Patricia I. Romero, Inc. d/b/a Pacific West Builders

CourtArmed Services Board of Contract Appeals
DecidedMay 12, 2023
Docket63093
StatusPublished

This text of Patricia I. Romero, Inc. d/b/a Pacific West Builders (Patricia I. Romero, Inc. d/b/a Pacific West Builders) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Patricia I. Romero, Inc. d/b/a Pacific West Builders, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Patricia I. Romero, Inc. d/b/a Pacific West ) ASBCA No. 63093 Builders ) ) Under Contract No. N62473-08-D-8655 )

APPEARANCE FOR THE APPELLANT: David A. Rose, Esq. Rose Consulting Law Firm Valdosta, GA

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Joshua S. Kauke, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE MCLISH ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

This appeal involves disputes arising under a task order issued by the Naval Facilities Engineering Systems Command Southwest (NAVFAC or the government) to Appellant Patricia I. Romero Inc. (d/b/a Pacific West Builders) (PWB) for repair work at Buckley Air Force Base in Aurora, Colorado. PWB asserts that NAVFAC required extra work without due compensation or time extensions, improperly withheld superior knowledge, and caused numerous delays that resulted in extra costs to PWB. PWB also seeks interest under the Prompt Payment Act.

The government moves for summary judgment on each of PWB’s claims on the grounds that (1) the claims are barred by the applicable statute of limitations, (2) certain claims are barred by accord and satisfaction, and (3) the claim for interest is barred by the Prompt Payment Act. We dismiss some of the claims for lack of jurisdiction and grant summary judgment in the government’s favor except as to two of the remaining claims.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

I. The Contract

The contract at issue is a task order issued under an indefinite-delivery, indefinite-quantity, multiple award construction contract. The underlying contract is Contract No. N62473-08-D-8655, awarded by the NAVFAC to PWB on September 22, 2008. (R4, tab 1 at 1) 1

The task order at issue was awarded on or about September 20, 2011, when NAVFAC issued PWB Task Order No. 0003 for the Denver NOSC Repair Project at Buckley Air Force Base in Aurora, Colorado in the amount of $3,431,294.00 (R4, tab 4 at 208-09). The original contract completion date was October 8, 2012, and the task order included a liquidated damages clause (R4, tab 4 at 225).

Under the task order, PWB was to make renovations and repairs to existing buildings referred to as Buildings 1301, 1302 and 1304 and associated areas (R4, tab 2 at 118).

II. Contract Modifications

During performance, eight written modifications were made to the Contract. Seven of them were made bilaterally by both of the parties (Modification Nos. 1-3, 5-8) (R4, tabs 5-7, 9-12). One the government issued unilaterally (Modification No. 4) (R4, tab 8).

After performance was completed, on or about November 9, 2015, the government unilaterally issued Modification No. 9, which assessed liquidated damages against PWB for alleged late completion of the work (R4, tab 13). Modification No. 10, discussed below, was issued on September 28, 2021. It, among other things, rescinded the liquidated damages assessed in Modification No. 9. (R4, tab 14)

III. PWB’s Disagreement with CPARS Evaluation

Meanwhile, on or about September 24, 2015, NAVFAC issued a performance evaluation under the Contractor Performance Assessment Reporting System (CPARS) regarding PWB’s performance of the contract. The CPARS evaluation apparently criticized PWB’s performance of the contract in several respects. 2

PWB submitted a letter to the Contracting Officer dated December 15, 2015, taking issue with the negative aspects of the CPARS evaluation (R4, tab 18 at 404-28).

1 The government paginated the Rule 4 files with a prefix and several zeroes before each page number, e.g., “GOV000001.” For ease of reference, we cite only the page numbers without the prefix and leading zeroes. 2 The CPARS evaluation itself is not in the Rule 4 file or otherwise included in the parties’ submissions. Our description of the CPARS evaluation is thus based on references to it in documents that are in the record, primarily PWB’s December 15, 2015, letter to the contracting officer disputing the accuracy of the evaluation (R4, tab 18 at 404-28). 2 Attached to the letter were 53 exhibits (id. at 429-606). The December 15, 2015, letter alluded to PWB’s intent to submit a claim challenging the CPARS evaluation, as well as the assessment of liquidated damages, and indicated PWB would seek monetary relief for various acts and omissions by NAVFAC during contract performance (id. at 404-28).

IV. PWB’s Certified Claim, Contracting Officer’s Final Decision, and Appeal

As forecast in the December 15, 2015, letter, PWB eventually did submit a certified claim to the contracting officer, but not until March 23, 2021 (R4, tabs 17-18). 3 The claim attached and “incorporated . . . by reference for all purposes” the December 15, 2015, letter from PWB to the Contracting Officer (R4, tab 17 at 396)

PWB’s claim first contended that the CPARS evaluation was unfair and “substantially incorrect” and should be replaced with a positive or, at a minimum, a neutral rating (R4, tab 17 at 396, 398). Second, in addition to the CPARS claim, PWB alleged that “PWB has experienced actual damages and seeks the removal of liquidated damages and the final payment of the funds due under the contract of $366,193.48, which includes the additional amount of Modification 08 . . .” (id. at 398). Modification No. 8 had added a requirement to install a glycol feeder system and add glycol solution to the air handler system (R4, tab 12).

Third, the claim stated that “PWB also seeks an additional $324,923.72 for costs due to additional work and delay (See Exhibit 3)” (R4, tab 17 at 398). Exhibit 3 to the claim, entitled “PWB Additional Costs Breakdown,” contained PWB’s calculation of its claimed additional costs (R4, tab 18 at 611). The claim letter alleged that NAVFAC caused delays and extra costs in the way it reviewed and commented on design documents for the SCIF 4; by failing to advise PWB of security requirements in the SCIF; by failing to disclose that only one source could perform work on the controls system; and by failing to adequately maintain the existing hot water supply system, allegedly causing failure of two new air handling units (R4, tab 17 at 397). The December 15, 2015, letter that PWB incorporated into its claim had raised those same contentions and also alleged various other instances of delay and uncompensated costs for which PWB claimed the government was responsible (R4, tab 18 at 404-28), as summarized here:

3 The Government suggests that the claim may not have been fully submitted until March 30, 2021, when the contracting officer received the exhibits referenced in the March 23, 2021, submission. We assume for purposes of this motion that the claim was submitted on the earlier date. 4 A SCIF is a sensitive compartmented information facility. 3 Event Giving Rise to Claim Date of Alleged Event 1. PWB was directed not to begin December 17, 2012-February 4, 2013 (id. and work in Enclave on schedule 571-72) (R4, tab 18 at 423) 2. PWB denied access to begin December 13, 2012– January 3, 2013 (id. and flooring work in Rooms 1-208, 573-74) 1-212, 1-216 and 3-204 (id. at 423) 3. Work in Room 3-109 stopped January 23, 2013-May 31, 2013 (id. and 575) for Government to undertake mold abatement (id. at 423) 4. Subcontractors denied bases March 13-25, 2013 (id. and 577) access because sponsor’s authorization expired (id. at 423) 5. Renewal base passes denied for April 1-16, 2013 (id. and 578-80) drywall crew for unknown reason (id. at 424) 6. Site work stopped to March 5-11, 2013 (id.) accommodate an advancement exam (id. at 424) 7. Delay waiting for Government October 2013 (id. and 581-82) to clear closet where CRAC units to be located and to perform work relating to door security locks (id.) 8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Irwin v. Department of Veterans Affairs
498 U.S. 89 (Supreme Court, 1991)
Fallini v. United States
56 F.3d 1378 (Federal Circuit, 1995)
Gabriel J. Martinez v. United States
333 F.3d 1295 (Federal Circuit, 2003)
Floorpro, Inc. v. United States
680 F.3d 1377 (Federal Circuit, 2012)
Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)
Menominee Indian Tribe of Wis. v. United States
577 U.S. 250 (Supreme Court, 2016)
Kellogg Brown & Root Services, Inc. v. Murphy
823 F.3d 622 (Federal Circuit, 2016)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)
The Tolliver Group, Inc. v. United States
20 F.4th 771 (Federal Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Patricia I. Romero, Inc. d/b/a Pacific West Builders, Counsel Stack Legal Research, https://law.counselstack.com/opinion/patricia-i-romero-inc-dba-pacific-west-builders-asbca-2023.