Excel Construction, Inc. v. HKM Engineering, Inc.

2010 WY 34, 228 P.3d 40, 2010 Wyo. LEXIS 38, 2010 WL 1032010
CourtWyoming Supreme Court
DecidedMarch 23, 2010
DocketS-09-0120
StatusPublished
Cited by23 cases

This text of 2010 WY 34 (Excel Construction, Inc. v. HKM Engineering, Inc.) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Excel Construction, Inc. v. HKM Engineering, Inc., 2010 WY 34, 228 P.3d 40, 2010 Wyo. LEXIS 38, 2010 WL 1032010 (Wyo. 2010).

Opinion

DAVIS, District Judge.

[T1] This is an appeal from a summary judgment granted to Appellee HKM Engineering by the district court for Big Horn County. For the reasons set forth below, we affirm the district court.

ISSUES

[12] 1. Should this Court modify its ruling in Rissler & McMurry Co. v. Sheridan Area Water Supply Joint Powers Bd., 929 P.2d 1228 (Wyo.1996), to permit negligence claims by general contractors against project engineers or design professionals?

2. May Excel Construction maintain a claim against HKM for tortious interference with the contract between Exeel Construction and the Town of Lovell when HKM was acting as Lovell's agent?

3. May Exeel Construction maintain a claim of misrepresentation on the basis asserted in the trial court under the Rissler decision?

4. Does 19.10(A) of the agreement between the Town of Lovell and HKM impose a duty of good faith and fair dealing on HKM, creating an issue which must be tried?

FACTS

[13] This case involves a dispute between general contractor Exeel Construction, Inc. ("Excel") and project engineer HKM Engineering, Inc. ("HKM") related to a contract for the replacement and improvement of water and sewer lines in the Town of Lovell, Wyoming. The record before the Court is sparse, with only portions of the contract documents supplementing the pleadings below. The following can be gleaned from the *43 record, the briefing, and the arguments of counsel.

[14] The Town of Lovell entered into an agreement with HKM Engineering, Inc. for engineering services on the project, including both design of the new water and sewer system and project management. In the terms pertinent to this appeal, the agreement provided that HKM would be the Town of Lovell's representative during construction. HKM was to make periodic site visits, and to assure that work progressed in accordance with project plans and specifications. If the parties agreed, HKM was to provide a project representative to provide more extensive observation of the work. The record does not reflect whether this occurred or not.

[15] HKM was empowered to issue written clarifications of the contract documents, to authorize minor variations in the work, and to reject defective work by the contractor. HKM was also authorized by the agreement with the Town of Lovell to determine compliance of completed work with the contract requirements, and to act as an impartial interpreter and judge in so doing.

[T6] The contract between the Town of Lovell and HKM also provided as follows in 9.10(A):

Neither ENGINEER's authority or responsibility under this Article 9 or under any other provision of the Contract Doeu-ments nor any decision made by ENGINEER in good faith either to exercise or not exercise such authority or responsibility or the undertaking, exercise, or performance of any authority or responsibility by ENGINEER shall create, impose, or give rise to any duty in contract, tort, or otherwise owed by ENGINEER to CONTRACTOR, and Subcontractor, any Supplier, any other individual or entity, or to any surety for or employee or agent of any of them.

[17] The Town of Lovell entered into a separate agreement with Excel to serve as general contractor on the project. Only a small portion of the contract between the town and Exeel are in the record. In any event, Excel and HKM each contracted separately with the Town of Lovell, and there is no contract between HKM and Exeel. The provisions of 1 9.10 of the Town of Lovell-HKM contract are incorporated in the Town of Lovell-Exeel contract by § 9.01(A)(4).

[T8] The record does not reflect any detailed information as to the nature of the dispute which arose between HKM and Excel. At oral argument, counsel for Excel gave as examples of Excel's claims that HKM's specifications called for insufficient backfill in certain locations, and that Excel was told by HKM representatives to simply purchase the required backfill and bill all of the charges for it at the end of the month, rather than submitting an immediate request for a change order or payment. Excel claims that HKM engaged in misrepresentation and other tortious conduct in making that representation, and that it was not paid for the cost of the additional backfill after it relied on HKM's direction. Counsel also claimed that HKM released Excel from the worksite with the understanding that it would return to complete some minor work, and then attempted to assess liquidated delay damages for the time during which Excel was not working after being released. It also claims that HKM improperly denied certification of substantial completion. Until substantial completion is certified, Excel cannot obtain the funds held as retainage to insure completion of the project.

[T9] Excel initially filed suit against the Town of Lovell on February 5, 2008. It claimed breach of contract, breach of an implied covenant of good faith and fair dealing, account stated, unjust enrichment, and entitlement to a declaratory judgment for amounts due under the agreement between the parties The town counterclaimed for damages based on alleged breaches of contract by Excel. Exeel amended its complaint to join HKM as a party-defendant on June 13, 2008, claiming that HKM had engaged in the tort of misrepresentation, breached a duty of good faith and fair dealing, intentionally interfered with Excel's contract with the Town of Lovell, and acted negligently. In its complaint, Excel accused HKM of unreasonably refusing to certify substantial completion of the work, and of hindering and delaying Excel's work by refusing to meet, approve change orders after *44 altering the seope and duration of the work, refusing to provide accurate and buildable drawings for the work, and generally of interfering with Excel's performance of its contract.

[T10] Defendant HKM filed a motion to dismiss on August 8, 2008. In that motion, it contended that the complaint must be dismissed under Rissler & McMurry Co. v. Sheridan Area Water Supply Joint Powers Bd., 929 P.2d 1228 (Wyo.1996), which determined that a contractor's claims against a project engineer were barred by the economic loss rule. Exeel responded to the motion, and included in its response copies of portions of the contract between it and the Town of Lovell, as well as copies of portions of the contract between the town and HKM.

[111] At a hearing held on February 13, 2009, the district court converted HKM's motion to dismiss to a Rule 56 motion for summary judgment as permitted by Wyoming Rule of Civil Procedure 12(b)(6), based upon the inclusion of matters beyond the pleadings. The record does not reflect a request from either party for additional time to conduct discovery or to supplement the record to include any additional information which might properly have been considered on a motion for summary judgment.

[112] The district court granted HKM's motion. In its decision letter, the Court held that the economic loss rule articulated in Rissler did in fact bar recovery in this case, which it found to involve similar claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Janet G. Peterson v. Meritain Health, Inc.
2022 WY 54 (Wyoming Supreme Court, 2022)
Sinclair Wyoming Refining v. A & B Builders
989 F.3d 747 (Tenth Circuit, 2021)
Domson, Inc. v. Kadrmas Lee & Jackson, Inc.
2018 SD 67 (South Dakota Supreme Court, 2018)
Timothy Glick v. KF Pecksland LLC
Court of Chancery of Delaware, 2017
City of Casper v. Holloway
2015 WY 93 (Wyoming Supreme Court, 2015)
Stroth v. North Lincoln County Hospital District
2014 WY 81 (Wyoming Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2010 WY 34, 228 P.3d 40, 2010 Wyo. LEXIS 38, 2010 WL 1032010, Counsel Stack Legal Research, https://law.counselstack.com/opinion/excel-construction-inc-v-hkm-engineering-inc-wyo-2010.