Corinthian-WBCM, a Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedMay 19, 2021
DocketASBCA No. 62379
StatusPublished

This text of Corinthian-WBCM, a Joint Venture (Corinthian-WBCM, a Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Corinthian-WBCM, a Joint Venture, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - ) ) Corinthian-WBCM, a Joint Venture ) ASBCA No. 62379 ) Under Contract No. N40080-15-C-0169 )

APPEARANCES FOR THE APPELLANT: Vivian Katsantonis, Esq. Jonathan R. Wright, Esq. Watt, Tieder, Hoffar & Fitzgerald, L.L.P. McLean, VA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Sean P. Morgan, Esq. Devin A. Wolak, Esq. Anthony Hicks, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE HERZFELD

Corinthian-WBCM, a Joint Venture (Corinthian), has appealed the deemed denial of a certified claim submitted to the United States Department of the Navy, Naval Facilities Engineering Command (Navy). The Navy has moved to compel production of certain documents. The Board resolved many of these issues during a March 23, 2021 status conference and in a subsequent March 24, 2021 Order. However, at the request of Corinthian, the Board permitted each party to submit a supplemental brief regarding the Navy’s motion to compel Corinthian to produce the information Corinthian relied on in preparing its proposal. For the reasons stated below, the Board grants the Navy’s request for this information.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

On September 30, 2015, Corinthian and the Navy entered a contract for construction to widen Russell Road at Marine Corps Base Quantico, Virginia (Contract) (R4, tab 2 at 151 (Contract No. N40080-15-C-0169); 1 compl. ¶ 1). The Quantico

1 Citations to the “R4” refer to the Rule 4 file submitted by the Navy on May 1, 2020, and citations to the “app. supp. R4” refer to Corinthian’s Rule 4 supplemental file submitted on June 1, 2020. The Navy numbered pages as “GOV00000151” and Corinthian numbered pages as “JV_0002314” (for example), but we have dropped the prefix and extra zeros. We just cite the numeric page number. road-widening project was phase three of a four-phased project and required Corinthian to include “the required signaling devices with camera equipment to control the direction of traffic and the relocation of existing utilities such as telecom, water, sewer, electric, and natural gas utility lines as necessary” (R4, tab 2 at 158; compl. ¶ 2).

During performance of the Contract, Corinthian submitted requests for equitable adjustment under the Changes and Differing Site Conditions clauses that were incorporated by reference in the Contract (R4, tab 2 at 174-75 (incorporating Federal Acquisition Regulation (FAR) 52.243-4, CHANGES (JUN 2007), and FAR 52.236-2, DIFFERING SITE CONDITIONS (APR 1984)); tabs 17, 19, 21, 23, 34, 36, 38).

The Changes clause permitted the Navy’s contracting officer to

by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract, including changes— (1) In the specifications (including drawings and designs); (2) In the method or manner of performance of the work; (3) In the Government- furnished property or services; or (4) Directing acceleration in the performance of the work.

FAR 52.243-4(a)(1)-(4). The clause also states that:

[a]ny other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; [p]rovided, that the Contractor gives the Contracting Officer written notice stating (1) [t]he date, circumstances, and source of the order and (2) [t]hat the Contractor regards the order as a change order.

FAR 52.243-4(b). If any change under the Changes clause “causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.” FAR 52.243-4(d).

The Differing Site Conditions clause directed Corinthian to provide written notice to the Navy’s contracting officer regarding “(1) [s]ubsurface or latent physical conditions at the site which differ materially from those indicated in this contract, or (2) [u]nknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character

2 provided for in the contract.” FAR 52.236-2(a). The Contract also includes the Site Investigation and Conditions Affecting Work clause, which required Corinthian to take “steps reasonably necessary to ascertain the nature and location of the work, and that it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost” and acknowledge satisfaction “as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract” (R4, tab 2 at 174 (incorporating by reference FAR 52.236-3, Site Investigation and Conditions Affecting the Work (APR 1984))).

This appeal involves seven of Corinthian’s requests for equitable adjustment that invoked, among other clauses, the Changes and Differing Site Conditions clauses. These seven requests for equitable adjustment (REA) make up Corinthian’s certified claim on appeal. (R4, tab 39 at 4379) As pertinent to the motion to compel, we discuss two of these REAs.

For REA No. 3, 2 Corinthian requested an equitable adjustment for additional re-design costs and time to comply with Virginia’s storm water regulations after the Navy’s refusal to allow Corinthian to purchase nutrient credits from the Virginia Department of Environmental Quality (compl. ¶ 38, ex. B; R4, tab 19; app. supp. R4, tab 91, tabs 95-96 at 2518-37). Corinthian’s REA No. 3 stated that Corinthian “based its proposed design upon the purchase of Nutrient Credits” from the Virginia Department of Environmental Quality (compl., ex. B; R4, tab 19 at 334; app. supp. R4, tab 96 at 2518; see also compl. ¶ 38 (“The JV planned its proposed design of the Project’s stormwater management features with the intent to purchase nutrient credits to satisfy the VDEQ stormwater quality requirements for the Project, as permitted by VDEQ, the RFP and the FAR.”)).

For REA No. 4, Corinthian requested an equitable adjustment based on a differing site condition, asserting that the water line at the east end of the project was located and configured differently from the as-built drawings provided by the Navy and the on-site conditions (compl. ¶¶ 44-52, ex. C; R4, tab 21 at 359; app. supp. R4, tab 82). Corinthian contends that this differing site condition resulted in Corinthian expending additional costs and time in adding 88 linear feet to the water line (compl. ¶ 46). In its correspondence with the Navy, Corinthian stated that “all the additional water line work required . . . was never considered in our bid” (R4, tab 21 at 362).

2 Corinthian and the Navy refer to the REAs as REA Nos. 2-8 because that is the numbering system used by Corinthian in its claim and in this appeal. We will continue to refer to each aspect of Corinthian’s claim using the REA number.

3 In the Navy’s first set of requests for production of documents, number 19, the Navy requested that Corinthian “[p]roduce all support [worksheets (in native format), notes, historical data, takeoffs, vendor/subcontractor quotes, pricing guides or other documents] for CCI-WBCM’s final proposed price” (app. opp’n to resp. mot. to compel, ex. 1 at 5 (Corinthian opp’n)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Renda Marine, Inc. v. United States
509 F.3d 1372 (Federal Circuit, 2007)
Afro-Lecon, Inc. v. The United States
820 F.2d 1198 (Federal Circuit, 1987)
Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
Fruin-Colnon Corporation v. The United States
912 F.2d 1426 (Federal Circuit, 1990)
Drone Technologies, Inc. v. Parrot S.A.
838 F.3d 1283 (Federal Circuit, 2016)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Corinthian-WBCM, a Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/corinthian-wbcm-a-joint-venture-asbca-2021.