Thomas J. Davis, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 1, 2021
DocketASBCA No. 62634
StatusPublished

This text of Thomas J. Davis, Inc. (Thomas J. Davis, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas J. Davis, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Thomas J. Davis, Inc. ) ASBCA No. 62634 ) Under Contract No. W912UM-12-C-0029 )

APPEARANCE FOR THE APPELLANT: Yong Eui Song, Esq. Central IP & Law Seoul, Korea

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Robert M. Sundberg, Esq. SoCheung Lee, Esq. Steven H. Finch, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Far East Seoul, Korea

OPINION BY ADMINISTRATIVE JUDGE PROUTY

Appellant, Thomas J. Davis, Inc. (TJD), is challenging here a contracting officer’s final decision (COFD) dated June 3, 2020, seeking $1,097,808.15 for its allegedly defective design of an aircraft corrosion control facility on Osan Air Base (AB) in the Republic of Korea, pursuant to the above-captioned contract (the contract). Today, we address TJD’s motion for summary judgment, which argues that the government was well aware of the qualities of the design which it now considers deficient as early as 2012, thus precluding the filing of the government’s claim in 2019, which would be outside of the six-year statute of limitations imposed by the Contract Disputes Act (CDA). As explained below, we deny TJD’s motion because we find there is a triable dispute of fact regarding when the government’s claim accrued.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION 1

I. Relevant Contract Provisions

The government awarded the contract to TJD on April 10, 2012 (R4, tab 2 at 1). As alluded to above, the contract was for the provision of the design of a specified

1 We note from the outset that TJD’s motion for summary judgment (app. mot.) is not compliant with Board Rule 7(c)(2), requiring its factual assertions to be supported corrosion control facility 2 on Osan AB, in accordance with the scope of work (SOW) included in the contract and with pre-design meeting minutes from January 2012. For these services, TJD was to be paid $858,940. (R4, tab 2 at 3)

Among many other dictates, the SOW elaborated that the corrosion control facility would be a:

. . . two bay facility including Painting Bay, and Washing Bay and a separate room for the painting booth and plastic media blast system. No secure rooms will be needed. Air Force Corrosion Control Facility reference guide Nov 2010 (PACAF LGFIPG 4.3) shall be used for the design of this project.

(R4, tab 2 at 5)

The SOW included a schedule of when different iterations of the design would be due from TJD. The iterations were: 10% submittal, which was the proposed floor and site plans; the 30% submittal, which was the “early preliminary design”; the 90% submittal, which was the “final” design; the 95% submittal, which was the corrected final design; and the 100% submittal, which included contract documents. (R4, tab 2 at 6) The 10%, 30%, and 90% submittals were subject to On Board Review (OBR) meetings (R4, tab 2 at 8). Their due dates were contingent upon the notice to proceed and the completion of the OBRs for prior phases (e.g., the 95% submittal was due 21 days after the OBR for the 90% submittal) (R4, tab 2 at 9).

The contract incorporated by reference, the standard Federal Acquisition Regulation (FAR) Disputes clause, 52-233-1 (R4, tab 2 at 53).

by citation to the record or additional evidence. Many of the factual assertions in TJD’s motion are supported with no citation, whatsoever, or have only a vague reference to a document without explaining how that reference supports the allegations made. We strongly considered rejecting TJD’s motion on this basis alone. Nevertheless, in the interest of more expeditiously resolving this dispute, we decided it is best to address the issues raised by the motion and do the best we could to determine which assertions were supported by facts that we could find in the record. Needless to say, this is a suboptimal use of our time and if future filings from TJD follow the model of this one, it should anticipate their rejection by the Board. 2 A “corrosion control facility” in this context is basically a building to clean aircraft and

to sand and re-paint them or their parts (see R4, tab 2 at 5).

2 The SOW explicitly stated that the review of documents by the contracting officer (CO) or his or her representative did not relieve TJD of its responsibility to check for errors or to correct them if discovered at a later date (R4, tab 2 at 29). The contract also incorporated by reference FAR 52.236-23, RESPONSIBILITY OF THE ARCHITECT-ENGINEER CONTRACTOR (APR 1984) and FAR 52.236-24, WORK OVERSIGHT IN ARCHITECT-ENGINEER CONTRACTS (APR 1984) (R4, tab 2 at 54). The first of these, FAR 52.236-23, specified that the contractor bore responsibility for the “professional quality [and] technical accuracy” of the design and that the government’s review and acceptance of designs did not constitute a waiver of the government’s rights under the contract. The second, FAR 52.236-24, stated that the work performed by the contractor was subject to the “general oversight, supervision, direction, control, and approval of the Contracting Officer.”

II. Contract Performance

A. TJD’s 30% Submittal Designed the Restoration Bay to be Suitable For Painting

TJD asserts in its motion that its 30% design submittal included “sanding/grinding and painting of aircraft” (app. mot. at 2). Indeed, our review of that design, submitted on June 5, 2012, finds that the floor plan for Sector “A” (also referred to as the “Restoration Bay”) includes a paint booth, a paint mixing room, and a paint/solvent storage room in design sheet AE104 (see app. mot., encl. A at 2). 3 Similar depictions may be found in the 30% design sheet for the Sector A Heating, Ventilation and Air Conditioning (HVAC) plan, MH401 (see id. at 1).

B. TJD (Maybe?) Decides it Doesn’t Need to Provide for Painting

According to TJD’s motion, shortly after it submitted its 30% design, unspecified government personnel “instructed” it to “modify the subsequent designs which did not include painting of aircrafts in the Restoration Bay” (app. mot. at 2). In the context of its motion and its appeal, we take this sentence to mean that TJD was instructed to modify its design to remove the ability to paint aircraft in the Restoration Bay (that is not exactly what TJD wrote, but a literal reading of that sentence would not make sense in the context of this motion). But TJD provides no evidence for this striking claim. None, besides the assertions of counsel which, of course, are not evidence.

To the contrary, the government has provided evidence both directly and indirectly refuting it. With respect to direct evidence, the government submitted the affidavits of Mr. Victor Diaz, who was involved in 2012 meetings with TJD representing the Air Force

3 TJD attached multiple “enclosures” (which are, for all intents and purposes, evidentiary exhibits) to its motions. We refer to them as “app. mot. encl.__.”

3 (see gov’t opp’n, ex. B), and Mr. Kwang Kyu Choe, an Army Corps of Engineers employee who was the CO’s representative (COR) for the contract (see gov’t opp’n, ex. A). Both gentlemen were adamant that the government never withdrew the requirement that the Restoration Bay be set up to allow for painting (see gov’t opp’n, ex. A, ex. B).

Additional evidence refuting TJD’s allegation that the government waived the painting requirement is found in multiple places in the record. One compellingly direct location is in the November 6, 2012 minutes of the November 1, 2012 ORB meeting held after the 90% design submittal was submitted (see app. mot., encl. D).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Diebold, Inc.
369 U.S. 654 (Supreme Court, 1962)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)
Kellogg Brown & Root Services, Inc. v. Murphy
823 F.3d 622 (Federal Circuit, 2016)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
Thomas J. Davis, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-j-davis-inc-asbca-2021.