Standard Roofing Co. v. ELLIOT CONST. CO.

535 So. 2d 870, 1988 WL 131168
CourtLouisiana Court of Appeal
DecidedNovember 30, 1988
Docket87 CA 0506
StatusPublished
Cited by14 cases

This text of 535 So. 2d 870 (Standard Roofing Co. v. ELLIOT CONST. CO.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Roofing Co. v. ELLIOT CONST. CO., 535 So. 2d 870, 1988 WL 131168 (La. Ct. App. 1988).

Opinion

535 So.2d 870 (1988)

STANDARD ROOFING COMPANY OF NEW ORLEANS
v.
ELLIOT CONSTRUCTION COMPANY, INC., et al.

No. 87 CA 0506.

Court of Appeal of Louisiana, First Circuit.

August 22, 1988.
As Amended November 30, 1988.
Writs Denied February 17, 1989.

*872 Jack Alltmont, New Orleans, for plaintiff-appellant Standard Roofing Co. of New Orleans.

Douglas Kewley, Metairie, for third party plaintiff-appellant Celotex Corp.

John C. Miller, Baton Rouge, for third party defendant-appellant August Perez and Associates.

Gordon A. Pugh, Baton Rouge, for defendant-appellant Elliott Const. Co.

Daniel Atkinson, Baton Rouge, for third party defendant-appellant U.S. Fidelity and Guar. Co.

Robert E. Redmann, New Orleans, for defendant-appellee State of La.

Ben Lightfoot, Baton Rouge, for defendant-appellee National Gypsum Co.

Before WATKINS, CARTER and FOIL, JJ.

CARTER, Judge.

This is a suit arising from a defective roof installed pursuant to a construction contract. Plaintiff, the roofing subcontractor, appeals the trial court's decision requiring it to pay $309,044.00 to the general contractor and dismissing its third party demands.

The parties to the appeal are: (1) the State of Louisiana (State), the owner of the building under construction; (2) Standard Roofing Company of New Orleans, Inc. (Standard), plaintiff and roofing subcontractor; (3) August Perez and Associates, Inc. (Perez), the project architect; and (4) Celotex Corporation (Celotex), the supplier of the roofing system. Elliot Construction Company (Elliot), the general contractor, also appealed, but then settled its claims with Standard and Standard's surety/insurer, United States Fidelity and Guaranty Company (USF & G). Elliot and USF & G assigned to Standard all rights on appeal against third parties.

The State contracted with Elliot, as general contractor, and Perez, as architect, for the construction of the Community Educational Assembly and Athletic Center (minidome) on the Baton Rouge campus of Southern University. Elliot subcontracted with Standard to provide the labor and materials necessary to install the roofing system on the domed roof. Standard purchased the roofing system materials specified in Perez's plans and specifications from Celotex.

After Standard applied the recommended roofing system to the major portion of the domed roof, Perez rejected Standard's work for failure to follow plan specifications. The rejection was based on two problems—the roof's failure to be watertight and its wrinkled appearance.

A second roofing subcontractor was hired and applied Celotex's roofing system following all plan specifications. Prior to completion, it became apparent that the second roof, although watertight, also had an unacceptable wrinkled appearance. After changes were made in installation procedures, the roof's appearance was deemed acceptable, and it was completed.

Initially, Standard sued Elliot and Aetna Casualty and Surety Company (Aetna), the insurer of Elliot's construction bond, for the $81,886.60 balance allegedly due under its roofing subcontract. Elliot reconvened against Standard and the State seeking damages based on the necessity of replacing the first roof and the associated delays. Standard filed third party demands against the following parties: (1) the project architect, Perez; (2) National Gypsum, the manufacturer of the roof decking referred to as tectum; (3) Celotex, the supplier of the roofing system; and (4) the State. Elliot filed a reconventional demand against Standard and USF & G and third party demands against: (1) the State; (2) National Gypsum;[1] and (3) Celotex. Perez filed a third party demand against the State and Celotex. Numerous other demands were filed by the various parties.

The district court rendered judgment against Standard and in favor of Elliot in the amount of $309,044.00 for damages caused by Standard's breach of the roofing subcontract. USF & G was found solidarily *873 liable with Standard for the limits of its performance bond. The claims against all other parties were dismissed. Standard appeals the judgment in favor of Elliot, as well as the dismissal of its original action and third party demands.[2] Standard is also asserting the rights of Elliot and USF & G obtained through assignment, against the State and Celotex. Standard seeks to recover in whole, or in part, the amounts for which it was cast by the trial court, together with the amount allegedly due under its subcontract. Additionally, Standard seeks reimbursement of attorney's fees and costs from Celotex based upon the redhibitory defects in the roofing system.

The issues on appeal are as follows:

(1) The parties responsible for paying the costs incurred in replacing the roof and the basis of that responsibility;
(2) The damages incurred in replacing the roof; and
(3) Standard's right to reimbursement for attorney's fees and costs from Celotex under the theory of redhibition.

FACTS

In February of 1972, the State of Louisiana, through the Capital Outlay Budget Board, Division of Administration, (State) entered into a contract with Elliot for the construction of the minidome. The minidome was described by the trial judge in his written reasons for judgment as follows:

The Mini-Dome is a large circular building. The dome affect (sic) is created by the roof structure. It consisted of thirty-two (32) metal beams, also referred to as ribs or rib beams. These beams extended from a tension ring just below the top of the interior side of the exterior wall upwards to a compression ring at the top of the dome. A series of metal purlins between each rib lent lateral support to the rib beams and the two constituted the frame work upon which the decking and the roofing material were to be placed.

The rib beams each consisted of six sections fabricated end to end to give the beam the desired arch. With the beams all in place and viewed from the top, the corresponding end of each section of each beam formed a series of rings and were referred to as such. There were seven such rings, commencing with the compression ring at the top (Ring 1) down to the end of the last section of the beam at the interior wall (Ring 7). The area at Ring 7 and the interior wall throughout the circumference of the building was referred to as the valley. The area between each rib beam was referred to as a bay of which there were thirty-two (32). At the bottom of the alternate bays were located downspouts. The roofing material was installed in horizontal fashion in each bay from the bottom of the dome to the compression ring.

According to Perez's plans, a product known as "tectum" was laid on top of the beams and purlins by Elliot to form the roof deck. Tectum, which is manufactured by National Gypsum, is a composite board, resembling shredded wheat, and composed of shredded wood-type material compressed into boards and cemented together. It is approximately three inches thick and, as per the dome plans, came with a factory-applied felt (roofing paper) on what was to be its outer surface.

Standard was then to glue the roof covering, known as "Chem-Ply," to the tectum's factory-applied felts in horizontal strips with an epoxy adhesive. Chem-Ply, which is manufactured by Celotex, is a white, vinyl-like sheet material with a foam-backing. It was purchased and provided by Standard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abs Servs., Inc. v. James Constr. Grp.
269 So. 3d 723 (Louisiana Court of Appeal, 2018)
Lloyd's Syndicate 457 v. Am. Global Mar. Inc.
346 F. Supp. 3d 908 (S.D. Texas, 2018)
Josh Norris v. Garry Causey
869 F.3d 360 (Fifth Circuit, 2017)
N. Clark, L.L.C. v. Chisesi
206 So. 3d 1013 (Louisiana Court of Appeal, 2016)
Akers v. Bernhard Mechanical Contractors, Inc.
137 So. 3d 818 (Louisiana Court of Appeal, 2014)
Greater Lafourche Port Commission v. James Construction Group, L.L.C.
104 So. 3d 84 (Louisiana Court of Appeal, 2012)
Harris Builders, L.L.C. v. URS Corp.
861 F. Supp. 2d 746 (E.D. Louisiana, 2012)
Lingoni v. Hibernia National Bank
33 So. 3d 372 (Louisiana Court of Appeal, 2010)
Young v. City of Plaquemine
818 So. 2d 892 (Louisiana Court of Appeal, 2002)
Theriot v. Bourg
691 So. 2d 213 (Louisiana Court of Appeal, 1997)
Thibaut v. Thibaut
607 So. 2d 587 (Louisiana Court of Appeal, 1992)
Colbert v. BF Carvin Const. Co.
600 So. 2d 719 (Louisiana Court of Appeal, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
535 So. 2d 870, 1988 WL 131168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-roofing-co-v-elliot-const-co-lactapp-1988.