Iacobelli Construction, Inc. v. County of Monroe, Rochester Pure Waters District, and Calocerinos & Spina Consulting Engineers, P.C.

32 F.3d 19, 40 Fed. R. Serv. 1193, 1994 U.S. App. LEXIS 18278
CourtCourt of Appeals for the Second Circuit
DecidedJuly 21, 1994
Docket1460, Docket 93-9193
StatusPublished
Cited by86 cases

This text of 32 F.3d 19 (Iacobelli Construction, Inc. v. County of Monroe, Rochester Pure Waters District, and Calocerinos & Spina Consulting Engineers, P.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iacobelli Construction, Inc. v. County of Monroe, Rochester Pure Waters District, and Calocerinos & Spina Consulting Engineers, P.C., 32 F.3d 19, 40 Fed. R. Serv. 1193, 1994 U.S. App. LEXIS 18278 (2d Cir. 1994).

Opinion

GEORGE C. PRATT, Circuit Judge:

This appeal arises out of a contract to construct a sewage tunnel in Rochester, New York. When the plaintiff, Iacobelli Construction, Inc., encountered more subsurface water inflows during construction of the tunnel than it had anticipated, it requested additional compensation under the contract’s differing site conditions clause. The County of Monroe denied Iaeobelli’s request, which led Iacobelli to institute this suit in the United States District Court for the Western District of New York, Michael A. Telesca, Chief Judge. The district court held that Iacobelli failed to establish a viable claim for differing site conditions and granted summary judgment for the county.

FACTS AND BACKGROUND

The Rochester Pure Waters District (“RPWD”), an agent for the County of Monroe in New York, was responsible for the overall administration of the Combined Sewer Overflow Abatement Project for Rochester, New York. Funded primarily by the Environmental Protection Agency (“EPA”), the project involved establishing a network of tunnels for storing sewage overflow during storm periods and for transporting it to a treatment facility. For the purpose of soliciting bids, RPWD combined construction of *22 two large waste-water tunnels, the Jay-Ar-nett and Saxton-Colvin tunnels, into one project. The Jay-Arnett tunnel was to be 8792 feet long; the Saxton-Colvin tunnel, 6155 feet. Both tunnels were to have an excavated diameter of twelve feet and were to be constructed in hard rock more than 120 feet underground.

In 1981 RPWD retained Calocerinos & Spina Consulting Engineers (“C & S”) to prepare the bid documents and to help administer and supervise the construction. C & S in turn engaged two other firms to perform a geotechnical investigation and to prepare the final tunnel design. RPWD then distributed to prospective bidders the materials prepared by C & S, which contained information about the site conditions, technical specifications for the tunnels, construction plans, and geotechnical information. The geotechnical information included borehole data and descriptions of the subsurface rock conditions. Construction would require excavating the tunnels, removing debris, lining the tunnels with concrete, grouting the connections between tunnel segments, and a final cleanup.

Because the project was funded largely by the EPA, federal regulations required a differing site conditions clause to be part of the contract. It provided:

a. The CONTRACTOR shall promptly, and before such conditions are disturbed, notify the ENGINEER in writing of:
(1) Subsurface or latent physical conditions at the site differing materially from those indicated in this Contract, or
(2) unknown physical conditions at the site of an unusual nature differing materially from those ordinarily encountered and generally recognized as inherent in the work of the character provided for in this Contract.
The ENGINEER shall promptly investigate the conditions and, if he finds that such conditions do materially so differ and cause an increase or decrease in the CONTRACTOR’S cost of, or the time required for, performance of any part of the work under this Contract, whether or not changed as a result of such conditions, an equitable adjustment shall be made and the Contract.modified in writing accordingly-

Iacobelli, the low bidder, was ultimately awarded the contract. To prepare its estimate, Iacobelli’s tunneling engineer, Jim Peters, reviewed the documents furnished by RPWD, conducted an inspection of the project site, and consulted someone who had previously managed two of Rochester’s deep-tunnel projects. Peters concluded that the Jay-Arnett and Saxton-Colvin tunnel sites would be relatively dry, and advised Iacobelli that ground-water inflows should not be sufficiently large to affect operations. Iacobelli structured its bid accordingly.

Construction on the Saxton-Colvin tunnel went smoothly, and it was completed first. However, when Iacobelli began working on the Jay-Arnett tunnel, it encountered three conditions that differed from those it had anticipated from the bid documents: a geological fault, water inflows, and hydrogen sulfide gas. Although Iacobelli had originally planned on constructing both tunnels in essentially the same manner, these three factors forced it to modify its plans in order to complete the Jay-Arnett tunnel in accordance with the contract specifications.

The water inflows created the most difficulty for Iacobelli, because the level of infiltration was much greater than what it had expected. To stave off the additional water, Iacobelli had to perform excavation, concrete-lining, and grouting operations for which it had not originally planned. Consequently, on January 26, 1984, Iacobelli informed C & S that it had encountered

an unknown physical condition at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract.

As required by the differing site conditions clause, C & S began investigating Iacobelli’s claim. It also requested further information from Iacobelli.

Iacobelli submitted an itemized “Claim for Extra Compensation Resulting from Excessive Water” on May 18, 1984. Stating that water entered the tunnel at a rate of four-hundred gallons per minute more than nor *23 mal, causing premature failure in the tunnel boring machine and the muck-conveyor system, Iaeobelli requested additional compensation of $757,947. After conducting its own investigation, C & S recommended that the county reject Iacobelli’s claim, because it found that the water inflow in the tunnel was not excessive and that it was Iacobelli’s own inability to handle the infiltration of hydrogen sulfide gas and failure to dewater which led to the delays in construction of the tunnel. The county finally rejected Iacobelli’s claim in mid-1986.

Iaeobelli filed this action in December 1988, claiming breach of contract and breach of warranty against the county and RPWD, and claiming negligence against C & S. On October 27,1992, the district court dismissed Iacobelli’s claim against C & S, holding that it was barred by New York’s three-year statute of limitations for negligence. The county then impled C & S as a third-party defendant.

On October 13, 1993, the district court granted summary judgment for the county on the remaining claims, holding that there was no evidence to support Iacobelli’s claim that “the contract documents failed to give it notice of troublesome water.”

DISCUSSION

On appeal, Iaeobelli claims that the district court: (1) erred in granting summary judgment for the county, because a genuine issue of material fact exists regarding whether the encountered conditions materially differed from those indicated in the contract; (2) should not have dismissed its claims of unreasonable interference and breach of warranty; and (3) erred in ruling that its negligence action against C & S was time-barred, because it incorrectly determined the time at which the action accrued. We address each contention in turn.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re: Kenneth Gene Wilkinson
E.D. California, 2025
St. Sauver v. Byrd-Hunt
S.D. California, 2022
Loeber v. Alghusain
N.D. California, 2020
Jensen v. Cablevision Sys. Corp.
372 F. Supp. 3d 95 (E.D. New York, 2019)
Lara v. Delta International Machinery Corp.
174 F. Supp. 3d 719 (E.D. New York, 2016)
Hilaire v. DeWalt Industrial Tool Co.
54 F. Supp. 3d 223 (E.D. New York, 2014)
Indradjaja v. Holder
Second Circuit, 2013
Pedersen v. Office of Personnel Management
881 F. Supp. 2d 294 (D. Connecticut, 2012)
Valentini v. Citigroup, Inc.
837 F. Supp. 2d 304 (S.D. New York, 2011)
Noveck v. PV Holdings Corp.
742 F. Supp. 2d 284 (E.D. New York, 2010)
Securities & Exchange Comm'n v. Johnson
525 F. Supp. 2d 66 (District of Columbia, 2007)
Blansett v. Continental Airlines, Inc.
246 F. Supp. 2d 596 (S.D. Texas, 2002)
We Media Inc. v. General Electric Co.
218 F. Supp. 2d 463 (S.D. New York, 2002)
New York v. Solvent Chemical Co., Inc.
225 F. Supp. 2d 270 (W.D. New York, 2002)
Stanford Square, L.L.C. v. Nomura Asset Capital Corp.
228 F. Supp. 2d 293 (S.D. New York, 2002)
Webster v. Moquin
175 F. Supp. 2d 315 (D. Connecticut, 2001)
In re Linerboard Antitrust Litigation
203 F.R.D. 197 (E.D. Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
32 F.3d 19, 40 Fed. R. Serv. 1193, 1994 U.S. App. LEXIS 18278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iacobelli-construction-inc-v-county-of-monroe-rochester-pure-waters-ca2-1994.