Graham Construction & Maintenance Corp. v. Village of Gouverneur

229 A.D.2d 815, 646 N.Y.S.2d 720, 1996 N.Y. App. Div. LEXIS 7963

This text of 229 A.D.2d 815 (Graham Construction & Maintenance Corp. v. Village of Gouverneur) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Graham Construction & Maintenance Corp. v. Village of Gouverneur, 229 A.D.2d 815, 646 N.Y.S.2d 720, 1996 N.Y. App. Div. LEXIS 7963 (N.Y. Ct. App. 1996).

Opinion

Cardona, P. J.

Cross appeals from an order of the Supreme Court (Demarest, J.), entered March 23, 1995 in St. Lawrence County, which denied motions by plaintiff and third-party defendant for summary judgment and partially granted defendant’s cross motion for summary judgment and dismissed the first cause of action.

This dispute originates with a contract entered into between plaintiff and defendant dated July 19,1988. The contract called for plaintiff to install certain sewer improvements for defendant. Plaintiff commenced work on or about August 1, 1988. Shortly thereafter, however, plaintiff allegedly encountered running water and unstable subsoil conditions which it claimed were unanticipated and could not have been discovered until the commencement of construction. Under the terms of the contract, if plaintiff encountered subsurface conditions "materially differing from those shown on the Plans” it was required to "immediately give notice” to the engineer for the project. If, upon investigation, the engineer agreed that there were such conditions, it would issue a change in the plans and any increase in the cost resulting therefrom. Accordingly, by letter dated October 5, 1988, plaintiff’s counsel notified the engineers for the project, O’Brien & Gere Engineers, Inc. (hereinafter OBG), that plaintiff had ceased working on the project because of the subsurface conditions. The letter also stated that test results both in areas encountered by plaintiff as well as those that plaintiff had not yet reached revealed unanticipated subsurface conditions. OBG responded by directing plaintiff to continue working. Instead, by letter dated October 25, 1988, plaintiff’s counsel informed OBG, inter alia, that it was claim[816]*816ing $299,678.46 for costs incurred due to the differing site conditions.

OBG hired Mueser Rutledge Consulting Engineers to review plaintiff’s studies. Mueser compared the subsurface investigations done by OBG and those done for plaintiff. Both OBG’s and plaintiff’s studies involved drilling holes into the ground (borings) and compiling data as a result of those tests. In a letter dated November 23,1988, Mueser concluded that both studies "generally showed similar subsurface materials” and that plaintiff’s construction difficulties were primarily caused by "insufficient groundwater lowering”. Mueser’s letter addressed plaintiff’s contentions concerning both the conditions it had already encountered (hereinafter claim No. 1) and those that it would encounter (hereinafter claim No. 2). With respect to claim No. 2, plaintiff’s October 5, 1988 letter to OBG indicated that there was an "aquifer flow” present that would require a redesign of the remaining portion of the project.1 In reference to the presence of an aquifer, Mueser’s November 23, 1988 letter stated that it could not verify its presence but that if it existed it would be a "changed condition”. The letter also pointed out that the reported artesian condition was 600 to 1,600 feet east of where plaintiff had been working and recommended further investigation.

Based on Mueser’s letter, OBG informed plaintiff that defendant was rejecting claim No. 1, stating that the conditions plaintiff encountered should have been anticipated because the borings studies made available to plaintiff prior to entering into the contract described the subsurface conditions encountered by plaintiff. By letter dated January 14, 1989, plaintiff’s counsel informed OBG that it considered defendant in breach of the contract for failure to make payment pursuant to the contract’s terms.

Thereafter, at a January 16, 1989 meeting, defendant authorized OBG to proceed with further soil borings as recommended by Mueser and agreed to delay giving plaintiff notice to proceed with the rest of the project until the new soil borings were done. Defendant also agreed to pay plaintiff’s progress pay[817]*817ment requisition No. 2 and delay payment of requisition No. 3 for materials stored on site, pending review by OBG.

After conducting its own borings tests, Mueser informed OBG, by letter dated March 10, 1989, that there was no evidence to support claim No. 1 but that "dewatering” and depressurizing would be required in part of the area where plaintiff would be working and "should be viewed as extra to the contract”. OBG ordered plaintiff back to work. Plaintiff refused and, on May 31, 1989, filed a notice of claim seeking damages in the amount of $299,678.46 and subsequently commenced this action seeking the same amount. In its first cause of action for breach of contract, plaintiff alleged that the site conditions were "cardinal” changes and outside the scope of the parties’ agreement. The second cause of action also claimed that defendant breached the contract by not paying plaintiff. Defendant answered and counterclaimed for, inter alia, breach of contract and negligent performance of the contract.2

Plaintiff moved for summary judgment, requesting damages for the first time in the amount of $509,687.46. Defendant cross-moved for summary judgment against plaintiff. Supreme Court denied plaintiff’s motion in its entirety and partially granted defendant’s cross motion with respect to plaintiff’s first cause of action. The parties have cross-appealed.3

In properly denying plaintiff’s motion, Supreme Court initially determined that plaintiff’s first cause of action was based only on claim No. 1 for work already completed because the complaint and documents submitted failed to assert a claim as to claim No. 2 regarding work to be done in the future. The evidence does not support the contention that the October 5, 1988 and October 25, 1988 letters provided notice to defendant that plaintiff was claiming damages based on future work, as well as work already done. Although the October 5, 1988 letter stated that subsoil conditions "will be encountered * * * throughout the remaining project course”, no specific claim was made and the October 25, 1988 letter stated that defendant was to treat the letter "as a claim for $299,678.46 for costs incurred for differing site conditions” (emphasis supplied). [818]*818Plaintiffs complaint stated only that plaintiff was entitled to all costs "expended on the PROJECT of $299,678.46” (emphasis supplied). Likewise, its notice of claim sought the same amount for costs "incurred”. It was not until plaintiffs motion for summary judgment that it claimed damages in excess of that amount. No amendment to the complaint was ever sought.

We also note that, prior to plaintiffs commencing this action, defendant never actually rejected plaintiffs assertions as to claim No. 2. In fact, Mueser’s March 10, 1989 letter specifically concluded that the remaining work in part of the unexcavated area was to be viewed as extra to the contract. The only claim rejected by defendant was claim No. 1. Given these circumstances and the record before us, we cannot say that Supreme Court erred in determining that plaintiffs claim was limited to recovering expenditures only for the work it had already performed.

The next question is whether Supreme Court properly determined that, because the conditions encountered by plaintiff before it stopped working did not materially differ from those indicated in the contract, plaintiff failed to establish its first cause of action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fruin-Colnon Corp., Traylor Bros. v. Niagara Frontier Transportation Authority
180 A.D.2d 222 (Appellate Division of the Supreme Court of New York, 1992)
Reliance Insurance v. County of Monroe
198 A.D.2d 871 (Appellate Division of the Supreme Court of New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
229 A.D.2d 815, 646 N.Y.S.2d 720, 1996 N.Y. App. Div. LEXIS 7963, Counsel Stack Legal Research, https://law.counselstack.com/opinion/graham-construction-maintenance-corp-v-village-of-gouverneur-nyappdiv-1996.