.

INA’s argument is based upon Clifford F. MacEvoy Co. v. United States, for the Use and Benefit of Calvin Tomkins Company, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163 (1944). There, the Supreme Court held that persons who do not have a direct contractual relationship with the contractor or a subcontractor may not recover on bonds issued under the Miller Act, 40 U.S. C. § 270a, et seq. Although the Miller Act governs public works projects of the federal government and not such projects undertaken by the State of Oklahoma, INA maintains that, because of the similarity in the language in the Miller Act and Okla.Stat. tit. 61, §§ 1 and 2, the reasoning of MacEvoy should be applied to bar Yellow Pine from bringing suit on the subject bond.

An analysis of INA’s argument requires comparison of the language of the Miller Act and Okla.Stat. tit. 61, §§ 1 and 2. With regard to the procedures to be followed by the parties not having a direct contractual relationship with the contractor, the language of the Miller Act, set forth in 11 U.S.C. § 270b, is nearly identical to the language of Okla.Stat. tit. 61, § 2. The only differences concern the manner of service of notice on the contractor.

However, the section of the Miller Act concerning the scope of the bonds issued under it, 40 U.S.C. § 270a, does contain certain differences from the analogous Oklahoma provision, Okla.Stat. tit. 61, § 1. 40 U.S.C. § 270a(a)(2) requires “A payment bond with surety or sureties ... for the protection of all persons supplying labor and material in the prosecution of the work [547]*547provided for in said contract for the use of each such person.” The Miller Act provision does not state, as does Okla.Stat. tit. 61, § 1, that the bond “shall insure that the contractor shall pay all the indebtedness incurred by said contractor, his subcontractors, and all materialmen for such labor, material, and repair of and parts for equipment as are used and consumed in the performance of said contract.”

INA contends that the above-quoted language of 40 U.S.C. § 270a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Welling v. American Roofing & Sheet Metal Co.
1980 OK 131 (Supreme Court of Oklahoma, 1980)
American Casualty Company v. Town of Shattuck, Okl.
228 F. Supp. 834 (W.D. Oklahoma, 1964)
Standard Accident Insurance v. Basolo
1937 OK 149 (Supreme Court of Oklahoma, 1937)
Limb v. Limb
1945 OK 96 (Supreme Court of Oklahoma, 1945)
City of Purcell v. Merco Manufacturing, Inc.
324 F. Supp. 210 (W.D. Oklahoma, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
687 F. Supp. 545, 1988 U.S. Dist. LEXIS 6595, 1988 WL 64904, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yellow-pine-lumber-co-v-insurance-co-of-north-america-okwd-1988.