Shook v. United States

38 Cont. Cas. Fed. 76,424, 26 Cl. Ct. 1477, 1992 U.S. Claims LEXIS 484, 1992 WL 312639
CourtUnited States Court of Claims
DecidedOctober 28, 1992
DocketNo. 254-86C
StatusPublished
Cited by2 cases

This text of 38 Cont. Cas. Fed. 76,424 (Shook v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shook v. United States, 38 Cont. Cas. Fed. 76,424, 26 Cl. Ct. 1477, 1992 U.S. Claims LEXIS 484, 1992 WL 312639 (cc 1992).

Opinion

OPINION

HORN, Judge.

This case is before the court on defendant’s Motion to Dismiss for lack of subject matter jurisdiction, pursuant to Rule 12(b) of the Rules of the United States Claims Court (RUSCC), or in the alternative, for Summary Judgment, pursuant to RUSCC 56(b). Defendant contends that this court lacks jurisdiction over plaintiff’s claim because the claim was not submitted for a final decision by the contracting officer pri- or to filing the complaint in this court, in accordance with the requirements of the Contracts Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613 (1988).

Plaintiff, Neil E. Shook (Shook), the receiver of Focus Building Systems, Inc. (Focus), maintains that, at the direction of the Department of Labor (DOL), the Veterans Administration (VA) unlawfully withheld $46,520.00 in progress payments on a contract between the VA and Focus, because the VA failed to withhold the funds pursuant to statute, either the Davis-Bacon Act, 40 U.S.C.App. § 276a-l to a-5 (1982), or the Contract Work Hour and Safety Standards Act (CWHSSA), 40 U.S.C.App. §§ 327-333 (1982), or to issue proper prior notice of such withholding. Plaintiff alleges that it had presented its claim to the contracting officer of the VA, and that the VA did not deny the claim, but, rather, disclaimed any interest in the claim as a contract matter. Consequently, the DOL went ahead with the administrative wage determinations, and the monies were subsequently-withheld by the VA. The plaintiff further argues that the cross-withholding of $10,459.85 on Contract 441 was not authorized by law. Plaintiff maintains that, because the VA “was not damaged by” Focus Building Systems, Inc., because the VA would be unjustly enriched by retention of the payments at issue, because “no one has a better right to the funds than the Receiver,” and because the receiver is entitled to administer the funds for the benefit of creditors, plaintiff is entitled to $36,-060.15.1 After careful consideration of the briefs filed by both parties, and for the reasons discussed below, defendant’s Motion to Dismiss is, hereby, GRANTED.

FACTS

Plaintiff, Neil E. Shook, is the equity receiver of a government contractor, Focus Building Systems, Inc., an Indiana corporation, with its principal place of business in Indianapolis, Indiana. Appointed as receiver by the United States District Court for the Southern District of Indiana, Indianapolis Division, on December 20,1984, plaintiff alleges that it was authorized by that court [1479]*1479to bring this action in the United States Claims Court.

Prior to the appointment of Shook as receiver, Focus entered into five contracts with the VA. The case at bar involves four of the five VA contracts, each concerning a project at the Richard L. Roudebush Veterans Administration Medical Center (Roudebush), in Indianapolis, Indiana. The first contract, Contract No. V583C-441 (Contract 441), which concerned the relocation of the Cardiac Catheterization Laboratory at Roudebush, was entered into on June 21, 1983, for a contract price of $109,234.00. Contract No. V583C-448 (Contract 448) involved the expansion of the Nuclear Medicine Unit at Roudebush, and was entered into on August 18, 1983, for $149,848.00. On September 27, 1983, defendant and Focus entered into Contract No. V583C-451 (Contract 451), for renovation of the medical center’s Nursing Health Care Unit at a price of $296,899.00. The final contract at issue, Contract No. V583C-454 (Contract 454), was executed on October 19,1983, for $119,933.00, and required preparation for Automatic Data Processing Operations at Roudebush.

Each of the four contracts contained the same standard Disputes clause in the General Provisions section of the contract. Contract 441 and Contract 448 contained identical clauses governing (1) Disputes Concerning Labor Standards and (2) Withholding of Funds. Contracts 451 and 454 contained similar, albeit not identical clauses to those in Contracts 441 and 448. In addition, the same Davis-Bacon Act, 40 U.S.C.App. § 276a to 276a-5, and Contract Work Hours and Safety Standards Act (CWHSSA), 40 U.S.C. §§ 327-333, clauses were included in the Labor Standards Provisions section of each of the contracts.

By letter dated May 15,1984, the Department of Labor (DOL) notified VA contracting officer, Carlene S. Yeakle, that Focus and its subcontractor on Contracts 448, 451 and 454, Polk & Sons Electric Contractors, Inc. (Polk), had violated the Davis-Bacon Act and the Contract Work Hours and Safety Standards Act. The DOL stated that, because the investigations had just commenced at the time of the letter, no further information was available.

Pursuant to the DOL findings, the VA contracting officer, Yeakle, advised Focus, by .letter dated May 21, 1984, that, pursuant to the Labor Standards Provisions of the contracts, withholdings would be made from Contracts 448, 451 and 454. Yeakle informed Focus that because she had been “advised by the Department of Labor that violations of the Davis-Bacon Act and the Contract Work Hours and Safety Standards Act exist[ed],” she would continue to withhold ten percent of the total requested payment each month, until the DOL notified her that all wage violations had ceased, and that all employees had been paid their back wages. The contracting officer’s letter concluded with the statement: “Should it appear, as the investigation continues, that additional retainage is needed to cover such wages, I will notify you in advance of the withholding action.”

By letter dated June 27, 1984, Yeakle provided Focus with such advance notification. Yeakle stated:

On May 21, 1984, I advised you by letter that I would begin to withhold 10% on the following three contracts to cover Davis Bacon Act and Safety Standards Act violations.
Contract No. V583C-448, “Expand Nuclear Medicine”
Contract No. V583C-451, “Renovate N.H.C.U.”
Contract No. V583C-454, “Prepare for ADP Operations”
At the time of the letter the amount of back wages due employees were not known. I have recently been informed by the Department of Labor that there is a considerable amount owed by Polk and Sons Electric and the ten percent figure will not be sufficient retainage to insure payment of these wages to the employees.
I therefore will begin to withhold the back wage amounts furnished me by the Department of Labor on the above three [1480]*1480contracts with the exception of Contract No. V583C-451, “Renovate N.H.C.U.” I will continue to withhold 10% retainage on this contract until further information is furnished this office.

On July 18, 1984, Yeakle sent a formal cure notice to Focus regarding Contract 451, which provided the contractor with ten days to correct mechanical items which were delaying contract completion. Yeakle warned Focus that its failure to comply with the cure notice could result in termination of the contract, pursuant to the “Termination for Default” clause of the contract.

By letter dated October 22, 1984, Yeakle notified Focus that the DOL had requested withholdings from Contracts 441, 448 and 454, pending completion of investigations of Polk for Davis-Bacon Act violations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fire Insurance v. United States
61 Fed. Cl. 494 (Federal Claims, 2004)
Domagala v. United States
39 Cont. Cas. Fed. 76,600 (Federal Claims, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,424, 26 Cl. Ct. 1477, 1992 U.S. Claims LEXIS 484, 1992 WL 312639, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shook-v-united-states-cc-1992.