Kamaludin Slyman CSC

CourtArmed Services Board of Contract Appeals
DecidedApril 29, 2021
DocketASBCA No. 62006, 62007, 62008
StatusPublished

This text of Kamaludin Slyman CSC (Kamaludin Slyman CSC) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kamaludin Slyman CSC, (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Kamaludin Slyman CSC ) ASBCA Nos. 62006, 62007, 62008 ) Under Contract Nos. H92237-12-C-0089 ) H92237-12-C-0131 ) H92237-12-C-0322 )

APPEARANCES FOR THE APPELLANT: Bryant S. Banes, Esq. Sean D. Forbes, Esq. Neel, Hooper & Banes, P.C. Houston, TX

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Christopher M. Judge-Hilborn, Esq. Kyle E. Gilbertson, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE PROUTY

These three consolidated appeals center upon appellant Kamaludin Slyman CSC (Kamaludin)’s leasing heavy construction equipment to the United States Army (Army) for use in Afghanistan via three separate contracts. It turned out that the Army needed to use the equipment at different locations than first anticipated, and for longer periods of time than the contracts permitted. The parties made some efforts to secure compensation to Kamaludin for the change in contract terms, but this never happened. In any event, about four or five months after this extended performance was completed, Kamaludin submitted three “letters of claim” to the Army seeking payment as a consequence. The amounts sought were $155,500; $55,000 and $18,183. The letters were not “certified” as that term is used in the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109, and a later effort (almost six years after the original letters) was made by Kamaludin to retroactively certify them via email. 1 Shortly thereafter, Kamaludin submitted appeals to the Board of the deemed denials of its claim letters.

The government responded to the appeals by filing a motion to dismiss Appeal No. 62006 for lack of signature on its certification and to dismiss Appeal No. 62007 for

1 Only the $155,500 claim required certification, since the threshold for certification under the CDA is claims exceeding $100,000. 41 U.S.C. § 7103(b).

1 failure to state a claim. 2 Since the signature issue required consideration by the Board’s Senior Deciding Group, we considered it apart from the failure to state a claim contention and issued a decision revisiting our view of what constituted a “signature” for purposes of claims certification and holding that Kamaludin had submitted a properly certified claim in Appeal No. 62006. See Kamaludin Slyman CSC, ASBCA Nos. 62006 et al., 20-1 BCA ¶ 37,694.

After the Senior Deciding Group issued its decision, and before we decided the motion to dismiss for Appeal No. 62007, the Army filed a motion for summary judgment in Appeal No. 62006, arguing that, even if the claim were properly certified, it was brought outside of the CDA’s six-year statute of limitations. See gov’t MSJ. In addition to responding directly to the Army’s motion, Kamaludin argues that it should be permitted discovery before our deciding it. See app. MSJ opp.

Here, we decide both the Army’s motion to dismiss and its motion for summary judgment.

STATEMENT OF UNDISPUTED FACTS 3

I. The Contracts

The Army awarded three contracts to Kamaludin, a small Afghan company, in late 2011/early 2012. The first contract, Contract No. H92237-11-C-0322 (the Deh Bouchey contract), was executed by the parties on September 10, 2011 (R4, tab 2 at 1). It was for the provision of specified heavy construction equipment to a location in Afghanistan, Village Support Platform (VSP) Deh Bouchey, where it would be used for a three-month period, ending on December 14, 2011 (R4, tab 2 at 5).

Contract No. H92237-12-C-0089 was executed on December 25, 2011, and was for the provision of numerous pieces of heavy construction equipment at VSP LAM in

2 We refer to the government’s submissions with respect to the motion to dismiss as “gov’t MTD” and “gov’t MTD reply.” Kamaludin’s opposition to the motion to dismiss is “app. MTD opp.” The government’s motion for summary judgment will be referred to as “gov’t MSJ” along with “gov’t MSJ reply” for its reply brief. Kamaludin’s opposition and sur-reply will be “app. MSJ opp.” and “app. MSJ sur- reply,” respectively. 3 As will be discussed in more detail below, a motion to dismiss for failure to state a

claim is decided based upon the terms of the complaint and documents incorporated into it without resort to an outside record, while a motion for summary judgment is based upon undisputed material facts and often rests upon evidence beyond the complaint and associated documents. For our purposes today, however, we may address the two together.

2 Afghanistan through June 30, 2012 (R4, tab 14 at 1, 4-5). By bilateral change order, executed by the parties on January 16, 2012, the location of the equipment was changed from VSP LAM to Fire Base (FB) Maholic (R4, tab 15), thus, we will refer to it as “the Maholic Contract.”

Contract No. H92237-12-C-0131 (the Chenar contract) was executed on March 17, 2012, and was for the provision of a water truck and a dump truck for three months (ending June 15, 2012) at VSP Chenar (R4, tab 10 at 1, 3). What is not clear on the face of the VSP Chenar contract is that it actually was an extension, of sorts, of the Deh Bouchey contract: the water truck and dump truck in the Chenar contract had been originally provided by Kamaludin under the Deh Bouchey contract, but the government moved them to VSP Chenar without Kamaludin’s permission and kept them there longer than the terms of the Deh Bouchey contract. The Chenar contract was essentially a back- dated way for the parties to remedy this out-of-scope action in the earlier contract (R4, tab 19 at 2) 4.

The three contracts all envisioned the equipment being used at the place of performance and appear to have implied that the equipment would be retrieved by Kamaludin from the Army at the close of performance at the place of performance: the Deh Bouchey contract required the equipment to be delivered by Kamaludin to VSP Deh Bouchey and inspected there and that performance of the contract would be there (R4, tab 2 at 5). Also, the contract specified that personal property of Kamaludin’s left at the contract site after completion of the contract would be sold or otherwise disposed of by the government in accordance with 10 U.S.C. § 2575 (R4, tab 2 at 30).

The Chenar contract contained similar language to the De Bouchey contract about delivery and inspection of the equipment at VSP Chenar along with language that VSP Chenar was the location of performance (R4, tab 10 at 3). The Chenar contract also included similar language regarding the disposal of personal property after contract completion being accomplished pursuant to 10 U.S.C. § 2575 (R4, tab 10 at 22).

The Maholic contract, as modified, contained similar provisions to the Deh Bouchey and Chenar contracts regarding delivery and inspection of the equipment (see R4 tab 15 at 3) and disposal of personal property after the conclusion of performance in accordance with 10 U.S.C. § 2575 (R4, tab 14 at 29).

All three contracts incorporated by reference the standard Disputes clause provided by Federal Acquisition Regulation (FAR) 52.233-1 (see R4, tab 2 at 8 (Deh Bouchey); tab 10 at 5 (which incorporates FAR 52.212-4 for the Chenar contract, which, in turn, incorporates the Disputes clause); tab 14 at 7-8 (Maholic)). Inter alia, this clause

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Franconia Associates v. United States
536 U.S. 129 (Supreme Court, 2002)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Arctic Slope Native Association, Ltd. v. Sebelius
583 F.3d 785 (Federal Circuit, 2009)
Cary v. United States
552 F.3d 1373 (Federal Circuit, 2009)
Serdarevic v. Advanced Medical Optics, Inc.
532 F.3d 1352 (Federal Circuit, 2008)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Doe v. Busby
661 F.3d 1001 (Ninth Circuit, 2011)
Scott Timber Company v. United States
333 F.3d 1358 (Federal Circuit, 2003)
Menominee Indian Tribe of Wis. v. United States
577 U.S. 250 (Supreme Court, 2016)
Kellogg Brown & Root Services, Inc. v. Murphy
823 F.3d 622 (Federal Circuit, 2016)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
A & D Auto Sales, Inc. v. United States
748 F.3d 1142 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Kamaludin Slyman CSC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kamaludin-slyman-csc-asbca-2021.