Carchia v. United States

485 F.2d 622, 202 Ct. Cl. 723, 1973 U.S. Ct. Cl. LEXIS 226
CourtUnited States Court of Claims
DecidedOctober 17, 1973
DocketNo. 242-67
StatusPublished
Cited by26 cases

This text of 485 F.2d 622 (Carchia v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carchia v. United States, 485 F.2d 622, 202 Ct. Cl. 723, 1973 U.S. Ct. Cl. LEXIS 226 (cc 1973).

Opinion

Davis, Judge,

delivered the opinion of the court:

This is a contract case, brought by the plaintiff, receiver for Dorchester Equipment Co., Inc. (the company is sometimes called plaintiff), for breach of a construction contract between that firm and the United States, acting through the Post Office Department. The contract was in lump-sum form, subject to adjustment for unit prices for piling, pre-drilling for piling, and other such items. The price arrived at by competitive bidding was $265,000. The award was made on July 19, 1961, by the Post Office Department, Bureau of Facilities, Division of Beal Estate. The work required the contractor to furnish all labor, equipment and materials and perform work for demolition, removal of railroad trackage, canopies, etc., necessary to construct footings for a future canopy at Terminal Annex, South Postal Annex, United States Post Office, Boston, Massachusetts. The plans and specifications had been prepared by Pedersen and Tilney, architects of Boston. The work was to commence as soon as possible after receipt of notice to proceed and was to be completed in 150 calendar days after receipt of that notice. The completion date thus computed became December 27, 1961.

The plaintiff makes claim on account of extra work necessitated by changed conditions, for costs incurred by reason of unreasonable delays to the work, and for damages resulting from the alleged wrongful termination of the contract.

The intervenor, the Aetna Casualty and Surety Company, became the surety on the performance and payment bonds. By motion to intervene on the ground that representation of its interest is or may be inadequate, that it may be bound by the judgment, and that it has a pecuniary interest in the subject matter of the action, the intervenor has been permitted to be [728]*728added, as a party to this litigation and has participated in the proceedings. By arrangement with the Government, the surety completed the contract work.

The defendant filed a counterclaim against the plaintiff covering certain architect-engineer expenses and other expenses by reason of alleged defective work, in the sum of $5,789. The defendant also filed a contingent counterclaim against the intervenor for sums which the court might find were paid by the defendant to Aetna, but which should have been paid to the Dorchester Equipment Company. It originally asked judgment, also, over against Aetna for any amount awarded to the plaintiff, but that claim is no longer pursued.

The contractor’s claims were the subject of an appeal to the Post Office Board of Contract Appeals which, after extended hearings, found that the “termination for default was premature”, and remanded the matter to the contracting officer for settlement of the amount due Dorchester. When the parties were unable to agree on a settlement, additional hearings were held and a subsequent decision was entered which allowed the plaintiff $20,725.47 for extra work but held that the Board was without jurisdiction to determine liability for delay claims or standby time or the claim relating to termination for default. There is no evidence that the $20,725.47 was ever paid to the plaintiff or Dorchester Equipment. In this court, the parties agreed to a trial de novo which has been held.

As a result of the trial, the trial judge determined: “On the basis of the entire record it is concluded that the termination for default was improper and unwarranted and a breach of the contract since a great deal of the delay which was charged to the plaintiff was actually the fault of the defendant through its architect and in turn through its architect’s subcontractor. Additional causes of delay are clearly not chargeable to the contractor since they were due to the encountering of a great many underground obstructions which interfered with the orderly progress of the work by not only the contractor but its pile-driving subcontractor. For such breach of contract the defendant must respond in [729]*729damages for 'the breach.”1 Defendant does not challenge these conclusions, nor does it contest that the contractor performed additional work for which it should be compensated. It is therefore unnecessary to recite the facts showing that the trial judge is correct. (His findings on these points, which we adopt, present sufficient detail.) The issues which remain to be decided concern the amounts of recovery 'by the plaintiff (Part I, infra) and by the surety (Part IT, infra), and the disposition of the Government’s counterclaims (Part III, infra).

I

The trial judge found $63,602.30 now owing by defendant to plaintiff. The Government contests only one item (i.e. anticipated profits), but plaintiff asks us to add several additional sums. We reject all of these exceptions and confirm the amount arrived at by the trial judge.

a. Since this was an old-style contract which did not provide that a wrongful default termination was to be considered a convenience-termination, plaintiff was entitled to anticipated profits for work not yet performed at the time it received the improper notice of default termination. See General Builders Supply Co. v. United States, 187 Ct. Cl. 477, 485-86, 409 F. 2d 246, 251 (1969); J. D. Hedin Constr. Co. v. United States, 187 Ct. Cl. 45, 58-59, 408 F. 2d 424, 431-32 (1969). The trial judge assessed this at $28,042.70, a sum derived from the costs incurred and the profit made by the company which completed the work on behalf of the surety. The Government argues that it was error to use that firm’s profit-and-costs as a measure, and that the correct gauge of anticipated profits would take into account the relationship of the amount of work left undone by Dorchester Equipment to the contract’s original fixed price. The latter amount was $265,000, and under our findings Dorchester performed $152,000 of this work, leaving $113,000 worth still to be performed; defendant would grant plaintiff 10% of this sum ($11,300) in anticipated profits.

[730]*730We hold that the trier’s method was acceptable. If Dor-chester had not been wrongly terminated, it would have completed the contract and probably done the same work and incurred the same costs (including a very considerable amount of extras) as the company which actually finished the job. The completing firm’s profit is therefore a reasonable basis for the award to plaintiff of the gain it lost through the Government’s wrongful ending of the contract. As we point out below (Part II, B, infra), the completing firm’s actual costs and outlays must be taken on this record as reasonable — and it is not far-fetched to infer that Dorchester would have had equivalent expenses and done about the same amount of work.

b. 1. In his brief, plaintiff specifies a number of work items, omitted by the trial judge, for which he says Dor-chester should be further compensated.2 We agree with defendant that, as to one instance, the trial judge did in fact cover the item and allow compensation, and, as to the others, plaintiff has made insufficient proof that it incurred the costs now claimed. On these items, there is plainly insufficient reason to overturn the trial judge’s considered denial of compensation. Cf. Davis v. United States, 164 Ct. Cl. 612, 616-17 (1964).

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nova Casualty Co. v. United States
69 Fed. Cl. 284 (Federal Claims, 2006)
Dunn & Black, P.S. v. United States
366 F. Supp. 2d 1008 (E.D. Washington, 2005)
Home Insurance v. United States
46 Fed. Cl. 160 (Federal Claims, 2000)
International Fidelity Insurance v. United States
42 Cont. Cas. Fed. 77,368 (Federal Claims, 1998)
Federal Insurance v. United States
39 Cont. Cas. Fed. 76,576 (Federal Claims, 1993)
George W. Kane, Inc. v. United States
38 Cont. Cas. Fed. 76,385 (Court of Claims, 1992)
United Pacific Insurance v. United States
38 Cont. Cas. Fed. 76,361 (Court of Claims, 1992)
Westech Corp. v. Fireman's Fund Insurance
36 Cont. Cas. Fed. 75,885 (Court of Claims, 1990)
Ransom v. United States
35 Cont. Cas. Fed. 75,674 (Court of Claims, 1989)
Washington International Insurance v. United States
16 Cl. Ct. 663 (Court of Claims, 1989)
Travelers Indemnity Co. v. United States
35 Cont. Cas. Fed. 75,607 (Court of Claims, 1988)
Universal Surety Co. v. United States
33 Cont. Cas. Fed. 74,603 (Court of Claims, 1986)
Balboa Insurance Company v. The United States
775 F.2d 1158 (Federal Circuit, 1985)
Hedstrom Lumber Co. v. United States
32 Cont. Cas. Fed. 73,113 (Court of Claims, 1984)
Peck Iron & Metal Co. v. United States
603 F.2d 171 (Court of Claims, 1979)
Allied Materials & Equipment Co. v. United States
569 F.2d 562 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
485 F.2d 622, 202 Ct. Cl. 723, 1973 U.S. Ct. Cl. LEXIS 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carchia-v-united-states-cc-1973.