Dehnert v. Arrow Sprinklers, Inc.

705 P.2d 846, 1985 Wyo. LEXIS 549
CourtWyoming Supreme Court
DecidedAugust 29, 1985
Docket84-142
StatusPublished
Cited by19 cases

This text of 705 P.2d 846 (Dehnert v. Arrow Sprinklers, Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dehnert v. Arrow Sprinklers, Inc., 705 P.2d 846, 1985 Wyo. LEXIS 549 (Wyo. 1985).

Opinions

ROSE, Justice.

Architect Eugene F. Dehnert and the architectural firm of Dehnert, Richardson and Bensman appeal from the judgment entered on a jury verdict awarding $400,-000 in compensatory damages to appellee Arrow Sprinklers, Inc., upon its claim that appellants intentionally interfered with its landscaping and irrigation contract with Fremont County School District No. 1. We will hold that the evidence was insufficient to establish that appellants acted without justification in recommending that the school board terminate appellee’s contract, and will, therefore, reverse the judgment of the district court.

FACTS

Dehnert, Richardson and Bensman entered into a contract with Fremont County School District No. 1 on April 14, 1978 to study the district’s educational facilities and requirements and to design and administer various construction projects. The contract obligated the architectural firm to advise and consult with the owner/school district during the construction phase, to inform the owner of the progress and quality of the work, and to “endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor.” The architect had authority under the contract to issue certificates for payment to contractors when appropriate and to reject work which did not conform to construction specifications.

The contract authorized the architect to approve a contractor’s proposals only for conformance with the design concept and with contract requirements:

“1.5.13 The Architect shall review and approve or take other appropriate action upon the Contractor’s submittals such as Shop Drawings, Product Data and Samples, but only for conformance with the design concept of the Work and with the information given in the Contract Documents.”

[848]*848Any changes in the work, other than minor adjustments, had to be approved by the school district pursuant to a formal change order:

“1.5.14 The Architect shall prepare Change Orders for the Owner's approval and execution in accordnace with the Contract Documents, and shall have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or an extension of the Contract Time which are not inconsistent with the intent of the Contract Documents.”

Appellant Dehnert represented the architectural firm in its performance of this contract.

The construction projects contemplated by this contract included the installation of sprinkler systems and- landscaping for three elementary schools in Lander, Wyoming. Appellants hired the engineering firm of Nelson, Melius & Associates, P.C. to act as a consultant for these projects. Harold Diddle, a mechanical designer and employee of Nelson, Melius and Associates, actually prepared the performance specifications for the irrigation systems and the landscaping.

The documents distributed to potential bidders on these projects specified the use of brass sprinkler heads, known as “SAM” heads,1 or an approved equal. Contractors wishing to submit bids on the basis of equipment other than that specified were required to obtain prior approval from the architect. A successful bidder who had not obtained prior approval to substitute materials could, according to the bidding documents, apply in writing for permission to do so:

“After execution of Contracts, should Contractor desire to substitute materials and/or methods not approved prior to bid opening, apply in writing for such permission stating:
“1. Cause for request with substantiating documents.
“2. Documentary proof of equal or superior quality.
“3. Delivery time.
“4. Costs in the form of certified quotations from suppliers of both specified and proposed materials.
“Approved substitutions will be incorporated into the work by Change Order under conditions of the General Conditions.” (Emphasis added.)

The General Conditions of the Contract for Construction, A/A Document A201, prepared by The American Institute of Architects and incorporated into the bidding documents, defines a change order as a written authorization from the owner and the Architect to deviate from contract requirements:

“12.1.1 A Change Order is a written order to the Contractor signed by the Owner and the Architect, issued after execution of the Contract, authorizing a change in the Work or an adjustment in the Contract Sum or the Contract Time.”

Without obtaining prior approval pursuant to the bidding documents, appellee Arrow Sprinklers submitted a bid to the school board based on the use of a nonspe-cified, plastic sprinkler head, known as the “15103” head. At the bid opening on August 4, 1981, Calvin Bishop, president of Arrow Sprinklers, informed members of the school board that he intended to use the plastic sprinkler heads. The board awarded the construction contract to appel-lee as the low bidder on the project.

The agreement between the school district and Arrow Sprinklers, dated August 5, 1981, incorporated by reference the project specifications as well as the General Conditions of the Contract for Construction prepared by The American Institute of Architects. These General Conditions describe the roles of the owner, the architect, and the contractor, and include the architect’s powers and duties as set out in the [849]*849agreement between appellants and the school district.

On August 11, 1981, Calvin Bishop, representing appellee, and a consultant met with Harold Diddle who had prepared the specifications for the sprinkler system on behalf of appellants.2 Appellee submitted to Diddle a letter proposing to use certain irrigation equipment, including the 15108 head. The letter referred to the proposed head by number only and contained no information as to its quality or cost. Ap-pellee also presented to Diddle its blueprints or “layouts,” listing the 15103 head in the legend, and some catalogs describing various sprinkler equipment. After Diddle and Bishop discussed the differences between the proposed sprinkler heads and the specified SAM heads, Diddle expressed his approval of the nonspecified plastic heads. Bishop and Diddle then presented the layouts and submittal letter to appellant Deh-nert, who verbally approved the plans after eliciting Diddle’s opinion that the proposed system would work.

On August 17, 1981, Dehnert advised appellee in writing of the architectural firm’s conditional acceptance of the layouts:

“We are hereby accepting your lay-outs with any qualifications noted in the Specifications, as well as those noted on the attached letter.”

The attached letter from the engineering firm noted certain minor items for revision, but contained no objection to the proposed plastic sprinkler heads. Bishop’s submittal letter of August 11 was returned to him, bearing Diddle’s notation that only the proposed pumps were rejected.

With its plans thus approved, Arrow Sprinklers began work on the landscaping project in late August. By early November, Dehnert had reported to the school board that the project was substantially complete'and had certified payments to ap-pellee representing 78 to 90 percent of the total contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiMaria Const., Inc. v. Interarch
799 A.2d 555 (New Jersey Superior Court App Division, 2001)
Dan Nelson Construction, Inc. v. Nodland & Dickson
2000 ND 61 (North Dakota Supreme Court, 2000)
Wiekhorst Bros. Excavating & Equipment Co. v. Ludewig
529 N.W.2d 33 (Nebraska Supreme Court, 1995)
Century Ready-Mix Co. v. Campbell County School District
816 P.2d 795 (Wyoming Supreme Court, 1991)
Young v. WEST COAST INDUST. RELATIONS ASS'N, INC.
763 F. Supp. 64 (D. Delaware, 1991)
Four Nines Gold, Inc. v. 71 Construction, Inc.
809 P.2d 234 (Wyoming Supreme Court, 1991)
Four Nines Gold, Inc. v. 71 Const., Inc.
809 P.2d 236 (Wyoming Supreme Court, 1991)
Dynan v. Rocky Mountain Federal Savings & Loan
792 P.2d 631 (Wyoming Supreme Court, 1990)
Price v. Sorrell
784 P.2d 614 (Wyoming Supreme Court, 1989)
Carlson v. Carlson
775 P.2d 478 (Wyoming Supreme Court, 1989)
Wyoming Sawmills, Inc. v. Morris
756 P.2d 774 (Wyoming Supreme Court, 1988)
First Wyoming Bank, Casper v. Mudge
748 P.2d 713 (Wyoming Supreme Court, 1988)
Western Utility Contractors, Inc. v. City of Casper
731 P.2d 24 (Wyoming Supreme Court, 1986)
Texas West Oil and Gas Corp. v. Fitzgerald
726 P.2d 1056 (Wyoming Supreme Court, 1986)
Dehnert v. Arrow Sprinklers, Inc.
705 P.2d 846 (Wyoming Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
705 P.2d 846, 1985 Wyo. LEXIS 549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dehnert-v-arrow-sprinklers-inc-wyo-1985.