Neal & Company, Inc. v. The United States

945 F.2d 385, 37 Cont. Cas. Fed. 76,172, 24 Cl. Ct. 385, 1991 U.S. App. LEXIS 22255, 1991 WL 184874
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 23, 1991
Docket90-5108
StatusPublished
Cited by34 cases

This text of 945 F.2d 385 (Neal & Company, Inc. v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neal & Company, Inc. v. The United States, 945 F.2d 385, 37 Cont. Cas. Fed. 76,172, 24 Cl. Ct. 385, 1991 U.S. App. LEXIS 22255, 1991 WL 184874 (Fed. Cir. 1991).

Opinion

PLAGER, Circuit Judge.

Plaintiff-appellee Neal & Company, Inc. (Neal) entered into a fixed-price contract with defendant-appellant the United States (Government) to construct two fuel storage tanks at the United States Navy base at Adak, Alaska (Adak). The Government provided the specification for the manufacture of panels used in constructing the tanks. Some of the panels bowed during construction resulting in unanticipated costs to Neal. Additionally, Neal claimed that the contract required the Government to ship certain construction materials but that the Government did not, causing Neal to incur unanticipated shipping expenses. Neal submitted its claim, for both the bowed panels and shipping expenses, to the Resident Officer in Charge of Construction (ROICC) who in turn forwarded the claim to the contracting officer. The contracting officer refused to award these expenses to Neal and Neal sought recovery in the United States Claims Court. Chief Judge Smith, in a well reasoned opinion, held that the claim was properly before the court under the Contract Disputes Act and that Neal was entitled to recovery for both the bowed panel and the shipping expenses. Neal & Co. v. United States, 19 Cl.Ct. 463 (1990). The Government appeals; we affirm.

BACKGROUND

On February 17, 1984, the Government awarded Neal a fixed-price contract in the amount of $7,693,000 for the construction of two fuel oil storage tanks 1 at Adak. Each tank is constructed from a series of precast concrete panels covered on one side with a one-quarter inch thick steel lining. The roof of the tank is made of hundreds of smaller precast concrete panels and has no steel lining. During construction, the walls are erected, the roof attached and then a concrete floor is poured. Steel liner in the form of plates laid on top of the concrete floor completes the lining of the tank.

Neal arranged for the tank wall panels (with steel plates attached) and the roof panels to be manufactured by a third party near Seattle, Washington. These panels were than shipped to Adak for installation.

Bowing of the Panels. The wall panels were manufactured to the specification provided by the Government. Unfortunately, during manufacture, unanticipated bonding occurred between the steel lining and the wall panels causing the wall panels to bow. 2 To avoid the expense of discarding the bowed panels and starting again, Neal devised a plan to measure and match the bowed panels, thus allowing their use in a tank. This procedure required that the panels be erected in a particular sequence. Neal sought recovery of the unanticipated expense associated with measuring and marking the panels as well as unloading the panels in Adak to allow their erection in the required sequence.

Shipping. Under the contract, some of the construction material was to be shipped by the Government at Government expense and some was to be shipped by Neal at Neal’s expense. The relevant contract provision states in part:

The Government will ship from Seattle, Washington, to the U.S. Naval Station, Adak, Alaska, such [Neal]-owned construction materials as may be required for use under this contract, except precast concrete elements and steel tank liner, at no expense to [Neal],

Joint Appendix at 93. Neal read this provision to require the Government to ship all construction materials except the precast concrete elements attached to steel liners. Thus, the steel floor plates, which are not attached to concrete, would be shipped by the Government. The Government read the contract to require that it ship all con *388 struction material except: 1) precast concrete elements; and, 2) steel tank liner.

DISCUSSION

A. Jurisdiction

The Government argues that under the Contract Disputes Act, 41 U.S.C. §§ 601-12 (1988), the Claims Court lacked jurisdiction to rule on Neal’s claim. The Claims Court has jurisdiction over “any claim by or against, or dispute with, a contractor arising under [41 U.S.C. § 609(a)(1)].” 28 U.S.C. § 1491(a)(2) (1988). Section 609(a)(1) provides that a contractor may appeal to the Claims Court a decision of a contracting officer under section 605. Section 605(a) requires that:

All claims by a contractor against the government relating to a contract shall be in writing and shall be submitted to the contracting officer for a decision.

The Government argues that Neal failed to submit its claim to the contracting officer and that West Coast Gen. Corp. v. United States, 19 Cl.Ct. 98, 100-01 (1989) holds that a submission to other than the contracting officer fails to meet the requirements of section 605(a). From this, the Government concludes that the Claims Court lacked jurisdiction.

In the present case, prior to Neal’s submitting its claim to the ROICC, Neal wrote the ROICC requesting a contract adjustment. The ROICC responded in a letter stating that Neal had not submitted sufficient information to warrant a contract adjustment but that Neal could

request a decision of the Contracting Officer pursuant to the provisions of the disputes clause of the contract. [Neal could also] submit additional information and ... request that the previous correspondence concerning this matter be forwarded to the Contracting Officer for further review and final determination.

Joint Appendix at 256. Neal submitted additional information along with a claim addressed to the ROICC. The claim included a request for “a Contracting Officer’s Decision in accordance with [the contract].” Id. at 110.

The Claims Court, in awarding Neal monies for the bowed panel and shipping expenses, awarded interest from the time the claim reached the contracting officer, rather than from the time Neal submitted documentation to the ROICC. In effect, the court determined that the claim was submitted to the contracting officer on the date the claim was received by the contracting officer. Neal, 19 Cl.Ct. at 474; see 48 C.F.R. § 33.208 (1990).

The plain language of § 605 requires claims against the Government to be submitted to the contracting officer. It does not, however, require that the claims be sent only to the contracting officer, or necessarily directly to that officer. In enacting § 605 of the Contract Disputes Act, Congress described the flexible role of the contracting officer:

While the objective may be to make the contracting officer the focal point for decisions, practicability dictates that the extent to which the contracting officer relies on his own judgment or abides by the advice or determination of others is dependent on a variety of factors, including ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Endure Industries, Inc.
Armed Services Board of Contract Appeals, 2026
M. Nicolas Enterprises, Llc.
Federal Claims, 2021
KBAJ Enterprises, LLC t/d/b/a Home Again
Armed Services Board of Contract Appeals, 2016
KBAJ Enterprises, LLC t/b/d/a Home Again
Armed Services Board of Contract Appeals, 2016
RECO Rishad Engineering Construction ORG
Armed Services Board of Contract Appeals, 2016
Delaware Cornerstone Builders, Inc. v. United States
117 Fed. Cl. 539 (Federal Claims, 2014)
Diversified Maintenance Systems, Inc. v. United States
110 Fed. Cl. 612 (Federal Claims, 2013)
Newtech Research Systems LLC v. United States
99 Fed. Cl. 193 (Federal Claims, 2011)
Terry v. United States
96 Fed. Cl. 131 (Federal Claims, 2010)
Paradigm Learning, Inc. v. United States
93 Fed. Cl. 465 (Federal Claims, 2010)
Kemron Environmental Services, Inc. v. United States
93 Fed. Cl. 74 (Federal Claims, 2010)
Public Service Co. v. United States
88 Fed. Cl. 250 (Federal Claims, 2009)
Parker v. United States
77 Fed. Cl. 279 (Federal Claims, 2007)
Alliant Techsystems Inc. v. United States
74 Fed. Cl. 566 (Federal Claims, 2007)
Travelers Casualty & Surety of America v. United States
74 Fed. Cl. 75 (Federal Claims, 2006)
California Oregon Broadcasting, Inc. v. United States
74 Fed. Cl. 394 (Federal Claims, 2006)
Modeer v. United States
68 Fed. Cl. 131 (Federal Claims, 2005)
Tecom, Inc. v. United States
66 Fed. Cl. 736 (Federal Claims, 2005)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
Danka De Puerto Rico, Inc. v. United States
63 Fed. Cl. 20 (Federal Claims, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
945 F.2d 385, 37 Cont. Cas. Fed. 76,172, 24 Cl. Ct. 385, 1991 U.S. App. LEXIS 22255, 1991 WL 184874, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neal-company-inc-v-the-united-states-cafc-1991.