Fruin-Colnon Corp., Traylor Bros. v. Niagara Frontier Transportation Authority

180 A.D.2d 222, 585 N.Y.S.2d 248, 1992 N.Y. App. Div. LEXIS 8218
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 5, 1992
DocketAppeal No. 1
StatusPublished
Cited by19 cases

This text of 180 A.D.2d 222 (Fruin-Colnon Corp., Traylor Bros. v. Niagara Frontier Transportation Authority) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fruin-Colnon Corp., Traylor Bros. v. Niagara Frontier Transportation Authority, 180 A.D.2d 222, 585 N.Y.S.2d 248, 1992 N.Y. App. Div. LEXIS 8218 (N.Y. Ct. App. 1992).

Opinion

OPINION OF THE COURT

Denman, P. J.

This dispute arises from a contract between plaintiff, a joint venture consisting of Fruin-Colnon Corporation, Traylor Bros., Inc., and Onyx Construction & Equipment, Inc., and defendant, the Niagara Frontier Transportation Authority. The contract called for plaintiff to excavate and construct twin subway tunnels, each approximately two miles long, as part of the Buffalo light rail rapid transit system. There are three major areas of dispute. The first, the focus of plaintiff’s first cause of action, concerns whether, during its excavation efforts, plaintiff encountered a "differing site condition” (DSC) entitling it to recover $3,255,150 in excess of the contract price of $38,949,800. The second area of dispute concerns which party bears the responsibility for rectifying the infiltration of water into the tunnels. The "watertightness” issue is the focus of plaintiff’s second cause of action, which sought $568,297.80 as reimbursement for remedial grouting efforts undertaken by plaintiff before it was ordered off the project. The watertightness issue is also the subject of defendant’s counterclaim seeking to recover actual damages (payments to [225]*225third parties for remedial waterproofing) and liquidated damages. The third area of dispute, somewhat related to the watertightness issue, is whether plaintiff improperly constructed the tunnel by leaving voids between the concrete tunnel liner and the surrounding rock and by failing to pour the concrete to a minimum thickness of 12 inches. The "tunnel thickness” issue is the subject of defendant’s additional counterclaim seeking to recover approximately $750,000 paid to third parties to test the tunnel and bring it into compliance with the contract requirements.

Following a lengthy two-stage trial, the IAS court entered judgment awarding plaintiff $568,297.80 plus 4% interest on its watertightness claim. The court denied plaintiff’s DSC claim, and also denied defendant’s watertightness and tunnel thickness counterclaims. Plaintiff appeals from that judgment insofar as it denied its DSC claim and failed to award 9% interest on its watertightness claim. Plaintiff contends that the trial proof unequivocally established the existence of a DSC; that the court erred in refusing to admit into evidence a certain letter (in which defendant’s subconsultants favorably evaluated plaintiff’s DSC claim) as an adoptive admission; and that, by statute, interest should accrue on the judgment at the rate of 9%.

Defendant cross-appeals from the judgment insofar as it granted plaintiff recovery on its watertightness claim and denied defendant’s watertightness and tunnel thickness counterclaims. Defendant contends that the contract contained a performance specification that imposed the responsibility for achieving watertightness upon plaintiff. Defendant argues that, consequently, plaintiff was not entitled to extra payment for grouting, that defendant properly terminated plaintiff for its default in correcting the water leakage, that defendant is entitled to recover the cost of remedial work to bring the tunnel into conformity with the contract, and that defendant is entitled to liquidated damages for delay in completion of the work.

Additionally, defendant appeals from a subsequent order granting plaintiff’s motion to settle the record on appeal to include Exhibit 212, the aforementioned letter of defendant’s subconsultants that plaintiff unsuccessfully sought to admit into evidence in support of its DSC claim. Defendant contends that the document was improperly included in the record because it was not admitted into evidence.

[226]*226 DSC DISPUTE

PLAINTIFF DID NOT ESTABLISH THE EXISTENCE

OF DIFFERING SITE CONDITIONS.

In order to prevail on its differing site condition claim, plaintiff was required to prove six elements: the contract documents must have affirmatively indicated the subsurface conditions; plaintiff must have acted as a reasonably prudent contractor in interpreting the contract documents; plaintiff must have reasonably relied on the indications of subsurface conditions in the contract; the subsurface conditions actually encountered must have differed materially from those indicated in the contract; the actual subsurface conditions encountered must have been reasonably unforeseeable; and plaintiff’s claimed damages, excess costs associated with extra work and delays allegedly incurred as a result of the unforeseen need to use steel ribbing for temporary support of the tunnel during excavation, must have been solely attributable to such materially different subsurface conditions (see, Stuyvesant Dredging Co. v United States, 834 F2d 1576, 1581, affg 11 Cl Ct 853, 858; Weeks Dredging & Contr. v United States, 13 Cl Ct 193, 218-244, affd 861 F2d 728). The court found that the conditions actually encountered did not differ materially from those indicated in the contract documents, and that the conditions actually encountered were not reasonably unforeseeable. The issue thus is whether the court erred in finding that plaintiff failed to prove those elements by a preponderance of the evidence (Stuyvesant Dredging Co. v United States, supra; Weeks Dredging & Contr. v United States, supra).

Plaintiff’s primary argument is that the court failed to take into account the concession by defendant’s expert, Flanagan, that DSCs existed at least to a limited extent. Plaintiff contends that such testimony, in combination with the testimony of plaintiff’s experts, eliminated any factual question or issue of credibility and compelled a finding that there were DSCs. Plaintiff’s argument ignores the fact that the existence of DSCs is fundamentally a legal judgment, i.e., a question of contract interpretation, not an engineering judgment (Maffei Bldg. Wrecking Corp. v United States, 732 F2d 913, 915-916; Weeks Dredging & Contr. v United States, supra, at 218). The existence of DSCs depends upon a comparison of the site conditions actually encountered with the affirmative representations of ground conditions contained in the bid and contract [227]*227documents (Foster Constr. C. A. & Williams Bros. Co. v United States, 435 F2d 873, 881; Weeks Dredging & Contr. v United States, supra, at 219). "[T]o the extent [that] the conditions described in the contract materialize, the contractor bears the risk, while the government assumes the risks for conditions [that] the contract documents fail to disclose” (Erickson-Shaver Contr. Corp. v United States, 9 Cl Ct 302, 304). The contract is controlling and the expert witnesses were not "experts” in contract interpretation. Indeed, the court was bound to disregard the expert testimony where it was contradicted by the contract and bid documents and unsupported by the facts concerning the conditions unearthed during the work (Weeks Dredging & Contr. v United States, supra, at 218).

Examining the bid and contract documents in their entirety, we conclude that they accurately represented the subsurface conditions actually encountered. More importantly, they adequately put plaintiff on notice of the possible need to employ steel ribbing as temporary support in portions of the excavation. The Engineering Design Rationale (EDR) indicated that rock quality generally would be "average to good” for tunneling, but warned of the existence of localized areas of poor rock quality, opened, weathered, and in some cases "solutioned” fractures, and intersecting vertical and horizontal joints.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tutor Perini Corp. v. State Univ. Constr. Fund
2025 NY Slip Op 52062(U) (New York Supreme Court, Albany County, 2025)
Resetarits Constr. Corp. v. Norfolk S. Ry. Co.
2024 NY Slip Op 04019 (Appellate Division of the Supreme Court of New York, 2024)
Matter of Prismatic Dev. Corp. v. New York City Tr. Auth.
2021 NY Slip Op 07072 (Appellate Division of the Supreme Court of New York, 2021)
Loughlin v. Meghji
2020 NY Slip Op 05196 (Appellate Division of the Supreme Court of New York, 2020)
Angiolillo v. Christie's, Inc.
2020 NY Slip Op 3848 (Appellate Division of the Supreme Court of New York, 2020)
CGM Construction, Inc. v. Sydor
144 A.D.3d 1434 (Appellate Division of the Supreme Court of New York, 2016)
HAYWARD BAKER, INC. v. C.O. FALTER CONSTRUCTION CORP.
104 A.D.3d 1253 (Appellate Division of the Supreme Court of New York, 2013)
Huff v. Rodriguez
64 A.D.3d 1221 (Appellate Division of the Supreme Court of New York, 2009)
Paragon Restoration Group, Inc. v. Cambridge Square Condominiums
42 A.D.3d 905 (Appellate Division of the Supreme Court of New York, 2007)
Niagara County ex rel. Niagara County Water District v. R&D Engineering, P.C.
298 A.D.2d 971 (Appellate Division of the Supreme Court of New York, 2002)
Graham Construction & Maintenance Corp. v. Village of Gouverneur
229 A.D.2d 815 (Appellate Division of the Supreme Court of New York, 1996)
Tishman Construction Corp. v. City of New York
228 A.D.2d 292 (Appellate Division of the Supreme Court of New York, 1996)
A. Beecher Greenman Construction Corp. v. Long Island Rail Road
202 A.D.2d 614 (Appellate Division of the Supreme Court of New York, 1994)
Niagara Frontier Transportation Authority v. Gibbs
202 A.D.2d 964 (Appellate Division of the Supreme Court of New York, 1994)
Reliance Insurance v. County of Monroe
198 A.D.2d 871 (Appellate Division of the Supreme Court of New York, 1993)
Fruin-Colnon Corp. v. Niagara Frontier Transportation Authority
184 A.D.2d 1000 (Appellate Division of the Supreme Court of New York, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
180 A.D.2d 222, 585 N.Y.S.2d 248, 1992 N.Y. App. Div. LEXIS 8218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fruin-colnon-corp-traylor-bros-v-niagara-frontier-transportation-nyappdiv-1992.