Universal Surety Co. v. United States

33 Cont. Cas. Fed. 74,603, 10 Cl. Ct. 794, 1986 U.S. Claims LEXIS 796
CourtUnited States Court of Claims
DecidedSeptember 18, 1986
DocketNo. 374-85C
StatusPublished
Cited by26 cases

This text of 33 Cont. Cas. Fed. 74,603 (Universal Surety Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Surety Co. v. United States, 33 Cont. Cas. Fed. 74,603, 10 Cl. Ct. 794, 1986 U.S. Claims LEXIS 796 (cc 1986).

Opinion

OPINION

BRUGGINK, Judge.

Pending before the court is Defendant’s Motion for Partial Summary Judgment, asserting that Count I of plaintiff’s two-count complaint must be dismissed for lack of subject matter jurisdiction. The general issue to be resolved in this case is a novel one: does a surety have the right to assert, independently of the contractor, claims against the government for amounts other than the “contract price?” Upon consideration of the written and oral arguments of the parties, the court concludes that under the circumstances presented here, it does [795]*795not, and dismisses all but one claim of Count I.

BACKGROUND

On April 7, 1982, Kener General Contractors, Inc. (“Kener”) entered into a contract with the Department of the Army Corps of Engineers for the construction of a mobile home park for the price of $476,995.00. On the same day, plaintiff executed both a performance bond and a payment bond, in the sums of $476,995.00 and $238,497.50, respectively, naming Kener as principal and defendant as obligee, thereby assuring funds for completion of the contract. On September 9, 1982, plaintiff sent defendant a registered letter stating that it was “financially assisting Kener in providing you a timely completed project.” Attached was a letter from Robert Lane, President of Kener, stating that his company had undergone a “temporary, but critical, cash-flow problem,” and that it therefore had “turned to our bonding company for assistance.” Based on the Lane letter, plaintiff went on to demand “that all further payments, including retention, be made payable to Universal.”

Subsequently, in a letter dated January 10, 1983, Carole Lane, Secretary/Treasurer of Kener, instructed defendant that:

Kener was forced to find financial assistance from Universal Surety Co. because of the cash flow problem caused by the government’s failure to meet progress payments. Kener has not assigned any government contracts to Universal Surety Co.

Although the precise circumstances and amounts are contested, it appears uncon-troverted that in late 1982, plaintiff began fulfilling its obligations under either the performance or payment bonds or both1 because of the financial instability of Ken-er. While plaintiff incurred losses on its bonds in the asserted amount of approximately $327,000.00, there was no written takeover agreement. Kener remained on the job and completed its work.

During the construction and after plaintiff began performing on its bonds, defendant issued a number of unilateral change orders in the work required, leading to adjustments, primarily downward, in the contract price. Plaintiff sought payment from defendant in the amount of $158,-331.78 for these change orders. In addition, plaintiff claimed $41,570.13 in damages alleged to have resulted from the clean-up of a PCB contamination at the project site, $6,000 in increased excavation costs, and $54,371.54, an amount retained by the government because of alleged payroll discrepancies. Finally, plaintiff also sought $87,075.00 for contract progress payments allegedly erroneously sent to Kener after plaintiff had notified the government that further payments should be sent to it.

Kener submitted no claim at all to the contracting officer for these disputed amounts. Although plaintiff did submit a claim, it admits that it was not in total compliance with the requirements of the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1982) (“CDA”). Plaintiff’s claim was dismissed by defendant on the ground that it should have been submitted by Kener, [796]*796and action was instituted in this court on June 24, 1985.

PLEADINGS

Plaintiffs complaint is based on its assertion that it paid claims against its performance bond in the sum of $327,000.00, and that it was therefore subrogated to all of Kener’s interest in the contract, including the right to assert claims under the CDA. In Count I of its complaint, plaintiff seeks $260,273.45 as damages resulting from the five change orders and the additional expenses allegedly incurred.

In Count II of the complaint, plaintiff seeks payment for the progress payment allegedly made improperly to Kener. Solely with respect to Count II, defendant has made Kener a third-party defendant and seeks indemnification from it for any potential liability. Although service was completed on Kener, no appearance has been made and no answer filed to defendant’s counterclaim. Count II is not at issue in the pending motion.

In its motion for summary judgment, defendant asserts as to Count I that the court lacks subject matter jurisdiction under the CDA because Kener did not file a properly certified claim with the contracting officer. It therefore seeks dismissal of Count I.

In subsequent briefing and argument, plaintiff states that the remedy sought in Count I is not dependent on a subrogation theory, and instead, that the surety agreement gives it direct privity of contract with defendant, so that it may recover either under the CDA or pursuant to 28 U.S.C. § 1491(a) (1982). More specifically, plaintiff asserts that it meets the definition of “contractor” contained in the CDA; that it filed a claim with the contracting officer; and that it therefore may bring this action under 41 U.S.C. § 609(a). Alternatively, plaintiff contends that if the court finds that it is not a “contractor” pursuant to the CDA, then it may rely on its alleged independent contractual relationship with the government, arising from the execution of the performance and payment bonds, naming the United States as obligee, to bring the action under 28 U.S.C. § 1491(a) without regard to the requirements of the CDA.

In reply, defendant asserts that sureties may bring contract actions against the government only under the doctrine of sub-rogation, and therefore that this action may not be grounded on 28 U.S.C. § 1491(a). Moreover, since the doctrine of subrogation is limited to claims against retained funds, plaintiff has no right to make claims for a price adjustment in the construction contract. With respect to plaintiff’s attempt to rest jurisdiction on 41 U.S.C. § 609(a), defendant contends that because plaintiff was not a party to the construction contract, it was not a “contractor” under the CDA and cannot file a claim under it. In any event, defendant argues that plaintiff’s attempt to submit a claim to the contracting officer under the CDA was ineffective because it failed to certify the claim in accordance with 41 U.S.C. § 605(c)(1).

ANALYSIS

A. Subrogation

The Court of Appeals for the Federal Circuit recently had occasion to discuss the remedies available to a construction contract surety against the government. In Balboa Insurance Co. v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartford Fire Insurance v. United States
108 Fed. Cl. 525 (Federal Claims, 2012)
Lumbermens Mutual Casualty Co. v. United States
654 F.3d 1305 (Federal Circuit, 2011)
Nelson Construction Co. v. United States
79 Fed. Cl. 81 (Federal Claims, 2007)
Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
Hanover Ins. Co. v. Corrpro Companies, Inc.
312 F. Supp. 2d 816 (E.D. Virginia, 2004)
Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)
Rig Masters, Inc. v. United States
42 Cont. Cas. Fed. 77,417 (Federal Claims, 1998)
Intercargo Insurance v. United States
42 Cont. Cas. Fed. 77,356 (Federal Claims, 1998)
Fidelity & Deposit Co. of Maryland v. United States
39 Cont. Cas. Fed. 76,675 (Federal Claims, 1994)
Transamerica Insurance v. United States
39 Cont. Cas. Fed. 76,671 (Federal Claims, 1994)
Transamerica Insurance Company v. The United States
989 F.2d 1188 (Federal Circuit, 1993)
North Slope Technical, Ltd. v. United States
38 Cont. Cas. Fed. 76,458 (Federal Claims, 1992)
George W. Kane, Inc. v. United States
38 Cont. Cas. Fed. 76,385 (Court of Claims, 1992)
Transamerica Insurance v. United States
37 Cont. Cas. Fed. 76,037 (Court of Claims, 1991)
Westech Corp. v. Fireman's Fund Insurance
36 Cont. Cas. Fed. 75,885 (Court of Claims, 1990)
Clean Giant, Inc. v. United States
36 Cont. Cas. Fed. 75,798 (Court of Claims, 1990)
Ransom v. United States
35 Cont. Cas. Fed. 75,674 (Court of Claims, 1989)
Washington International Insurance v. United States
16 Cl. Ct. 663 (Court of Claims, 1989)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,603, 10 Cl. Ct. 794, 1986 U.S. Claims LEXIS 796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-surety-co-v-united-states-cc-1986.