Aeroplate Corp. v. United States

112 Fed. Cl. 88, 2013 U.S. Claims LEXIS 1003, 2013 WL 3964006
CourtUnited States Court of Federal Claims
DecidedAugust 1, 2013
Docket12-374C
StatusPublished
Cited by1 cases

This text of 112 Fed. Cl. 88 (Aeroplate Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Aeroplate Corp. v. United States, 112 Fed. Cl. 88, 2013 U.S. Claims LEXIS 1003, 2013 WL 3964006 (uscfc 2013).

Opinion

Subeontractors’ Motion to Intervene; RCFC 24(a)(2)

OPINION AND ORDER

SWEENEY, Judge

Plaintiff Aeroplate Corp. alleges that the United States Department of Veterans Affairs (“VA”) breached a contract related to the renovation of the VA medical center in Philadelphia, Pennsylvania. U.S. Glass, Inc. and XLE Materials, Inc., two of plaintiffs subcontractors on the project, move to intervene in this suit to obtain and enforce an equitable lien on the funds held by the VA that are set aside for the project or owed to plaintiff. For the reasons set forth below, the court denies the subcontractors’ motion to intervene.

I. BACKGROUND

The VA awarded the medical center renovation contract, contract number VA244-C-1453, to plaintiff on July 30, 2010. 1 Plaintiff then executed a payment bond for the contract amount, $8,876,145, on September 8, 2010. The surety was an individual, Ronald D. Patterson, who pledged real estate at three locations in support of the bond. The VA issued a notice to proceed on November 3, 2010, and in May 2011, plaintiff hired the putative intervenors to provide materials and labor. The subcontractors submitted invoices to plaintiff in May, June, and July 2011, requesting payment for their work. Plaintiff did not pay the subcontractors. In October 2011, one of the subcontractors— U.S. Glass, Inc. — advised the VA that it had not been paid. However, according to the subcontractors, the VA continued to make payments to plaintiff. On January 31, 2012, the subcontractors submitted claims .to the payment bond surety: U.S. Glass, Inc. sought $118,085, and XLE Materials, Inc. sought $58,789.77. The surety has not paid the subcontractors.

The subcontractors filed a Miller Act suit against plaintiff, the surety, and a corporation purportedly owned by the surety on May *90 15, 2012, in the United States District Court for the Eastern District of Pennsylvania, for the money owed to them for the work that they performed on the project. The three defendants filed an answer on September 11, 2012, which included the following affirmative defense: “The United States Government is the owner of the property and responsible for the payment.”

In the meantime, on June 12, 2012, plaintiff filed suit in this court against the United States. Plaintiff alleges that work on the project has been suspended since September 24, 2011, and seeks damages of $688,513.14 for unpaid contract modifications, delays, and the aforementioned suspension of work. On October 24, 2012, the defendants in the district court action, including plaintiff here, sought a stay of the district court proceedings pending the resolution of this suit. In their stay petition, the district court defendants alleged that the United States refused to pay the balance due on the VA medical center renovation contract and that once the suit in the United States Court of Federal Claims was resolved, the subcontractors would be paid in full. The district court denied the stay petition on November 13, 2012; proceedings in that suit remain ongoing.

The subcontractors were not the only parties to file suit against plaintiff for its failure to make payments. After plaintiff defaulted on several loans made by Premier Valley Bank that were secured, in part, by plaintiff’s accounts receivable, the bank obtained a judgment against plaintiff in the Fresno County, California Superior Court on March 27, 2013, in the amount of $743,136.24. On May 8, 2013, the bank sought to intervene in this case for the sole purpose of placing a lien on the proceeds, if any, of plaintiffs suits in this court. 2 Due to the bank’s failure to assert noneonelusory allegations regarding its interest in plaintiffs claims, the court denied its motion to intervene on June 7, 2013.

Subsequently, on June 26, 2013, the subcontractors moved to intervene as plaintiffs. Specifically, the subcontractors “seek to obtain and enforce an equitable lien on funds held by the [VA], including, but not limited to, those funds earmarked for the construction project known as government contract number VA 244-C-1453 as well as other funds owing to [plaintiff].” As the basis for their motion to intervene, they contend that the VA did not properly scrutinize the issuer of the payment bond, that the payment bond did not conform to the relevant legal requirements, and that the VA continued to pay plaintiff despite having notice of plaintiffs failure to pay its subcontractors. 3 Both plaintiff and defendant oppose the subcontractors’ motion to intervene.

II. DISCUSSION

The subcontractors seek to intervene in this suit as a matter of right pursuant to Rule 24(a)(2) of the Rules of the United States Court of Federal Claims (“RCFC”). RCFC 24(a)(2) provides:

On a timely motion, the court must permit anyone to intervene who ... claims an interest relating to the property or transaction that is the subject of the action, and is so situated that disposing of the action may as a practical matter impair or impede the movant’s ability to protect its interest, unless existing parties adequately represent that interest.

The requirements of this rule “are to be construed in favor of intervention[.]” Am. *91 Mar. Transp., Inc. v. United States, 870 F.2d 1559 (Fed. Cir. 1989).

A. Timeliness

Parsing RCFC 24(a)(2)’s requirements, the first prong to satisfy intervention is that the motion must be timely filed. The United States Court of Appeals for the Federal Circuit (“Federal Circuit”) has provided factors to consider when determining whether a motion to intervene is timely: (1) the length of time a putative intervenor knew or should have known of its right to intervene prior to filing its motion; (2) the balance of harms — whether the prejudice to the rights of the existing litigants, if intervention is granted, is outweighed by the prejudice an intervenor would suffer if intervention is denied; and (3) the existence of unusual circumstances that weigh in favor of or against the granting of the motion. Belton Indus., Inc. v. United States, 6 F.3d 756, 762 (Fed. Cir. 1993).

According to the subcontractors, they first learned that plaintiff had filed a complaint in this court eight months prior to filing their motion to intervene. The subcontractors do not elaborate or offer anything more to their timeliness argument; consequently, the court will construe their argument to be that an eight-month delay in filing is insignificant. Interestingly, neither plaintiff nor defendant comment on the timeliness of the motion.

Although an eight-month lag in seeking intervention cannot be characterized as proceeding posthaste, RCFC 24(a)(2) requires only that the motion be timely. Because plaintiff amended its complaint and discovery disputes arose after the filing of the amended complaint, this ease has not progressed, after eight months, as far down the litigation track as the court finds optimal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
112 Fed. Cl. 88, 2013 U.S. Claims LEXIS 1003, 2013 WL 3964006, Counsel Stack Legal Research, https://law.counselstack.com/opinion/aeroplate-corp-v-united-states-uscfc-2013.