Tidewater, Inc.

CourtArmed Services Board of Contract Appeals
DecidedNovember 2, 2018
DocketASBCA No. 61076
StatusPublished

This text of Tidewater, Inc. (Tidewater, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tidewater, Inc., (asbca 2018).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Tidewater, Inc. ) ASBCA No. 61076 ) Under Contract No. W9126G-09-D-Ol l l )

APPEARANCES FOR THE APPELLANT: Elizabeth Haws Connally, Esq. Connally Law, PLLC San Antonio, TX

William W. Sommers, Esq. Langley & Banack, Inc. San Antonio, TX

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney S. DeAnn Lehigh, Esq. Michael T. Geiselhart, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Little Rock

OPINION BY ADMINISTRATIVE JUDGE YOUNGER ON THE GOVERNMENT'S MOTION FOR SUMMARY JUDGMENT

The United States Army Corps of Engineers (the Corps) has moved for summary judgment in this appeal, in which appellant Tidewater, Inc. (Tidewater) asserts that it encountered a Type I differing site condition. In particular, Tidewater alleges that soil conditions when it sought to install piers, and to obtain fill, for a building addition differed materially from those indicated in contract documents due to excessive rainfall, forcing it to change its construction method and incur additional performance time. The Corps argues that Tidewater has failed to allege essential elements of a Type I differing site condition, including the element of identification of the contract indications that form the basis of its claim. We grant the motion and deny the appeal.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

1. By date of September 30, 2009, the Corps awarded Tidewater Contract No. W9126G-09-D-Ol l l (the base contract), a multiple award, indefinite-delivery, indefinite-quantity, task order contract under which awardees were to provide all labor and equipment for repairs, alterations, construction and design-build of healthcare facilities for the U.S. Air Force Medical Services, U.S. Army Medical Command and other Corps of Engineers' customers with healthcare needs (R4, tab 4 at 2-3 of 37).

2. The contract contained various standard clauses, including Federal Acquisition Regulation (FAR) 52.236-2, DIFFERING SITE CONDITIONS (APR 1984 ); FAR 52.236-3, SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984); and FAR 52.243-4, CHANGES (JUN 2007) (R4, tab 4 at 13 of 27).

3. By date of July 27, 2012, the Corps issued Request for Proposal (RFP) No. W9126G-12-U-1016-0001 to Tidewater and other awardees, seeking proposals relating to a task order for the Barksdale Dental Clinic Project, to "create a complete and usable facility" ( app. supp. R4, tab 1 at l ). The RFP included Attachment G, "Site Surveys, Geotechnical Reports & Fill Material," which states in part: "The Contractor shall be responsible for providing all site surveys, geotechnical data, and fill material required for constntction and or utility installation. This includes obtaining all necessary permits and soil testing. Any existing surveys provided are for information only (FIO)." (Id at 51) In section 2.5, "Regional Setting,'' the RFP described the soils as composed of alluvial deposits of clay, silt and sand with varying bearing capacity. Section 2.5 also provided that "water table elevation is often high." (Id at 768)

4. It is undisputed that Tidewater participated in site visits on July 23, 2012, and August 10, 2012 ( compl. and answer ,r 13 ).

5. By date of August 16, 2012, the Corps issued Amendment No. 0003 to the RFP, requesting contractors to respond with proposals to "create a complete and usable facility" for the dental unit that would occupy the designated space ( app. supp. R4, tab 1 at 1307). The Corps stated that "[t]he magnitude of this requirement is estimated over $5,000,000.00" (id.).

6. The amendment included Design Compatibility Guidelines promulgated by the Air Force for work performed at Barksdale Air Force Base. The guidelines added that a ·'geotechnical report including ... design recommendations by a qualified geotechnical engineer is required." (App. supp. R4, tab 1 at 768) The guidelines also advised contractors that "[r]ainfall averages 46.6 inches annually, with the greatest monthly rainfall occurring in spring" (id. at 769).

7. Effective September 30, 2012, the Corps awarded Tidewater Task Order No. 0002, which gave rise to the present dispute. Under Task Order No. 0002, Tidewater was to renovate Building 4666 at Barksdale Air Force Base, Louisiana, over a performance period of 730 calendar days. (R4, tab 5 at 141-42, 146-47)

f 8. By date of December 20, 2012, the contracting officer issued Modification No. 02 to exercise Option 3 under the task order contract for the construction of an addition to Building 4666 (R4, tab 6 at 1-2).

9. By date of February 25, 2013, Professional Service Industries, Inc. (PSI), Tidewater's geotechnical engineering consultant, furnished its report to Tidewater, which the parties have referred to as the Geo Report. While Tidewater alleges that it ''became a contract-related document" (comp I. 1 44 ), we find that the Geo Report was not a contract document, but was commissioned by Tidewater consistent with Attachment G of the RFP (see statement 3 ). We further find that the report was addressed to Tidewater and the record contains no evidence that the Corps endorsed the report's contents. In pertinent part, PSI stated in the Geo Report that

Groundwater was observed at 19 feet in boring B-1 on completion of the borings [in February 2013]. Groundwater may be present at different depths during other times of the year depending upon drainage pattern alterations, climatic and rainfall conditions. PSI recommends the contractor determine the current groundwater depth at the time of construction.

(R4, tab 3C at 21, 30) PSI also stated that "groundwater levels may require dewatering operations be performed to allow drilled shaft construction or the shafts may have to be installed by slurry drilling methods" (id at 23). PSI further recommended that Tidewater's contractor "determine the actual groundwater levels at the site at the time of construction to assess the impact groundwater may have on construction" (id. at 25).

10. By letter to Tidewater dated May 9, 2013, the Corps suspended work because ''insufficient project funds [were] immediately available" (R4, tab 10 at 392-93). Approximately seven months later, by letter to Tidewater dated December 11, 2013, the administrative contracting officer stated that, "[e]ffective with the signing of Modification No. 06 by the Contracting Officer, the directed suspension of work was lifted and work shall again proceed" (id. at 394).

11. It is undisputed that, as approved by the Corps, Tidewater's final design for the construction of the addition to Building 4666 included use of straight shaft concrete piers for the foundation (compl. and answer 120).

12. By letter to the administrative contracting officer dated June 17, 2015, Tidewater gave notice of a differing site condition, which it described as follows:

I During the pier drilling activity conducted on June 9, 2015 it was discovered that the water table has risen drastically since our initial investigation which was conducted in 2013. This initial investigation encountered groundwater approximately 20 feet below the surface. Currently, the groundwater level is at approximately 9 feet below the surface.

(R4, tab 3i at 90)

13. By letter to Tidewater dated July 7, 2015, the administrative contracting officer responded, disagreeing that Tidewater had encountered a differing site condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
CONNER BROS. CONST. CO., INC. v. Geren
550 F.3d 1368 (Federal Circuit, 2008)
Pacific Alaska Contractors, Inc. v. The United States
436 F.2d 461 (Court of Claims, 1971)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Olympus Corporation v. United States
98 F.3d 1314 (Federal Circuit, 1996)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Baldi Bros. Constructors v. United States
50 Fed. Cl. 74 (Federal Claims, 2001)
McDevitt Mechanical Contractors, Inc. v. United States
36 Cont. Cas. Fed. 75,954 (Court of Claims, 1990)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
Tidewater, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tidewater-inc-asbca-2018.