McDevitt Mechanical Contractors, Inc. v. United States

36 Cont. Cas. Fed. 75,954, 21 Cl. Ct. 616, 1990 U.S. Claims LEXIS 401, 1990 WL 162233
CourtUnited States Court of Claims
DecidedOctober 23, 1990
DocketNo. 531-88C
StatusPublished
Cited by5 cases

This text of 36 Cont. Cas. Fed. 75,954 (McDevitt Mechanical Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDevitt Mechanical Contractors, Inc. v. United States, 36 Cont. Cas. Fed. 75,954, 21 Cl. Ct. 616, 1990 U.S. Claims LEXIS 401, 1990 WL 162233 (cc 1990).

Opinion

OPINION

MEROW, Judge.

This action is before the court on defendant’s motion for summary judgment. It is based upon an express contract between plaintiff and the United States and has been brought pursuant to 41 U.S.C. § 609(a)(1) and 28 U.S.C. § 1491(a)(1). Plaintiff, McDevitt Mechanical Contractors, Inc. (McDevitt), seeks an equitable adjustment in contract price because defendant, National Aeronautics and Space Administration (NASA), allegedly changed the terms of their contract, and because McDevitt allegedly encountered differing site conditions. NASA counters that McDevitt’s claims are not valid; that there is no genuine issue as to any material fact; and, therefore, that those claims should be summarily dismissed. For the following reasons, defendant’s motion for summary judgment will be granted.

Factual Background

On June 15, 1984, McDevitt entered into a contract with NASA to modify the Small Engine Componenfs Facility in test cells CE-17 and CE-18 at the Lewis Research Center in Cleveland, Ohio. The contract required that McDevitt furnish and install one motor-driven, single-span, underhung bridge crane in Test Cell CE-18. On April 23, 1986, McDevitt submitted a claim to NASA in the amount of $208,205 for added costs due to errors and delays allegedly made by the government. NASA responded to that claim in September, 1987 by approving certain items and by rejecting others. McDevitt’s complaint in this suit relates to Items 1 and 2 of Section V of that claim.

In Item 1, McDevitt seeks reimbursement in the amount of $1,488.30 for paying the electrical subcontractor to install the power wiring to the crane. Plaintiff argues that this electrification was not included in the contract. Compensation for Item 1 was denied by the contracting officer because “the electrical power wiring for the crane is explicitly specified in * * * Section 14380 * * * of the contract.” Accordingly, the subcontractor’s quote should have included the cost for electrification at the time of bidding.

McDevitt seeks in Item 2 an upward adjustment in price for the labor and materials expended when it encountered a differ[618]*618ing site condition in the form of an elevation discrepancy. Specifically, the 36" diameter stainless steel inlet pipe in CE-18 required shortening by IV2" because the flange on the horizontal pipe interfered with the overhead crane. This modification took two men three weeks to build an angle frame supporting a 36" elbow, to remove the IV2" length, and to reweld the pipe support. NASA’s contracting officer also rejected this item. She stated that installation of the inlet pipe in accordance with the specifications was strictly McDevitt’s responsibility, the problems were not due to differing site conditions, and could have been avoided if plaintiff had made the required verification of field measurements.

Discussion

Disposition by summary judgment is appropriate when there is no genuine dispute as to any material fact and when the movant is entitled to judgment as a matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). By isolating and disposing of factually unsupported claims or defenses, the procedure is designed to save time and expense, thereby achieving judicial economy. Celotex Corp. v. Catrett, 477 U.S. 317, 323-24, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986). To defeat a motion for summary judgment, the nonmovant must provide sufficient evidence that a genuine issue for trial does exist. Celotex Corp. v. Catrett, 477 U.S. 317, 324, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986).

In its first claim, McDevitt argues that there is a genuine issue as to whether the contract placed the responsibility of electrifying the crane on the prime contractor. Plaintiff alleges that the contract is ambiguous and that the intent of the parties is not clear because the specifications do not contain express language directing anyone to install the power wiring for the crane. McDevitt then draws attention to Oil Trading Associates, Inc. v. Texas City Refining, Inc., 201 F.Supp. 846 (D.C.N.Y.1962) (citing Severson v. Fleck, 251 F.2d 920 (8th Cir.1958)), which held that summary judgment is not appropriate when a written agreement is ambiguous and the intent of the parties is in dispute.

It is well established that contract interpretation is a matter of law, and that a primary function of the court is to determine the parties’ intent. Dynamics Corp. of America v. United States, 182 Ct.Cl. 62, 72, 389 F.2d 424, 429 (1968). To determine intent, the court should look to the written instrument, ITT Arctic Services, Inc. v. United States, 207 Ct.Cl. 743, 751, 524 F.2d 680, 684 (1975), giving reasonable meaning to all its portions. Martin Lane Co. v. United States, 193 Ct.Cl. 203, 215, 432 F.2d 1013, 1019 (1970). Furthermore, “a [cjourt should ascribe to the contract language ‘its ordinary and commonly accepted meaning,’ without twisted or strained analysis.” Industrial Indem. Co. v. United States, 14 Cl.Ct. 351, 356 (1988) (citing Hol-Gar Mfg. Corp. v. United States, 169 Ct.Cl. 384, 390, 351 F.2d 972, 976 (1965), and Aero Mayflower Transit Co. v. United States, 162 Ct.Cl. 233 (1963)).

Plaintiff maintains that the contract language referred to by NASA in this action detailed what products were to be used and what pre-electrification tests were to be performed, but did not direct anyone to do the actual electrification. However, plaintiff ignores certain portions of the contract specifications. Specifically, Subpart 1.2.1.3 of Section 01090 required McDevitt to “furnish and install” one motor-driven, single-span, underhung 4 ton bridge crane. The scope of the terms “provide,” “furnish” and “install” are set forth in Section 01090, Part 1, Subpart 1.2, and mean “to supply and deliver to the project site, and install, comylete and ready for the intended use." (Emphasis added.) In addition, Section 14380, Part 3, Subpart 3.6, stated that, “[ajfter the completed crane complex is erected, adjusted, lubricated, and made ready for oyeration, it shall be tested in the presence of the Contracting Officer.” (Emphasis added.) In essence, McDevitt is correct only to the extent that the specifications do not contain language expressly stating that the prime contractor is responsible for the electrification of the crane. Plaintiff is responsible for installing the [619]*619crane, complete and ready for the intended use, and for making it ready for operation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tidewater, Inc.
Armed Services Board of Contract Appeals, 2018
P.R. Burke Corp. v. United States
47 Fed. Cl. 340 (Federal Claims, 2000)
Weston Services, Inc. v. Halliburton Nus Environmental Corp.
839 F. Supp. 1144 (E.D. Pennsylvania, 1993)
Western States Construction Co. v. United States
38 Cont. Cas. Fed. 76,376 (Court of Claims, 1992)
C. Sanchez & Son, Inc. v. United States
37 Cont. Cas. Fed. 76,152 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,954, 21 Cl. Ct. 616, 1990 U.S. Claims LEXIS 401, 1990 WL 162233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdevitt-mechanical-contractors-inc-v-united-states-cc-1990.