PARSONS GLOBAL EX REL. ODELL INTERN. v. McHugh

677 F.3d 1166, 2012 WL 1372149, 2012 U.S. App. LEXIS 8062
CourtCourt of Appeals for the Federal Circuit
DecidedApril 20, 2012
Docket2011-1201
StatusPublished
Cited by26 cases

This text of 677 F.3d 1166 (PARSONS GLOBAL EX REL. ODELL INTERN. v. McHugh) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PARSONS GLOBAL EX REL. ODELL INTERN. v. McHugh, 677 F.3d 1166, 2012 WL 1372149, 2012 U.S. App. LEXIS 8062 (Fed. Cir. 2012).

Opinions

Opinion for the court filed by Circuit Judge PROST.

Dissenting opinion filed by Circuit Judge NEWMAN.

PROST, Circuit Judge.

This is an appeal from the Armed Services Board of Contract Appeals (“Board”) regarding whether the Board has jurisdiction over Parsons Global Services, Inc.’s (“Parsons”) sponsored claim on behalf of subcontractor Odell International, Inc. (“Odell”). The Board held that Parsons’s request for payment was “routine” and thus, under 48 C.F.R. (FAR) § 2.101, needed to be in dispute to constitute a claim over which the Board had jurisdiction. Because we agree that the Board did not have jurisdiction over Parsons’s request for payment, we affirm.

Background

In March 2004, the Army awarded Parsons contract no. W914NS-04-D-006 (“the prime contract”), an indefinite-delivery-indefinite-quantity contract for design-build work in Iraq. The cost reimbursement contract incorporated various Federal Acquisition Regulations (“FAR”), including regulations relating to reimbursement of subcontractor costs during the contract and after termination for convenience. Subsequently, Parsons entered into a basic ordering agreement (“BOA agreement” or “subcontract”) with Odell, effective as of March 25, 2004. The subcontract required Odell to construct health care facilities and deliver medical equipment in Iraq pursuant to the prime contract. Initially, the contract did not specify an overhead rate.

In May 2004, prime contract Task Order 0004 was issued for the construction, restoration, rebuilding, and development of public projects in Iraq, and in October 2004, Task Orders 0011 and 0012 issued requiring the construction of various health care facilities in Iraq. Parsons awarded Odell subcontract task orders to support Task Orders 0004, 0011, and 0012.

On October 27, 2004, Parsons and Odell amended their subcontract, effective March 26, 2004, to reflect the parties’ agreement that Odell was entitled to compensation for its overhead and general and administrative (“G & A”) costs. Specifically, the amendment added paragraph 1.0C(a), which states that “[a] mark-up of I.75% will be added to Subcontractor’s direct labor rates to cover G & A, [overhead] and other indirect costs.... ” Supplemental App. 11. In accompanying remarks, the parties noted that this provision was inadvertently omitted from the original subcontract. The parties again amended the subcontract on January 19, 2005, effective March 26, 2004, to better clarify paragraph l.OC(a) to the subcontract. The newly amended language read “[a] markup of 1.75 (175%) will be added to [Odell’s] direct labor rates to cover G & A, [overhead] and some other [in]direct costs.” J.A. 3 (first emphasis added) (second and fourth alterations in original). Despite these amendments, Odell continued to invoice its costs to Parsons at a 75% markup.

On February 28, 2006, the Defense Contract Audit Agency (“DCAA”) determined that Odell’s provisional indirect cost rate for 2005 was 187% and informed Odell that it had been billing Parsons using the incorrect 75% mark-up. On March 3, 2006, the Army terminated for convenience Task Orders 0004, 0011, and 0012. Four days later, on March 7, Odell submitted a memorandum to Parsons with an attached invoice for $2,113,864.99 — the difference between the 75% mark-up Odell had billed Parsons and the 187% rate that DCAA [1169]*1169determined was Odell’s 2005 provisional indirect cost rate. Parsons refused to pay the invoice, explaining that the 187% was a provisional indirect rate and “its time and materials BOA with Odell did not entitle Odell to use a mark-up of 187 percent.” Supplemental App. 12.

The government, through a modification to the prime contract, assigned termination contracting officer (“TCO”) authority to the Defense Contract Management Agency. In July 2007, Parsons submitted a termination settlement proposal for each terminated task order to the TCO, none of which mentioned the additional costs Odell sought or any mark-up rate issues between Parsons and Odell. Pursuant to settlement of the prime contract, the TCO requested that the DCAA audit Parsons’s billed costs for Task Order 0011 of the prime contract, including Odell’s costs. The DCAA’s June 2008 report discussed, inter alia, the appropriate mark-up for labor costs incurred under the subcontract. The DCAA clarified that the 187% markup discussed in its initial audit “would not apply to this subcontract as the 175% rate is a fixed rate specified in the subcontract agreement.” J.A. 208.

On July 8, 2008, Odell submitted a revised invoice totaling $2,444,976 for the claimed difference between the labor costs previously billed at 75% and the costs billed at the revised mark-up of 175%.1 In August 2008, Parsons submitted three Payment Approval Requests reflecting the costs submitted by Odell to the TCO. The TCO orally informed Parsons that it would not settle directly with Odell pursuant to FAR 49.108-8 because it was not in the best interest of the government. On December 22, 2008, Parsons submitted a sponsored “Certified Claim for Payment” under the Contract Disputes Act of 1978 (“CDA”) on behalf of Odell to the Procurement Contracting Officer (“PCO”).2 The claim was accompanied by a CDA certification and sought reimbursement for $2,585,642.71 for costs incurred under the subcontract for Task Orders 004, 0011, and 0012.3 On January 3, 2009, the PCO denied the claim and Parsons filed an appeal to the Board.

On appeal, the government moved to dismiss for a lack of jurisdiction, arguing that Parsons’s “routine” requests for payment did not amount to a claim under the CDA. Parsons countered that because its requests for payment occurred two years after the termination of the task orders and thus could not be subject to routine invoicing and termination procedures, the request was non-routine and sufficient in itself to constitute a claim. The Board agreed with the government that Parsons had failed to submit a valid sponsored claim and dismissed Parsons’s appeal for lack of jurisdiction. Parsons Global Sews., Inc., ASBCA No. 56731, 11-1 BCA ¶ 34,632. The Board determined that the request for Odell’s costs incurred under the subcontract was “routine”; as such, it did not become a claim under the CDA [1170]*1170until it was disputed by the government or the government unreasonably delayed payment. Id. Because its routine request was not in dispute, the Board held that Parsons had not submitted a claim under the CDA for which it had jurisdiction. Id. The Board also questioned whether Parsons, without conducting its own audit of the subcontractor costs, was actually liable to Odell for the costs because of statements that it will pay Odell only to the extent the government pays it. Id.

This appeal followed. We have jurisdiction to review the Board’s final decision under 28 U.S.C. § 1295(a)(10).

Discussion

Pursuant to 41 U.S.C. § 7107(b)(1), we review decisions by the Board on questions of law de novo. Thus, we review the Board’s determination of jurisdiction under the CDA and its interpretation of the applicable FAR provisions de novo. Sys. Dev. Corp. v. McHugh, 658 F.3d 1341, 1344 (Fed.Cir.2011).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Samho Enterprise
Armed Services Board of Contract Appeals, 2025
Platinum Services, Inc.
Armed Services Board of Contract Appeals, 2024
Case Healthcare Solutions, Inc. d/b/a Case HCS of Reston, Virginia
Armed Services Board of Contract Appeals, 2024
Kandahar Mahali Transit & Forwarding LTD.
Armed Services Board of Contract Appeals, 2024
Derian, Inc.
Armed Services Board of Contract Appeals, 2023
Fluor Intercontinental, Inc.
Armed Services Board of Contract Appeals, 2022
Triple Canopy, Inc. v. Secretary of the Air Force
14 F.4th 1332 (Federal Circuit, 2021)
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers
930 F.3d 1354 (Federal Circuit, 2019)
A.A.K.C.C
Armed Services Board of Contract Appeals, 2019
Kellogg Brown & Root Services, Inc. v. Murphy
823 F.3d 622 (Federal Circuit, 2016)
Estes Express Lines v. United States
123 Fed. Cl. 538 (Federal Claims, 2015)
Tektel, Incorporated v. United States
121 Fed. Cl. 680 (Federal Claims, 2015)
Lael Al Sahab & Co.
Armed Services Board of Contract Appeals, 2014
Kellogg Brown & Root Services, Inc.
Armed Services Board of Contract Appeals, 2014

Cite This Page — Counsel Stack

Bluebook (online)
677 F.3d 1166, 2012 WL 1372149, 2012 U.S. App. LEXIS 8062, Counsel Stack Legal Research, https://law.counselstack.com/opinion/parsons-global-ex-rel-odell-intern-v-mchugh-cafc-2012.