Century Ready-Mix Co. v. Campbell County School District

816 P.2d 795, 1991 Wyo. LEXIS 126, 1991 WL 157611
CourtWyoming Supreme Court
DecidedAugust 20, 1991
Docket90-129
StatusPublished
Cited by50 cases

This text of 816 P.2d 795 (Century Ready-Mix Co. v. Campbell County School District) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Century Ready-Mix Co. v. Campbell County School District, 816 P.2d 795, 1991 Wyo. LEXIS 126, 1991 WL 157611 (Wyo. 1991).

Opinions

GOLDEN, Justice.

Appellant Century Ready-Mix Company (Century) appeals the trial court’s orders granting summary judgment to appellees in this suit arising out of an agreement to provide concrete for an addition to Campbell County High School in Gillette, Wyoming.

Appellant raises the following issue:

[Whether] [t]he District Court erred in granting Summary Judgment to Appel-lees, Campbell School District, Rundquist & Hard, P.C., and Chris Hard, and Tom Barker dba Cooper Engineering & Material Testing.

We affirm the orders granting summary judgment.

FACTS

This case is before us a second time. In Century Ready-Mix Company v. Lower & Company, 770 P.2d 692 (Wyo.1989) (Century I), we reversed summary judgment entered against Century and in favor of Lower & Company, the general contractor. We are now faced with an appeal from orders granting summary judgment to the other defendants.

Some of the facts presented here overlap those of our earlier opinion. In 1986, Campbell County School District (CCSD) decided to expand the Campbell County High School building in Gillette. CCSD let bids, and Lower & Company (Lower) was chosen as the general contractor for the project. Lower entered into a detailed, standard form agreement with CCSD.

Appellee Rundquist & Hard contracted with CCSD to provide architectural services. Rundquist & Hard signed a written standard-form contract with CCSD. Appel-lee Tom Barker, doing business as Cooper Engineering and Materials Testing (C.E. & M.T.), was hired by CCSD to do initial geotechnical investigation and to provide materials testing after construction began, apparently without a formal, written contract.1

Century received a purchase order from Lower to supply concrete for the project. C.E. & M.T. tested samples of Century’s concrete as it was poured. The results of some of the 28-day tests2 showed that the concrete samples failed to meet the design [798]*798specifications required by the district. Specifically, the concrete broke at lower pressures than those required.

Century then called in an independent expert to evaluate C.E. & M.T.’s testing procedures. The expert, William Rossi, found that C.E. & M.T.’s testing procedures did not meet American Concrete Institute (ACI) and American Society for Testing in Materials (ASTM) standards. He characterized the procedures used by C.E. & M.T. for testing Century’s concrete as “the most careless and negligent procedures I had observed in 27 years of concrete testing.”

Chris Hard, the architect, recommended to the school board that core samples of the concrete already in place be removed and tested. Testing showed that the concrete in place met the design requirements and specifications.

The school board met on February 10, 1987. At this meeting, Chris Hard gave a progress report on construction of the high school addition. Larry Hite, one of the school board members, questioned Hard about the quantity of concrete already poured and then made a motion to stop the pouring of concrete until the testing problems could be worked out. During the discussion which ensued on this motion, Tom Barker of C.E. & M.T. stated that the unusual variations noticed in the stress the samples could handle was “probably a mistake in the ingredients.” Barker suggested that the job ought to continue under “more intense investigative activities to lay the basis for design mix revision.”

Hite asked Chris Hard for his opinion whether there was a problem with continuing to pour. Hard responded that in his opinion there was no major problem. He indicated that the already-poured concrete met the specifications of the bid. Nevertheless, the board voted to suspend pouring.

Barker then informed the board that an expert from the School of Mines in Rapid City had reviewed the procedures used on the projects and had indicated that the testing procedures were not the cause of the inconsistent test results. He stated that he “hoped” that the error was a product error, rather than a testing error.

After the meeting, Hard telephoned Jack Ylitalo, Lower’s project coordinator, and advised him of the board’s ruling. Hard received a return call from Dennis Lower, Jr., who asked him whether pouring could continue if the concrete supplier were changed. Hard stated he would pass this request on to the board.

Hard returned, at about 5:00 p.m., to the area where the board met. Most of the board members were still present. After explaining to board member Larry Hite that there may not have been a problem with the concrete, Hard presented Lower’s proposal to change concrete suppliers to various board members, and got their assent. (Apparently, no formal motion was made, nor is there any indication of official action taken in the board minutes on this point). Hard then called Lower back and they agreed to proceed quickly with the new supplier. The new supplier began pouring the next day.

Century sued Lower, the general contractor, for breach of contract. It sued CCSD for intentional interference with contract, negligent hiring, defamation, and breach of contract. It sued Tom Barker d/b/a C.E. & M.T. for negligence, intentional interference with contract, and defamation. It sued Chris Hard, individually, and Hard & Rundquist, P.C., for negligence and malpractice in breach of their contractual duties to the other defendants. The surviving claims involved in this appeal are against CCSD, Tom Barker d/b/a C.E. & M.T., and Chris Hard and Rundquist & Hard, P.C.

DISCUSSION

Standard of Review

Summary judgment is properly granted only where there is no genuine issue of material fact and the prevailing party is entitled to judgment as a matter of law. State of Wyoming v. Homar, 798 P.2d 824, 826 (Wyo.1990); Teton Plumbing and Heating, Inc. v. Board of Trustees, Laramie County School District No. [799]*799One, 763 P.2d 843, 847 (Wyo.1988). When reviewing a grant of summary judgment,

we review the judgment in the same light as the district court, using the same information. A party moving for summary judgment has the burden of proving the nonexistence of a genuine issue of material fact. Material fact has been defined as one which, if proved, would have the effect of establishing or refuting an essential element of the cause of action or defense asserted by the parties. Upon examination of a summary judgment, we view the record from the vantage point most favorable to the party opposing the motion, giving him all favorable inferences which may be drawn from the facts.

Doud v. First Interstate Bank of Gillette, 769 P.2d 927, 928 (Wyo.1989) (quoting Garner v. Hickman, 709 P.2d 407, 410 (Wyo.1985)).

If we can uphold summary judgment under the record presented under any proper legal theory, we will do so. Reeves v. Boatman, 769 P.2d 917, 918 (Wyo.1989).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Excel Construction, Inc. v. HKM Engineering, Inc.
2010 WY 34 (Wyoming Supreme Court, 2010)
D & D Transport, Ltd. v. Interline Energy Services, Inc.
2005 WY 86 (Wyoming Supreme Court, 2005)
In Re Estate of Drwenski
2004 WY 5 (Wyoming Supreme Court, 2004)
Natrona County v. Blake
2003 WY 170 (Wyoming Supreme Court, 2003)
Birt v. Wells Fargo Home Mortgage, Inc.
2003 WY 102 (Wyoming Supreme Court, 2003)
Owsley v. Robinson
2003 WY 33 (Wyoming Supreme Court, 2003)
Hoblyn v. Johnson
2002 WY 152 (Wyoming Supreme Court, 2002)
Hasvold v. Park County School District Number 6
2002 WY 65 (Wyoming Supreme Court, 2002)
Hulse v. First American Title Co. of Crook County
2001 WY 95 (Wyoming Supreme Court, 2001)
Beaulieu v. Florquist
2001 WY 33 (Wyoming Supreme Court, 2001)
Estate of Corpening v. Corpening
2001 WY 18 (Wyoming Supreme Court, 2001)
Vernon T. Delgado Family Ltd. Partnership v. Shaw
9 P.3d 982 (Wyoming Supreme Court, 2000)
Brown v. Life Insurance Co. of North America
8 P.3d 333 (Wyoming Supreme Court, 2000)
Fontaine v. Board of County Com'rs of Park County
4 P.3d 890 (Wyoming Supreme Court, 2000)
Unicorn Drilling, Inc. v. Heart Mountain Irrigation District
3 P.3d 857 (Wyoming Supreme Court, 2000)
Farmers Insurance Exchange v. Dahlheimer
3 P.3d 820 (Wyoming Supreme Court, 2000)
Schuler v. Community First National Bank
999 P.2d 1303 (Wyoming Supreme Court, 2000)
Waid v. State Ex Rel. Department of Transportation
996 P.2d 18 (Wyoming Supreme Court, 2000)
Taylor v. Schukei Family Trust Ex Rel. Schukei
996 P.2d 13 (Wyoming Supreme Court, 2000)
Osborn v. Anadarko Petroleum Corp.
996 P.2d 9 (Wyoming Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
816 P.2d 795, 1991 Wyo. LEXIS 126, 1991 WL 157611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/century-ready-mix-co-v-campbell-county-school-district-wyo-1991.