Walsh Construction Company

CourtUnited States Court of Federal Claims
DecidedOctober 3, 2018
Docket16-845
StatusPublished

This text of Walsh Construction Company (Walsh Construction Company) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walsh Construction Company, (uscfc 2018).

Opinion

In the United States Court of Federal Claims No. 16-845 C Filed: October 3, 2018 **************************************** * 28 U.S.C. § 1491 (Tucker Act WALSH CONSTRUCTION CO., et al., * Jurisdiction); * 41 U.S.C. §§ 7101-7109 (Contracts Plaintiffs, * Dispute Act); * 48 C.F.R. §§ 52.233–1 (Federal v. * Acquisition Regulation, Disputes), * 52.236-2 (Federal Acquisition THE UNITED STATES, * Regulation, Differing Site * Conditions); Defendant. * Good Faith And Fair Dealing. * ****************************************

Richard David Kalson, Benesch Friedlander, Coplan & Aronoff LLP, Counsel for Plaintiffs.

Igor Helman, United States Department of Justice, Civil Division, Washington, D.C., Counsel for the Government.

MEMORANDUM OPINION AND FINAL ORDER BRADEN, Senior Judge.

To facilitate review of this Memoranda Opinion And Final Order regarding the duty of good faith and fair dealing and differing site condition allegations set forth in a February 13, 2017 Amended Complaint, the court has provided the following outline.

I. FACTUAL BACKGROUND. A. On November 23, 2011, The United States Army Corps Of Engineers Issued Solicitation No. W912DR-12-R-0001 To Request Proposals For A Firm, Fixed- Price Contract To Build A Defense Logistics Agency Facility In New Cumberland, Pennsylvania. B. On August 17, 2012, The United States Army Corps Of Engineers Awarded Contract No. W912DR-12-C-0011 To Walsh Construction Company. C. In January 2013, Walsh Construction Company Conducted Rock Coring To Enable The Army Corps To Set Preliminary Tip Elevations. D. In February 2013, Richard Goettle, Inc. Began Drilling Shafts, But Experienced Significant Problems. 1. Caving And Water Problems Occurred At “Five Problem Shafts.” 2. Approximately Ninety Other Drilled Piers Failed Inspection. E. On November 30, 2015, Walsh Construction Company Submitted A Request For Equitable Adjustment To The United States Army Corps Of Engineers, On Behalf Of Richard Goettle, Inc. F. On April 18, 2016, The Contracting Officer Issued A Final Decision Denying Walsh Construction Company’s November 30, 2015 Request For Equitable Adjustment. II. PROCEDURAL HISTORY. III. DISCUSSION. A. Subject Matter Jurisdiction. B. Standing. C. Whether Plaintiffs Met Their Burden Of Proof, At Trial, To Establish The Allegations In The February 13, 2017 Amended Complaint. 1. Whether The Government Violated The Duty Of Good Faith And Fair Dealing, Thereby Breaching The Contract (Counts One and Two). 2. Whether Plaintiffs Are Entitled To Recover Costs For A Differing Site Condition At The Defense Logistics Agency Headquarters Site (Count Three). IV. CONCLUSION.

I. FACTUAL BACKGROUND.1

A. On November 23, 2011, The United States Army Corps Of Engineers Issued Solicitation No. W912DR-12-R-0001 To Request Proposals For A Firm, Fixed-Price Contract To Build A Defense Logistics Agency Facility In New Cumberland, Pennsylvania.

On November 23, 2011, the United States Army Corps of Engineers (the “Army Corps”) issued Request for Proposals No. W912DR-12-R-0001 (the “Solicitation”) for offers to construct a Defense Logistics Agency (the “DLA”) facility at the Defense Distribution Depot Susquehanna, Pennsylvania (the “DDSP”), a large military facility in New Cumberland, Pennsylvania (the “Project”). DX 124 at 2. The Project site was located on the northern portion of the DDSP, close to the Susquehanna River shoreline. JX 51 at 1.

1 The facts discussed herein are derived from evidence adduced at a trial held on March 19–20, 22, and April 4, 2018, in Washington, D.C. (TR 1–1143), together with the parties’ Joint Stipulations of Fact (Jt. Stip. ¶¶ 1–21). The witnesses for each party are identified in Court Exhibit A. At trial, the court admitted into evidence: Plaintiffs’ Exhibits (PX 1–275); Government’s Exhibits (DX 1-178); Government’s demonstratives (DDX 1–3); and 70 Joint Exhibits (JX 1–70). See TR 8, 9, 76, 104, 274, 829–30.

2 On December 12, 2011, the Army Corps prepared a Final Geotechnical Report for the Project site that was included as an amendment to the Solicitation, showing a fault line that runs through the DDSP. JX 51 at 4–5. The subsurface on one side of the fault line was comprised of siltstone or claystone; the subsurface on the other side, i.e., where the Project site was located, was comprised of “Epler Formation limestone[2 that] forms a subsurface karst terrain that is typical of the soluble carbonate rock response to weathering and erosion.” JX 51 at 5; TR 677–78 (Tucker) (“But here we have a fault line that runs through New Cumberland, and what that does is basically separates two geologies. You have the one thrust plate, where our project is, which has the limestone, and then the southern part, where – the other portion of the project does not have limestone.”); TR 780 (Garrett) (“[T]his one was limestone, and that rock is claystone/siltstone, a different type of geology.”). The Final Geotechnical Report described the limestone as “a light gray, hard, massive . . . bedrock,” that was “typically slightly weathered, highly to moderately fractured, and very hard[,]” as well as “pinnacled.”3 JX 51 at 5-6.

The Final Geotechnical Report also reflected that “[c]oncrete drilled piers[4] extending into the Epler limestone are required for support of the column loads of the [DLA] building.” JX 51 at 15. Therefore, the Solicitation, as amended, required the contractor to “install special deep foundations” for drilled piers ranging from thirty to seventy-two inches in diameter. DX 124 at 6–9, 13. The drilled piers support the building solely by side-shear resistance5 at the rock socket,6

2 “Epler limestone,” or “karst limestone,” is a type of rock composed of “calcium carbonate,” that upon reacting with water “creates pinnacles and voids and things like that [within the rock].” TR 674 (Tucker). 3 “Pinnacled” describes a rock surface of varying elevations, i.e., one that is “up and down all over the place.” TR 682 (Tucker); see also TR 778 (Garrett) (“[B]ecause this is this pinnacled, kind of unpredictable rock formation, I would not have extrapolated directly between borings[.]”). 4 Drilled piers are a type of deep foundation system where concrete cylinders of varying diameters are constructed by “excavating a hole, typically 3 to 12 feet in diameter, inspecting the soil or rock in to which the foundation is formed, and constructing a cast-in-place reinforced concrete foundation within the hole.” DX 111 at 1–3. 5 Side-shear resistance results when concrete is poured into the drilled shafts, and a section at the bottom of the concrete adheres to the sides of the rock surrounding the shaft, as the concrete is poured. See TR 681 (Tucker) (defining “shear” as “the bond between the concrete and the rock. . . . The she[a]r is in the sides.”). Side-shear resistance differs from base resistance, where the base of the drilled pier bears the load. DX 111 at 1–3; see also TR 681 (Tucker) (affirming that “the weight is being held by the sides of the rock rather than just resting on the bottom”). 6 A rock socket is a section of the drilled pier adhering to the surrounding rock that bears the building load. See TR 681 (Tucker).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Warth v. Seldin
422 U.S. 490 (Supreme Court, 1975)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Anderson v. United States
344 F.3d 1343 (Federal Circuit, 2003)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Walsh Construction Co. v. United States
132 Fed. Cl. 282 (Federal Claims, 2017)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
Fru-Con Construction Corp. v. United States
43 Cont. Cas. Fed. 77,449 (Federal Claims, 1999)
Severin v. United States
99 Ct. Cl. 435 (Court of Claims, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
Walsh Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walsh-construction-company-uscfc-2018.