United Pacific Insurance v. United States

16 Cl. Ct. 555, 1989 U.S. Claims LEXIS 16, 1989 WL 7441
CourtUnited States Court of Claims
DecidedFebruary 2, 1989
DocketNo. 321-86C
StatusPublished
Cited by8 cases

This text of 16 Cl. Ct. 555 (United Pacific Insurance v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Pacific Insurance v. United States, 16 Cl. Ct. 555, 1989 U.S. Claims LEXIS 16, 1989 WL 7441 (cc 1989).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This action comes before the court on parties’ cross motions for summary judgment. In dispute is whether defendant abused its discretion in issuing a progress payment during the course of a construction contract.

FACTS

On March 10, 1983, defendant through the Department of the Air Force awarded a contract to Electro Technical Corporation (ETC) for the construction of an emergency power system at Hill Air Force Base, Utah. Plaintiff, United Pacific Insurance Company, provided payment and performance bonds pursuant to the Miller Act, 40 U.S.C. [556]*556§§ 270a-270d (1982). Several months after work had begun on the project, ETC prepared an application for a fifth progress payment in the amount of $450,000.00 for diesel engine generator sets and $36,000.00 for electronic switchgear, stating therein that the equipment was ninety percent complete. The amount sought was more than half the original contract price and constituted a major portion of the contract.

Before approving the payment, project engineer Brian Nosker and project inspector Key Pittman met with representatives of ETC to visually confirm the progress of the generator sets, as represented by ETC, since progress payments were normally issued only for work already completed. The subcontractor in charge of manufacturing the generator sets, which consisted of generators, auxiliaries and gauges mounted onto diesel engines, had only the diesel engines in its possession. Individuals at that subcontractor’s yard assured Nosker and Pittman that the rest of the components were either on order or in transit and that all were intended for the Hill Air Force Base project. No apparent proof of those assertions were provided. Nosker and Pittman did not inspect nor inquire about the switchgear which was to be furnished by a different subcontractor. In truth, the components of the switchgear had not been ordered, let alone assembled, and contrary to the statements of ETC, neither the generator sets nor the switchgear were ninety percent complete. In addition, plaintiff was required by the terms of the contract to present shop plans and submittals for the generator sets and electronic switchgear to defendant for its approval. ETC’s submittals, however, had not passed government scrutiny and, at the point in time when ETC claimed that the equipment was ninety percent complete, were in a state of disapproval. Despite ETC’s apparent false statements about the degree of completion of the equipment, and the disapproval of its submittals, the contracting officer approved ETC’s application and caused a check to be issued in the full amount requested for the fifth progress payment on September 1, 1983. The check was deposited into ETC’s general account, but the funds were not used by ETC to pay for the generator sets or the electronic switchgear.

In late December, 1983, an unidentified disgruntled subcontractor informed defendant that ETC was not paying its bills and was in shaky financial condition. Defendant apparently chose not to investigate that allegation and continued to make progress payments during the course of construction.1 Progress was made on the contract and the completed generator sets were delivered to the jobsite on March 8, 1984, and the switchgear on August 28, 1984, almost a year after it was paid for. In October 1984, when it became obvious that the contractor’s fiscal problems might indeed threaten final completion of the project, defendant ceased making progress payments to ETC. The court notes that prior to that time defendant had received no notification from plaintiff that ETC was in financial difficulty or that it should stop making progress payments. On March 6, 1985, a year and a half after defendant became aware of the problem, plaintiff informed defendant of ETC’s poor financial state and requested that all future progress payments, plus retainage, be forwarded to plaintiff. Apparently, defendant complied with this request. The project was completed almost a month later on April 2, 1985, a full year after the scheduled completion date. The subcontractors working on the generator sets and switchgear were paid, not by ETC, but by plaintiff in accord with the surety agreement.

DISCUSSION

Summary judgment is appropriate when there is no genuine issue of material fact in dispute and the moving party is entitled to judgment as a matter of law. RUSCC 56(c). In evaluating a motion for summary judgment, any doubt over whether there is a genuine issue of material fact must be [557]*557resolved in favor of the non-moving party. Housing Corp. of America v. United States, 199 Ct.Cl. 705, 710, 468 F.2d 922, 924 (1972); Campbell v. United States, 2 Cl.Ct. 247, 249 (1983). In addition, the inferences to be drawn from the facts must be viewed in the light most favorable to the party opposing the motion. Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 1608-09, 26 L.Ed.2d 142 (1970). The court agrees with the parties that there are no genuine issues of material fact in dispute and that this case is properly before the court for disposition on cross motions for summary judgment.

Plaintiff brought suit pursuant to the Tucker Act, 28 U.S.C. § 1491(a)(1) (1982), alleging that defendant had no discretion to authorize the progress payment No. 5 because such payment went beyond the specific terms of the payments clause of the contract. In the alternative, plaintiff argued that even if defendant had the discretionary authority to issue the fifth progress payment, that discretion was abused when defendant acted in complete disregard of plaintiff's interests in the face of strict contractual guidelines to the contrary. Defendant countered simply that the contracting officer had the discretion to make the progress payment, that he acted within his authority, and that plaintiff failed to meet its burden of proof in demonstrating an abuse of discretion.

In its foundational argument, plaintiff maintained that the contract was the sole source of the contracting officer’s discretionary power, setting forth terms and conditions which had to be met before payment for off-site materials could be made. The specific contract language relied on by plaintiff states:

PAYMENTS TO CONTRACTOR (1979 MAR) ... Material delivered to the Contractor at locations other than the site may also be taken into consideration (1) if such consideration is specifically authorized by the contract and (2) if the Contractor furnishes satisfactory evidence that he has acquired title to such material and that it will be utilized on the work covered by this contract.

Plaintiff argued that because ETC did not have, indeed could not have had, title to the diesel engine generator sets and electronic switchgear, defendant failed to comply with the conditions for payment of off-site material and thus had no authority to make the fifth progress payment. Plaintiff relied upon Argonaut Ins. Co. v. United States, 193 Ct.Cl. 483, 434 F.2d 1362 (1970), in which that court noted that the contract “gave defendant the right to exercise broad discretion in administering payments as the work progressed in order to promote performance.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fire Insurance v. United States
78 Fed. Cl. 308 (Federal Claims, 2007)
Nova Casualty Co. v. United States
72 Fed. Cl. 755 (Federal Claims, 2006)
Lumbermens Mutual Casualty Co. v. United States
67 Fed. Cl. 253 (Federal Claims, 2005)
American Insurance v. United States
62 Fed. Cl. 151 (Federal Claims, 2004)
Westchester Fire Insurance v. United States
52 Fed. Cl. 567 (Federal Claims, 2002)
Reliance Insurance v. United States
38 Cont. Cas. Fed. 76,494 (Federal Claims, 1993)
Ransom v. United States
35 Cont. Cas. Fed. 75,674 (Court of Claims, 1989)
United States Fidelity & Guaranty Co. v. United States
35 Cont. Cas. Fed. 75,637 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
16 Cl. Ct. 555, 1989 U.S. Claims LEXIS 16, 1989 WL 7441, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-pacific-insurance-v-united-states-cc-1989.