U.S. Army Corps of Engineers v. John C. Grimberg Co., Inc.

CourtCourt of Appeals for the Federal Circuit
DecidedJune 9, 2020
Docket19-1608
StatusUnpublished

This text of U.S. Army Corps of Engineers v. John C. Grimberg Co., Inc. (U.S. Army Corps of Engineers v. John C. Grimberg Co., Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. Army Corps of Engineers v. John C. Grimberg Co., Inc., (Fed. Cir. 2020).

Opinion

Case: 19-1608 Document: 59 Page: 1 Filed: 06/09/2020

NOTE: This disposition is nonprecedential.

United States Court of Appeals for the Federal Circuit ______________________

UNITED STATES ARMY CORPS OF ENGINEERS, Appellant

v.

JOHN C. GRIMBERG CO., INC., Appellee ______________________

2019-1608 ______________________

Appeal from the Armed Services Board of Contract Ap- peals in Nos. 58791, 59167, 59168, 59169, 59170, 59171, 59717, Administrative Judge J. Reid Prouty, Administra- tive Judge Richard Shackleford, Administrative Judge Robert T. Peacock. ______________________

Decided: June 9, 2020 ______________________

ALBERT S. IAROSSI, Commercial Litigation Branch, Civil Division, United States Department of Justice, Wash- ington, DC, argued for appellant. Also represented by JOSEPH H. HUNT, ALLISON KIDD-MILLER, ROBERT EDWARD KIRSCHMAN, JR.; SCOTT SEUFERT, United States Army Corps of Engineers, Baltimore, MD.

HERMAN MARTIN BRAUDE, Braude Law Group, P.C., Case: 19-1608 Document: 59 Page: 2 Filed: 06/09/2020

2 U.S. ARMY CORPS OF ENG’RS v. JOHN C. GRIMBERG CO.

Rockville, MD, argued for appellee. Also represented by EDWARD JEROME PARROTT, Watt, Tieder, Hoffar & Fitzger- ald, McLean, VA. ______________________

Before O’MALLEY, WALLACH, and TARANTO, Circuit Judges. O’MALLEY, Circuit Judge. The United States Army Corps of Engineers (“Corps”) appeals a decision of the Armed Services Board of Contract Appeals (“Board”) holding that John C. Grimberg Co., Inc. (“Grimberg”) is entitled to an equitable adjustment to the contract price for construction of the Navy Medical Biolog- ical Defense Research Laboratory (“Biolab”) in Fort Detrick, Maryland. John C. Grimberg Co., ASBCA Nos. 58791, 59167, 59168, 59169, 59170, 59171, 59717, 18-1 BCA ¶ 37,191. While we understand the Board’s desire to reach a conclusion it felt was not unjust in the circum- stances, for the reasons discussed below, we must reverse. I. BACKGROUND The Corps issued a Request for Proposal (“RFP”) on February 23, 2009, seeking offers for the design and con- struction of the Biolab. The project entailed construction of a large laboratory building, an entry point building, parking facilities, an access road, stormwater manage- ment, and perimeter fencing. The RFP incorporated by ref- erence the standard differing site condition (“DSC”) clause, as prescribed by 48 C.F.R. § 52.236-2, pursuant to which a contractor can ask for a cost adjustment if subsurface con- ditions at the construction site “differ materially from those indicated in the contract.” The RFP also included, as an appendix, the “Geotech- nical Report and Requirements” (“Geotechnical Report”). J.A. 4248–4423. The Geotechnical Report, although “pre- liminary” was meant to provide “bidders with sufficient Case: 19-1608 Document: 59 Page: 3 Filed: 06/09/2020

U.S. ARMY CORPS OF ENG’RS v. JOHN C. GRIMBERG CO. 3

information to identify the general subsurface conditions of the site.” J.A. 4249. The Geotechnical Report stated that the Biolab should be supported by a deep foundation sys- tem of drilled piers (i.e., caissons or shafts) socketed into five feet of competent rock. J.A. 4256. The portion of the pier embedded in rock is called a “rock socket.” To assist contractors in developing bids for the Biolab’s foundation, the Geotechnical Report disclosed 46 test bor- ings to indicate the subsurface conditions at the project lo- cation. Eleven of the borings came from an investigation done during the construction of the National Interagency Bio-Defense Campus, of which the Biolab is a part. Just two of those borings, DH-11 and DH-12, were located within the planned footprint for the Biolab. Those two bor- ings indicated high quality rock, with no intervening in- competent rock. The Geotechnical Report indicated, however, that contractors should not assume that the rock at the site would be free of voids given the information available from other borings. For example, certain borings taken between 300 and 500 feet from the Biolab footprint, in preparation for a different construction project, showed between 0 and 20 feet of incompetent rock. Notably, the bedrock below the Biolab project, like the surrounding area, is limestone in a Karst formation. Karst geology is a condition of limestone rock that occurs when portions of the rock have been degraded over time by a Karst solutioning process. This process can create large cracks, fissures, and voids in the rock. As the Board ex- plained, “Karst is a recognized geohazard, ‘[k]nown for its variability and its degree of inconsistency, both vertically and horizontally over extremely short distances.’” J.A. 2. In response to the Corps’ RFP, Grimberg submitted a proposal on March 31, 2009. Grimberg estimated that it would need to drill through 240 feet of rock (exactly 5 feet for each of 48 piers), at between $270 and $530 per foot, depending on the depth of the pier. This quote relied on Case: 19-1608 Document: 59 Page: 4 Filed: 06/09/2020

4 U.S. ARMY CORPS OF ENG’RS v. JOHN C. GRIMBERG CO.

the testing results from DH-11 and DH-12, and assumed that excavation of incompetent rock would not be required as part of the construction. On May 29, 2009, the Corps awarded the Biolab Project Contract to Grimberg. Grimberg proceeded on the contract and, once it began work on the foundation, quickly began to encounter incompetent rock. On March 10, 2010, Grim- berg notified the Corps that it was encountering, in its view, a DSC. Grimberg ultimately drilled through 923 feet of rock—683 feet more than it had accounted for in its bid. J.A. 3435. In May 2012, once the Biolab project was complete, Grimberg submitted a request for equitable adjustment of the contract price to the Corps, alleging a Type I DSC. J.A. 3449–3452. The request acknowledged that Grimberg re- lied on only DH-11 and DH-12 when structuring its bid. J.A. 3450. The letter further stated that Grimberg drilled through an average of 13.6 feet more rock per pier than ex- pected to create the necessary rock sockets. J.A. 3451. The Corps denied Grimberg’s request in June 2012. In Decem- ber, Grimberg submitted a certified claim. The Corps again denied the claim and Grimberg appealed to the Board. The Board conducted an eight-day hearing and issued a lengthy opinion. Relevant to this appeal, the Board found that Grimberg encountered a Type I DSC. The Board ex- plained that Grimberg met the standard for a Type I DSC because “[t]he quantities of rock encountered greatly ex- ceeded the quantity reasonably foreseeable based on a fair reading of contractual indications.” J.A. 28. The Board found that Grimberg’s reliance on just two borings, DH-11 and DH-12, was unreasonable. J.A. 28–29; see also J.A. 31 (“Confronted with the plethora of cautionary contractual indications, ‘cherry picking’ a subset of 2 of 46 borings, re- gardless of their proximity to the Biolab foundation, was unjustifiable in the circumstances of this case.”). The Case: 19-1608 Document: 59 Page: 5 Filed: 06/09/2020

U.S. ARMY CORPS OF ENG’RS v. JOHN C. GRIMBERG CO. 5

Board explained, however, that Grimberg’s reliance on two borings was more reasonable than the government’s pro- posal that Grimberg should have relied on borings located 300 to 500 feet from the Biolab footprint. J.A. 29. The Board explained: a primary reason for our conclusion that [Grim- berg] is entitled to relief despite its misreliance solely on DH-11 and DH-12, is the gross disparity between the quantities of incompetent rock actu- ally encountered and the quantity that we consider was reasonably indicated in the contract’s Geotech- nical Report. Even if it had expanded its pre-pro- posal analyses to include the seven most proximate borings to the Biolab site . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stuyvesant Dredging Company v. The United States
834 F.2d 1576 (Federal Circuit, 1987)
H.B. Mac, Inc. v. United States
153 F.3d 1338 (Federal Circuit, 1998)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Rockies Express Pipeline LLC v. Interior
730 F.3d 1330 (Federal Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
U.S. Army Corps of Engineers v. John C. Grimberg Co., Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-army-corps-of-engineers-v-john-c-grimberg-co-inc-cafc-2020.