Greater Lafourche Port Commission v. James Construction Group, L.L.C.

104 So. 3d 84, 2011 La.App. 1 Cir. 1548, 2012 WL 4320228, 2012 La. App. LEXIS 1175
CourtLouisiana Court of Appeal
DecidedSeptember 21, 2012
DocketNo. 2011 CA 1548
StatusPublished
Cited by11 cases

This text of 104 So. 3d 84 (Greater Lafourche Port Commission v. James Construction Group, L.L.C.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Greater Lafourche Port Commission v. James Construction Group, L.L.C., 104 So. 3d 84, 2011 La.App. 1 Cir. 1548, 2012 WL 4320228, 2012 La. App. LEXIS 1175 (La. Ct. App. 2012).

Opinion

PETTIGREW, J.

|2In this contract dispute arising out of a public works construction project, the property owner and the construction contractor settled their claims against each other while reserving their rights against the engineering firm. From a judgment granting the engineering firm’s motion for summary judgment, the contractor has appealed. We reverse and remand.

FACTS

This matter arises out of a contract dispute between the Greater Lafourche Port Commission (“the Port”) and James Construction Group, LLC (“James”) for the construction of a steel sheet piling bulkhead and mooring bits (“the Project”) located at Port Fourchon, Lafourche Parish, Louisiana.1 Prior to entering into a contract with James, the Port, retained Piccio-la & Associates, Inc. (“Picciola”) to provide professional engineering services related to the Project.

On or about May 1, 2004, the Port entered into a written agreement with Picci-ola pursuant to which Picciola agreed to provide “necessary professional services” that included “design phase” as well as “bidding & construction phase” services. Picciola’s design phase services included the preparation of plans and technical specifications that would govern the contractor’s work on the Project. With respect to construction phase services, Pic-ciola agreed to assist the Port in securing and analyzing bids, and awarding the construction contracts. Picciola also agreed to prepare the formal documents for the award of the construction contracts, provide the Port with weekly progress reports, issue instructions from the Port to the contractor, and serve as the Port’s representative with authority to act on the Port’s behalf. The agreement further provided that Picciola would make routine visits to the site, act as interpreter of the terms and conditions of the contract documents, evaluate the contractor’s performance thereunder, and approve and recommend to the Port payments to the contractor.

|sOn December 9, 2004, Picciola issued Addendum No. 1 of the Contract, which provided that the contractor would be assessed stipulated damages of $2,000.00 per day for failure to complete a specific portion of the Project known as the “Delmar Site,” within 210 days of the issuance of the Notice to Proceed.

After public bidding, the Port and James entered into the Contract on January 26, [86]*862005, for the construction of the Project in the amount of $8,405,240.00. The work to be performed was composed of a “Base Bid,” “Alternate A,” and “Alternate B.” The “Base Bid” generally covered construction of roughly 3,000 linear feet of steel sheet piling and mooring bits and associated excavation and filing work. “Alternate A” covered construction of two (2) 30' x 70' Crane Pads. “Alternate B” covered construction of one (1) 67' Diameter Crane Pad Foundation. Both the General Provisions and Special Provisions of the Contract clearly defined the Contract Time, or the number of calendar days allowed for completion of the Project, at 300 days.

That portion of the Project known as the “Delmar Site” was composed of three (3) specific items: (1) Approximately 537 linear feet of bulkhead; (2) Alternate “A” (two (2) 30' x 70' Crane Pads); and (3) Alternate “B” (one (1) 67' Diameter Crane Pad Foundation). All three components of the Delmar Site were originally situated adjacent to the Flotation Canal.

On February 15, 2005, a Pre-Construction meeting was held wherein representatives of the Port, Picciola, and James discussed the possibility of a relocation of the Delmar Site. Thereafter plans were revised on March 15, 2005, and reissued on April 4, 2005, which depicted the Delmar Site, including Alternate “A” and Alternate “B” being moved or relocated from the Flotation Canal to Slip B. To accomplish this change, James requested an additional $144,459.77 in compensation and nine (9) additional contract days. On April 27, 2005, the Port granted James’ request and executed “Plan Change No. 1.”

The Notice to Proceed defined the commencement of the Contract Time as April 25, 2005. Plan Change No. 1 relocated the Delmar Site in exchange for the additional $144,459.77 with nine (9) additional days added to the 300-day Contract Time. Plan |4Change No. 1 also extended the Contract completion date from February 18, 2006 to February 27, 2006. On January 5, 2006, the Contract Time was extended an additional thirty-six (36) calendar days pursuant to “Plan Change No. 2,” which compensated James for delays resulting from Hurricanes Katrina and Rita. As a result of these extensions, the Contract Time was extended an additional forty-five (45) days. Consequently, the Revised Contract Completion Date was extended to April 4, 2006 (345 days from the Notice to Proceed) and the interim deadline for completion of the Delmar Site was extended to January 5, 2006 (245 days from the Notice to Proceed). The Delmar Site was completed on May 17, 2006, 133 days past the interim deadline of January 5, 2006. Accordingly, the Port withheld $266,000.00 (133 days @ $2,000.00 per day) from the payment to James as stipulated damages resulting from the failure of James to complete the Delmar Site in a timely manner.

PROCEDURAL HISTORY

As mandated by La. R.S. 38:2243, the Port filed the instant concursus proceeding in Lafourche Parish on November 21, 2006, to disburse the funds retained. In response, James filed an Answer, Recon-ventional Demand and Third Party Demand on March 7, 2007, wherein James asserted claims and demands against both the Port and Picciola. Specifically, James claimed that the Port breached its contract with James by improperly withholding and retaining liquidated damages, retainage, and the contract balance of $756,909.00. James further claimed that it detrimentally relied on certain representations by Pic-ciola to the effect that it would not be required to complete the Delmar Site within 210 days and that the associated [87]*87provision of Addendum No. 1 relating to stipulated damages would be waived. Accordingly, James asserted claims for improperly withheld stipulated damages and additional costs it allegedly incurred due to its re-sequencing of the work based upon Picciola’s representations that stipulated damages related to the Delmar Site would be waived. James took the position that because the Port and Picciola had allegedly caused and/or contributed to the project delays, the Port was not entitled to liquidated damages.

|fiThe Port and James later settled their disputes and submitted a Joint Motion for Partial Dismissal of all claims against each other with each party expressly reserving all remaining rights, claims, and defenses against the remaining defendant, Picciola. Thereafter, James filed a First Amended and Supplemental Incidental Demand naming Picciola’s insurer, Lloyds of London (“Lloyds”), as a third party defendant in this matter.

On March 28, 2011, Picciola filed a Motion for Summary Judgment seeking a dismissal of all of James’ claims against Picci-ola. With respect to James’ claims that it was entitled to recover from Picciola the full amount of any judgment for liquidated damages, Picciola contended that James’ release of its claims against the Port as principal also released any claims against Picciola as the Port’s disclosed agent. As to James’ claims that Picciola negligently issued ambiguous or defective plans and contract documents thereby misleading James and causing delays, disruptions, and increased costs, Picciola further contended that James had no evidence to establish these claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Government Employees Insurance Co.
220 So. 3d 915 (Louisiana Court of Appeal, 2017)
Balthazar v. Hensley R. Lee Contracting, Inc.
214 So. 3d 1032 (Louisiana Court of Appeal, 2017)
Louisiana Board of Ethics In re Villere
208 So. 3d 940 (Louisiana Court of Appeal, 2016)
James v. Berkley Insurance Co.
206 So. 3d 393 (Louisiana Court of Appeal, 2016)
Prime Insurance Co. v. Imperial Fire & Casualty Insurance Co.
151 So. 3d 670 (Louisiana Court of Appeal, 2014)
Monroe Surgical Hospital, LLC v. St. Francis Medical Center, Inc.
147 So. 3d 1234 (Louisiana Court of Appeal, 2014)
Iteld v. Four Corners Construction, L.P.
133 So. 3d 312 (Louisiana Court of Appeal, 2014)
Davis v. Canadian National Railway
124 So. 3d 585 (Louisiana Court of Appeal, 2013)
Smith v. Kopynec
119 So. 3d 835 (Louisiana Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
104 So. 3d 84, 2011 La.App. 1 Cir. 1548, 2012 WL 4320228, 2012 La. App. LEXIS 1175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/greater-lafourche-port-commission-v-james-construction-group-llc-lactapp-2012.