Kellogg Brown & Root Services, Inc. v. Murphy

823 F.3d 622, 2016 U.S. App. LEXIS 9044, 2016 WL 2893218
CourtCourt of Appeals for the Federal Circuit
DecidedMay 18, 2016
Docket2015-1148
StatusPublished
Cited by27 cases

This text of 823 F.3d 622 (Kellogg Brown & Root Services, Inc. v. Murphy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kellogg Brown & Root Services, Inc. v. Murphy, 823 F.3d 622, 2016 U.S. App. LEXIS 9044, 2016 WL 2893218 (Fed. Cir. 2016).

Opinion

NEWMAN, Circuit Judge.

The only issue on this appeal is whether the six-year statute of limitations of the Contract Disputes Act had run for this claim. The claim was filed by Kellogg Brown & Root Services, Inc. (KBR) for costs incurred by KBR for work done by its subcontractor in performing a contract with the Army to construct dining facilities and to provide meal and related services for troops in Iraq. On the Army’s motion, the Armed Services Board of Contract Appeals (ASBCA or Board) dismissed KBR’s claim for lack of subject matter jurisdiction, holding that the period of limitations had run before KBR filed this claim. 1 The *624 claim was filed on May 2, 2012; thus, the critical date of accrual for limitations purposes is May 2, 2006.

On review of the premises and the applicable law, we conclude that the Board erred in law and on the application of law to the undisputed facts. We conclude that the KBR claim had not accrued, for limitation purposes, before May 2, 2006. The Board’s dismissal is reversed; we remand for determination of the merits of the claim.

BACKGROUND

In summary: on December 14, 2001, the Army and KBR entered into a cost-plus-award-fee contract under the Logistics Civil Augmentation Program. KBR subcontracted with a joint venture between The Kuwait Company for Process Plant Construction & Contracting K.S.C. and Morris Corporation (AUST) PTY Ltd. (KCPC/Morris), to implement certain work release orders for construction of dining facilities and provision of food services at two locations in Iraq. On July 31, 2003, KBR terminated the subcontract for “fail[ure] to bring conditions to full contract performance as of 31 July, 2003,” as required by the subcontract. Army Br. at 4. KCPC/Morris disputed the termination, and, at KBR’s request, also continued performance until transition to a new subcontractor on September 12, 2003.,

The ensuing determination of reimbursable costs and termination conditions included a suit filed in 2004 by KCPC/Morris against KBR in the United States District Court for the Eastern District of Virginia, in which KCPC/Morris stated (and KBR disputed) that an oral settlement had been reached and sought its enforcement. On January 24, 2005, KBR and KCPC/Morris entered into a written agreement, described by the Board as follows:

[T]he parties divided KCPC/Morris’ costs into two groups: (a) the “Settlement Amount” of $17,400,000; and (b) KCPC/Morris’ costs incurred and profit related to its performance under the Master Agreement and the termination of the Work Releases ... including overhead, G & A, profit and certain costs incurred in preparing requests for payment to the U.S. Government.

Board Op. at 3. This agreement also converted the default termination into a termination for convenience. Id.

The group (a) “Settlement Amount” of $17,400,000 was paid, and is not at issue. This CD A action concerns only, the group (b) component. For the group (b) costs, the agreement stated that KBR and KCPC/Morris would cooperate “to prepare a well-supported invoice or invoices to the U.S. Government,” the agreement also stating that “[i]n no event shall KBR submit an invoice to the Government for any portion of the JOINT VENTURE’S costs that KBR does not believe is supportable.” 2005 Settlement Agreement at 4.

On August 26, 2006, KCPC/Morris submitted to KBR a certified claim for the “outstanding payments, costs and lost profit associated with the termination for convenience by [KBR] of the [ ] contract.” Army Br. at 5. On November 3, 2006, KBR forwarded KCPC/Morris’ claim to the Army, with a letter stating that KBR “does not certify or comment to the validity of these costs and does not have any other supporting documentation for validation.” Letter from Senior Manager, Contracts, KBR, to Chief, LOGCAP Branch, Department of the Army (Nov. 3, 2006) (“KBR Letter”).

The Army responded to KBR on May 30, 2007, stating that “it is KBR’s management responsibility to negotiate or discuss claims with its subcontractors and the Army does not comment in advance as *625 to whether a claim or certain costs are appropriate. Therefore, the Army will not meet with, or correspond directly with KBR’s subcontractors.” See Board Op. at 5 (quoting Army Sustainment Command Letter to KBR (May 30, 2007)). The Army refused to consider the submitted information, and directed KBR to “settle a claim by its sub with the sub, then bill the government.” E-mail from Chief, Contracting Division, Logistics Civil Augmentation Program, Army Sustainment Command, to Senior Manager, Contracts, Kellogg Brown and Root, “RE: Request for additional information regarding draft settlement” (July 19, 2007) (“Army Email”).

On October 10, 2007, KBR “sponsored” the KCPC/Morris claim, followed by certification of the claim by letter dated January 10, 2008. On September 8, 2010, KBR withdrew the claim, stating that “[u]pon further review of the data provided by KCPC/Morris, KBR has determined that this constitutes a business dispute between KBR and KCPC/Morris and should be resolved in accordance with KBR’s subcontract with KCPC/Morris.” Letter from Senior Manager, Contracts, Kellogg Brown and Root, to Army Contracting Command, “Subject: DAAA09-02-D-0007: Subcontractor Claim KCPC/Morris.” The record before us does not provide details, but KBR states that the asserted costs were eventually reduced by about $2.1 million. KBR Br. 20.

On August 4, 2011, KCPC/Morris filed suit against KBR in the United States District Court for the Eastern District of Virginia, stating in its complaint that “KBR allowed [KCPC/Morris’ claim] to languish with the Government, ... and then inexplicably withdrew the entire claim in September 2010 without consulting KCPC/Morris.... KBR has failed to submit and pursue the portions of the claim it concedes are well supported.... ” Compl. at 2, Kuwait Co. for Process Plant Const. & Contr. v. Kellogg, Brown & Root Servs., Inc., 1:11-cv-824-CMH/TRJ, (E.D.Va. August 4, 2011). This suit was withdrawn after KBR and KCPC/Morris entered into an agreement dated February 17, 2012, for payment to KCPC/Morris of $10,464,493, which the Board summarized as for “construction costs, equipment, expenses such as medical care and travel, meals served, overhead and G & A, profit, and termination settlement costs.” Board Op. at 4-5. On May 2, 2012, KBR filed a certified claim with the Army for this amount. The contracting officer did not act on the claim, thereby placing it in “deemed denied” status. KBR then appealed to the Board.

The Army moved to dismiss, stating that the six-year CDA statute of limitations had run. The Board granted the motion, finding alternative dates for the accrual of the claim, both dates before the critical limitations date of May 2, 2006. The Board found, first, that the claim accrued on September 12, 2003, the date when KCPC/Morris ended its work under the subcontract; and alternatively on January 24, 2005, when KBR and KCPC/Morris agreed to cooperate to present an invoice to the Army for costs above the “Settlement Amount” of $17.4 million. The Board held that there was no basis for equitable tolling of the limitations period. Board Op.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Platinum Services, Inc.
Armed Services Board of Contract Appeals, 2024
Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
Kandahar Mahali Transit & Forwarding LTD.
Armed Services Board of Contract Appeals, 2024
Restoration Specialists, LLC
Armed Services Board of Contract Appeals, 2023
American Technical Services, Inc
Armed Services Board of Contract Appeals, 2023
Patricia I. Romero, Inc. d/b/a Pacific West Builders
Armed Services Board of Contract Appeals, 2023
Lockheed Martin Aeronautics Company
Armed Services Board of Contract Appeals, 2022
Afghan Premier Logistics
Armed Services Board of Contract Appeals, 2022
Strategic Technology Institute, Inc.
Armed Services Board of Contract Appeals, 2022
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)
Thomas J. Davis, Inc.
Armed Services Board of Contract Appeals, 2021
Kamaludin Slyman CSC
Armed Services Board of Contract Appeals, 2021
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
Reed International, Inc.
Armed Services Board of Contract Appeals, 2020
Ford Lumber & Building Supply, Inc.
Armed Services Board of Contract Appeals, 2019

Cite This Page — Counsel Stack

Bluebook (online)
823 F.3d 622, 2016 U.S. App. LEXIS 9044, 2016 WL 2893218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kellogg-brown-root-services-inc-v-murphy-cafc-2016.