Schmidt Bros. Construction Co. v. Raymond Young Men's Christian Ass'n

180 Iowa 1306
CourtSupreme Court of Iowa
DecidedJune 26, 1917
StatusPublished
Cited by9 cases

This text of 180 Iowa 1306 (Schmidt Bros. Construction Co. v. Raymond Young Men's Christian Ass'n) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schmidt Bros. Construction Co. v. Raymond Young Men's Christian Ass'n, 180 Iowa 1306 (iowa 1917).

Opinion

Stevens, J.

On April 18, 1910, Schmidt Bros. Construction Company, of Chicago, appellant herein, entered into a written contract with the Raymond Young- Men’s Christian Association, of Charles City, Iowa, to furnish all the necessary material and labor, and construct for it a Y. M. C. A. building in said city. The contract provided that the building should be constructed according to the plans, drawings and specifications of an architect, and that the material used should be as specified. The contract further provided that the building should be completed on or before November 1st following, and that the association would be allowed as liquidated damages the sum of $15 per day for each and every day required for the construction of the building after November 1, 1910, and that the association would allow the contractor a like sum per day for each and every day that the building should be completed and accepted prior to November 1, 1910, in addition to the price stipulated in the contract. The consideration to be paid the contractor was $56,á7é, same to be paid upon certificates of the superintendent as nearly as possible on the 8th day of each month as the work progressed, monthly payments not to exceed 85 pér cent of all material wrought into the building, plus not to exceed $2,000 in value of the accepted material on the ground, the remainder on satisfactory completion and acceptance of the entire work after the expiration of 30 days.

The contractor began work about April 18th, and continued until May 31st, when work ivas suspended until the [1308]*1308early part of July, when it was resumed and continued until November 19th. Upon the latter date, the contractor abandoned his contract, and the building was subsequently completed by the association at its own expense. Payments were made from time to time by the association up to about the first of November, when, according to the estimate of the superintendent, there was due the contractor $12,019.85. The last payment made was on November 12th, and was in the sum of $6,019.85.

Appellant assigns as its reason for quitting work the first time certain disagreements between its representatives and appellee’s superintendent and some of its officers regarding written orders for extras, and the refusal of appellee to submit to the decision of the- architect a dispute regarding certain material used and on the ground for use in the building; for its final abandonment of the contract, nonpayment by appellee of a past-due monthly installment, and the refusal of appellee to pay a large sum demanded in payment of alleged extras, and to make future settlements upon estimates made by the architect or by appellant. The amount claimed by appellant at this time as due it for extras was $5,130.81. Appellee conceded $1,410.50 of this amount.

Appellant also claimed to have expended and paid for material wrought into the building or on the ground, about $16,500; for labor, $16,082; miscellaneous expense, $1,815; and that it was obligated to subcontractors for about $12,000, making the aggregate paid out and for which it was liable, $46,397; admitted the payment by appellee of $22,009.15, and claimed a balance due of $24,387.85. Appellee claims to have completed the building according to the plans and specifications, at an expense of $23,561.22, and to have suffered damages amounting to $2,925. Appellant offered testimony tending to show that the building could have been completed for approximately $16,000.

[1309]*1309The court found that appellant was entitled to recover the contract price, plus $1,410.50 allowed as extras, or a total of $57,884.50, against which it charged $22,009.15, the amount admitted to have been paid appellant, damages in the sum of $2,925, the cost of completing the building, $23,561.22, and rendered judgment for the balance, $9,389.13, in favor of appellant as principal, adding thereto $1,583.63 as interest, or a total of $10,972.76. The court further found that there was due several subcontractors, who had intervened, in the aggregate, $12,551.17, together with costs amounting to $71.80, and entered judgment against appellant in their favor for the amount due each respectively, and provided that the same be paid from the said judgment. The court further established a lien on the building for the amount found due and owed to appellant.

1- sc0isSon™nare’ grounds “de-' fault of both parties: mechanics’ Hens. I. As above stated, appellant finally quit work on the building and abandoned its contract about November 19, 1910, and, , ,. ,. . , , . while negotiations were carried on between the representatives of the respective parties relative thereto, it never resumed work on the building, and in July, 1911, appellee took charge of arid completed the same at its own expense. After the completion of the building by appellee, the construction company brought a suit in the district court of Floyd County, claiming the sum of $24,595 as the balance due it, and praying foreclosure of a mechanics’ lien. It was alleged in plaintiff’s petition that it had sought to perform its contract according to the terms thereof, and that it was prevented, by reason of the failure and refusal of appellee to make payments under the contract as the same became due, from completing same; that, notwithstanding it caused notice to be served upon appellee prior to November 19th, advising appellee’s officers that it would quit unless full payment was made, appellee neither paid nor tendered payment of the amount claimed to be due; [1310]*1310and that, on account thereof, it was justified in abandoning said contract. The petition further alleges that appellant was entitled to $5,130.81 as compensation for extra material and labor; that it had received payment in the sum of $22,009.15; and that the above balance was due and unpaid.

The contract between the parties provided that payments should be made as nearly as possible on the 8th of each month as the work progressed, in an amount equal to 85 per cent of all material wrought into the building, and material accepted and on the building site, not exceeding $2,000 in' value, and the balance 30 days after the expiration of the date on which the building was completed. Estimates were made by Mr. Emmett, superintendent, in accordance' with the provisions of the contract, for August, September, October and November. Estimates were also made by the representatives of appellant. Payments were made on the contract as follows: August 12th, $4,720.17; September 13th, $2,127.98; October 8th, $3,640; October l'5th, $2,500; October 15th, to subcontractor, $2,600; October 15th, to subcontractor, $400; November 12th, $6,019.85. According to estimate of appellee’s superintendent, it owed appellant, on November 8th, $12,019.85, and, according to appellant’s estimate, the amount due on said date was $16,195.68. But, as above stated, appellee paid $6,019.85, leaving a balance due on November 19th of $6,000.

The contract provided for the settlement of disputes ■ respecting the value of any work added or omitted by the contractor, and ■ such matters as might arise in relation to the contract, the work to be or that had been done or performed under it, or in relation to the plans, drawings and specifications. Disputes as to the work added or omitted were to be submitted to Charles Snyder, and, as to the oth- ■ er matters, referred to Shattuck & Hussey, architects, the decisions of each of said arbiters to be final and binding [1311]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conrad v. Dorweiler
189 N.W.2d 537 (Supreme Court of Iowa, 1971)
Shell Oil Company v. Kelinson
158 N.W.2d 724 (Supreme Court of Iowa, 1968)
Binkholder v. Carpenter
152 N.W.2d 593 (Supreme Court of Iowa, 1967)
Maytag Company v. Alward
112 N.W.2d 654 (Supreme Court of Iowa, 1962)
Jackson Lumber Co. v. Moseley
11 So. 2d 199 (Mississippi Supreme Court, 1942)
In Re Spencer Kellogg & Sons, Inc.
52 F.2d 129 (Second Circuit, 1931)
Johnson v. Vogel
222 N.W. 864 (Supreme Court of Iowa, 1929)
Golwitzer v. Hummel
206 N.W. 254 (Supreme Court of Iowa, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
180 Iowa 1306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schmidt-bros-construction-co-v-raymond-young-mens-christian-assn-iowa-1917.